2013 southeast district meeting
DESCRIPTION
2013 Southeast District Meeting. Hartsfield - Jackson Atlanta International Airport. Jordan Gray Jeff Hadden Savannah Harvey Robert Plank Sean Shahidpour Hampton Vann. Role Breakdown. Scope of Work. Initially erect batching plants on site as well as equipment and material stockpiling - PowerPoint PPT PresentationTRANSCRIPT
2013 Southeast District Meeting
Jordan GrayJeff Hadden
Savannah HarveyRobert Plank
Sean ShahidpourHampton Vann
Hartsfield- Jackson Atlanta International Airport
3
2012 AGC/ASC Heavy Civil | 1Kiewit
Role Breakdown
President
Vice President
CFO Hampton Vann Chief Estimator
Sean Shahidpour Chief Superintendent
Jordan Gray Jeff Hadden Project Managers
Accountant Superintendent
Robert Plank
Safety Director Estimator
Savannah Harvey
Site Administrator
2012 AGC/ASC Heavy Civil | 1Kiewit
Scope of Work
• Initially erect batching plants on site as well as equipment and material stockpiling
• Concrete cutting of 10,000’ x 150’ of runway as well as pavement demolition and removal of the runway and taxiways
• Installation of drainage piping, rebar, and electrical conduit• Repave runway, taxiways, and miscellaneous slabs• Construction will begin 60 days prior to November 6
4
2012 AGC/ASC Heavy Civil | 1Kiewit
Preliminary Breakdown of Work Performed
5
• Phase 1-60 days Prior to Closure• Major Items• Erection of Batch Planks• Materials and Equipment Stockpile • Haul Road Construction• Preliminary saw cutting• Miscellaneous slab replacement and small repairs (as directed by engineer)• Electrical Contractor on-site for conduit and light placement• Phase IA• Can be completed any time during Phase 1• Includes removal and replacement of 18 concrete panels ( 25’x25’)• Phase II- 45 days beginning with closure of runway 8R• Demo left and right sections• Active taxiway C,D,H• Work on taxiway H, E3, E1, E5, E11, E13, E, B, B2, B4, B6, B10 must be 100% completed, included striping and
electrical work, before Phase 3can begin. • Phase II A& B- a 15 day calendar period follows Phase III• Active Aircraft routes are taxiways H, E1 to B2 and E to B during Phase III• Work on taxiway H, E1, B2, E and E to B are to be 100% complete before Phase III can begin• Paving 1500ft of runway• All taxiways excluding C and D completed during Phase III
2012 AGC/ASC Heavy Civil | 1Kiewit
Safety and Risk Concerns
• Debris must be contained to not enter working areas as well as jet engines
• Security Crews, Gates, Fences and Badges for Employees• PPE, OHSA• Flagging for airport traffic• Coordination with airport officials at all times
6
2013 Southeast District Meeting