2014-05-13 construction meeting minutes.pdf
TRANSCRIPT
-
8/10/2019 2014-05-13 Construction Meeting Minutes.pdf
1/3
Page 1of 3
Ithaca Commons Repair & Upgrade Project C#2 Utilities, C#3A Surface, C#3B Electric
Date Start End Next Date Next Time Prepared By05/13/2014 10:00 AM 11:00 AM 05/20/2014 10:00 AM Jessica Buckley
Purpose Location
2014 Construction Meeting #7 Commons Project Office215 East State St Ithaca, NY
Distribution/Attendance: (Present at meeting unless noted: Aabsent)
City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason
Downtown Ithaca Alliance Tammy Baker
Sasaki Associates Susannah Ross (A), Eamonn Hutton (A)
Labella Associates Dan Walker, James Matzat (A)
Vacri Construction / ACP Ralph Avery, Andy Breznay, Matt Thomas(A), Roberto DeVincentis (A),
Bob Belavigna - ACP
Power & Construction Group Lou Zupan, Bill Planert, Brian Planert
Verizon James Edwards, Dave Comer (A)
NYSEG Gas Doug Stafford (A), Jack Barker, Dawn Stillwell (A)
DDS Jeff Bubb (A)
NYSEG Electric Jack Czapranski, Dennis Kuhn (A)
Item / Description Notes Due
1. RFIs
1.1.
Any open RFIs at this time
2.
SUBMITTALS
2.1.
Vacri report on: TTC alley HH (needed this
week); WF vault; Granite & steel shop
drawings; BM Pavilion shop drawings
Gateway anchors submitted; granite
submittals to be sent to architect; Sasaki /
EP to issue revised footer for BMP; Sasaki
to issue sketch of WF footprint; Home
Dairy storm structure CB 2.T is submittal
#30 R3 (lead time = 1.5-2 wks)
2.2.
P&CG report on: Stage lighting; Kiosks HH to be submitted this week; Concrete
HH available through Oldcastle; Lighting
package to be submitted this week;
3.
OPEN DESIGN ITEMS
3.1.
Water Feature Design pending approval
of health department
WF vault sanitary lateral is on hold
pending Ithaca water treatment facility /
health department approval
4.
SCHEDULE
4.1.
P&CG to schedule 1-2 additional crews
05/12: Start NW & SW end of E State;
Working w/ NYSEG Electric at N Tioga &
NE side of E State St
P&CG to work in Bank Alley; Vacri plans to
remove wall around yellow woods;
MEETING MINUTES
-
8/10/2019 2014-05-13 Construction Meeting Minutes.pdf
2/3
Page 2of 3
05/1906/16: Complete N Tioga
4.2.
NYSEG Electric to complete relocation of
secondary to Aurora St by 05/16
NYSEFG Electric crew only scheduled for 1
week
4.3.
Vacri / AC&P
May: Complete utilities; Verizon MH entry
June: Site demo; Pour foundations /footers; Site grading, curbs, expansion
joints
July: Prep & pour slab N Tioga; Paving
program
C#2 work remaining: Storm for Alleys & at
Seneca St; DW to review bump out at
Seneca St
4.4.
NYSEG Gas Priorities:
A.
Make connection at Aurora St
B.
Test, charge main and run service to
bldg north branch between Aurora &
Trolley Circle
C.
Provide new service to 215 E State St
prior to July
Cap midpoint of gas main at North side
Trolley Circle; Valve boxes are to
straightened; NYSEG is to use item 4 to
restore sidewalk;
5.
UTILITIES COORDINATION
5.1.
Verizon / Gas Conflicts E State St:P&CG
to report on # of Verizon conflicts with
cat. poles
P&CG to submit lighting package to drive
retirement of gas main; BP to report on
light pole/ Verizon DB conflicts , City to
respond
5.2.
Water Feature Rough In: Verizon
scheduled to start work lowering DB
05/19; Vacri to submit on WF vault as
specd
Revised price estimate pending revised
submittal; City & Engineer to review knock
out vault submittal
5.3.
TTC Alley/Telecom: 05/12:EE Root is to
expose TTC conduits to allow for the
installation of the TTC HH and stormlateral by Vacri; Verizon is to be
scheduled to expose cables in alley to
allow installation of storm lateral
TTC HH to arrive on site 05/20; Verizon to
be scheduled for end of this week, early
next week; EE Root to be scheduled 05/21to finish alley and connection to E state St;
Schedule switch over for TTC 05/02.
5.4.
Telecom Entry to Verizon MHs:Vacri
finished Cayuga St; Aurora & Seneca St to
be scheduled
Seneca St entry pending 05/20, Vacri to
schedule w/ Verizon & City; AB to submit
Seneca St plan, MK to confirm schedule of
05/19 with city
5.5. Asphalt Restoration: Vacri, NYSEG Gas &
Signals project (PC&G) to coordinatein
intersections
Trolley circle & bank alley to temp asphalt
to be done05/16
6.
VAULTS6.1.
Vault Infill208/210 to be filled by 8 AM
05/13; 123 infill to be complete by 05/21;
Other possible vault infills at 118, 119,
135,137,139; Vacri to submit price
estimate on infill at 126 & 208/210
Vacris cost breakdown pending material
invoice; 126 to be backfilled 05/14; 119 &
118 pending, not likely
7.
ELECTRIC
7.1.
Grading plan available for surveyor Vacri & P&CG surveyors to coordinate
-
8/10/2019 2014-05-13 Construction Meeting Minutes.pdf
3/3
Page 3of 3
grading plan
7.2.
Electric feed from panel west HH exposed
on fence hook east of 158 E State St
8.
TELECOM DUCT BANK
8.1.
Bank Alley west walkway to be closed
week of 05/12; TTC east entrance toremain open until 05/14
9.
M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
9.1.
All trenches need to be prepared for
graduation weekend; GasAt least item
4; Vacriasphalt; PC&GBeautiful
concrete / plate combo
DDS to confirm use of item 4 in trenches
9.2.
Vacri is to power off the electric during
the day, and on at the end of the day; Any
variation is to be communicated to
JB/MK, AB, LZ, Andy (Gas)
Lock out tag out procedures are to be put
in place on electric panel; DDS is to have
electrician disconnect / reconnect at end
of day;
9.3.
PERSONAL VEHICLES ARE PROHIBITED
FROM PARKING ON SITE
9.4.
Flaggers are required to bring trucks on &
off site, especially when backing up
9.5.
Pedestrian walkways are to be reinstated
at the end of each day; Only one crossing
may be closed at a time; If more than one
is to be closed a temporary crossing is to
be opened
9.6.
The mural fence may be disassembled to
allow work, however must be reinstated
at the end of each day9.7.
Vacri to propose sidewalk demo plan
DATES TO REMEMBER
May 16 to May 18Ithaca College Graduation, no work on weekend
May 23 to May 25Cornell Graduation, no work on weekend
May 30 to June 1Ithacafest, Cayuga St entrance closed
ADDITIONAL NOTES
City to request waterproofing detail from Architect / Engineer for #158 & #202; ACP to submit
cost breakdown
Vacri critical path item: Sasaki to issue WF rough in, needed for SD / TD Slot