    Ithaca Commons Repair & Upgrade Project C#2 Utilities, C#3A Surface, C#3B Electric

    Date Start End Next Date Next Time Prepared By05/13/2014 10:00 AM 11:00 AM 05/20/2014 10:00 AM Jessica Buckley

    Purpose Location

    2014 Construction Meeting #7 Commons Project Office215 East State St Ithaca, NY

    Distribution/Attendance: (Present at meeting unless noted: Aabsent)

    City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason

    Downtown Ithaca Alliance Tammy Baker

    Sasaki Associates Susannah Ross (A), Eamonn Hutton (A)

    Labella Associates Dan Walker, James Matzat (A)

    Vacri Construction / ACP Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis (A),

    Bob Belavigna - ACP

    Power & Construction Group Lou Zupan, Bill Planert, Brian Planert

    Verizon James Edwards, Dave Comer (A)

    NYSEG Gas Doug Stafford (A), Jack Barker, Dawn Stillwell (A)

    DDS Jeff Bubb (A)

    NYSEG Electric Jack Czapranski, Dennis Kuhn (A)

    Item / Description Notes Due

    1. RFIs

    1.1.

    Any open RFIs at this time

    2.

    SUBMITTALS

    2.1.

    Vacri report on: TTC alley HH (needed this

    week); WF vault; Granite & steel shop

    drawings; BM Pavilion shop drawings

    Gateway anchors submitted; granite

    submittals to be sent to architect; Sasaki /

    EP to issue revised footer for BMP; Sasaki

    to issue sketch of WF footprint; Home

    Dairy storm structure CB 2.T is submittal

    #30 R3 (lead time = 1.5-2 wks)

    2.2.

    P&CG report on: Stage lighting; Kiosks HH to be submitted this week; Concrete

    HH available through Oldcastle; Lighting

    package to be submitted this week;

    3.

    OPEN DESIGN ITEMS

    3.1.

    Water Feature Design pending approval

    of health department

    WF vault sanitary lateral is on hold

    pending Ithaca water treatment facility /

    health department approval

    4.

    SCHEDULE

    4.1.

    P&CG to schedule 1-2 additional crews

    05/12: Start NW & SW end of E State;

    Working w/ NYSEG Electric at N Tioga &

    NE side of E State St

    P&CG to work in Bank Alley; Vacri plans to

    remove wall around yellow woods;

    MEETING MINUTES

  • 8/10/2019 2014-05-13 Construction Meeting Minutes.pdf

    2/3

    Page 2of 3

    05/1906/16: Complete N Tioga

    4.2.

    NYSEG Electric to complete relocation of

    secondary to Aurora St by 05/16

    NYSEFG Electric crew only scheduled for 1

    week

    4.3.

    Vacri / AC&P

    May: Complete utilities; Verizon MH entry

    June: Site demo; Pour foundations /footers; Site grading, curbs, expansion

    joints

    July: Prep & pour slab N Tioga; Paving

    program

    C#2 work remaining: Storm for Alleys & at

    Seneca St; DW to review bump out at

    Seneca St

    4.4.

    NYSEG Gas Priorities:

    A.

    Make connection at Aurora St

    B.

    Test, charge main and run service to

    bldg north branch between Aurora &

    Trolley Circle

    C.

    Provide new service to 215 E State St

    prior to July

    Cap midpoint of gas main at North side

    Trolley Circle; Valve boxes are to

    straightened; NYSEG is to use item 4 to

    restore sidewalk;

    5.

    UTILITIES COORDINATION

    5.1.

    Verizon / Gas Conflicts E State St:P&CG

    to report on # of Verizon conflicts with

    cat. poles

    P&CG to submit lighting package to drive

    retirement of gas main; BP to report on

    light pole/ Verizon DB conflicts , City to

    respond

    5.2.

    Water Feature Rough In: Verizon

    scheduled to start work lowering DB

    05/19; Vacri to submit on WF vault as

    specd

    Revised price estimate pending revised

    submittal; City & Engineer to review knock

    out vault submittal

    5.3.

    TTC Alley/Telecom: 05/12:EE Root is to

    expose TTC conduits to allow for the

    installation of the TTC HH and stormlateral by Vacri; Verizon is to be

    scheduled to expose cables in alley to

    allow installation of storm lateral

    TTC HH to arrive on site 05/20; Verizon to

    be scheduled for end of this week, early

    next week; EE Root to be scheduled 05/21to finish alley and connection to E state St;

    Schedule switch over for TTC 05/02.

    5.4.

    Telecom Entry to Verizon MHs:Vacri

    finished Cayuga St; Aurora & Seneca St to

    be scheduled

    Seneca St entry pending 05/20, Vacri to

    schedule w/ Verizon & City; AB to submit

    Seneca St plan, MK to confirm schedule of

    05/19 with city

    5.5. Asphalt Restoration: Vacri, NYSEG Gas &

    Signals project (PC&G) to coordinatein

    intersections

    Trolley circle & bank alley to temp asphalt

    to be done05/16

    6.

    VAULTS6.1.

    Vault Infill208/210 to be filled by 8 AM

    05/13; 123 infill to be complete by 05/21;

    Other possible vault infills at 118, 119,

    135,137,139; Vacri to submit price

    estimate on infill at 126 & 208/210

    Vacris cost breakdown pending material

    invoice; 126 to be backfilled 05/14; 119 &

    118 pending, not likely

    7.

    ELECTRIC

    7.1.

    Grading plan available for surveyor Vacri & P&CG surveyors to coordinate

  • 8/10/2019 2014-05-13 Construction Meeting Minutes.pdf

    3/3

    Page 3of 3

    grading plan

    7.2.

    Electric feed from panel west HH exposed

    on fence hook east of 158 E State St

    8.

    TELECOM DUCT BANK

    8.1.

    Bank Alley west walkway to be closed

    week of 05/12; TTC east entrance toremain open until 05/14

    9.

    M&PTP: MAINTENANCE & PROTECTION

    OF TRAFFIC & PEDESTRIANS

    9.1.

    All trenches need to be prepared for

    graduation weekend; GasAt least item

    4; Vacriasphalt; PC&GBeautiful

    concrete / plate combo

    DDS to confirm use of item 4 in trenches

    9.2.

    Vacri is to power off the electric during

    the day, and on at the end of the day; Any

    variation is to be communicated to

    JB/MK, AB, LZ, Andy (Gas)

    Lock out tag out procedures are to be put

    in place on electric panel; DDS is to have

    electrician disconnect / reconnect at end

    of day;

    9.3.

    PERSONAL VEHICLES ARE PROHIBITED

    FROM PARKING ON SITE

    9.4.

    Flaggers are required to bring trucks on &

    off site, especially when backing up

    9.5.

    Pedestrian walkways are to be reinstated

    at the end of each day; Only one crossing

    may be closed at a time; If more than one

    is to be closed a temporary crossing is to

    be opened

    9.6.

    The mural fence may be disassembled to

    allow work, however must be reinstated

    at the end of each day9.7.

    Vacri to propose sidewalk demo plan

    DATES TO REMEMBER

    May 16 to May 18Ithaca College Graduation, no work on weekend

    May 23 to May 25Cornell Graduation, no work on weekend

    May 30 to June 1Ithacafest, Cayuga St entrance closed

    ADDITIONAL NOTES

    City to request waterproofing detail from Architect / Engineer for #158 & #202; ACP to submit

    cost breakdown

    Vacri critical path item: Sasaki to issue WF rough in, needed for SD / TD Slot