2010 Update Highway Capacity Manual

ARC’s Multi-modal LOS Analysis

Highway Capacity ManualHighway Capacity Manual…a Level Playing Field…

Bruce W. Landis, P.E., AICPVice President

Sprinkle Consulting, Inc.

Page 2: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• “First Down” Measures

• MMLOS Players & Referees

– MPOs, ARC and a State DOT

– NCHRP

– TRB’s HC & QS Committee

• The Playbook: Contents of the Highway Capacity

Manual Update

• Playing in the Game

The Game Plan…

Page 3: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

What gets “measured” gets “done”…What gets “measured” gets “done”…• Artifacts provide the evidence:

– Highway Capacity Manual– Federal Reporting by States (HPMS, etc.)– AASHTO (Roadway Geometric Design)

Manuals– Congestion Measures

Page 4: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

A New Game….

• Complete Streets

• Livability

• Sustainable “Whatever”

• Economically-Efficient Corridors

• More to Come….

Page 5: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Reliable Measures

• Fuel Savings

• Emissions / GHG

• Health Savings

• Economic Effects

• Motor Vehicle LOS

• Bicycling LOS

• Pedestrian LOS

• Transit LOS

Page 6: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• “First Down” Measures – how progress is marked

• MMLOS Players & Referees

– MPOs, ARC and a State DOT

– NCHRP

– TRB’s HC & QS Committee

• The Playbook: Contents of the Highway Capacity

Manual Update

• Playing in the Game

The Game Plan…

Page 7: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• Multi-modal LOS for Arterials

• Evaluated Bicycling & Walking Conditions Methods

• Established the Best Measures / Models

• Acknowledged Superiority of Bike/Ped Measures’

Approach to the Traditional MV LOS

• Tested then Intertwined all Modes’ Methods

• Created First Inter-translation QOS/LOS

• Established Simultaneous Reporting

National Cooperative Highway Research Program NCHRP 3-70

Page 8: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Nationwide Testing & Surveying

Page 9: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Metro Atlanta NCHRP 3-70 Test Corridors

Page 10: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• Auburn Avenue (Jesse Hill, Jr. Dr. to Peachtree St.)

• 17th Street (Northside Dr. to Market St.)

• Bullsboro Drive (Amlajack Blvd. to Greison Tr.)

• Buford Highway (Druid Hills Rd. to Clairmont Rd.)

• Cobb Parkway (Frey’s Gin Rd. to Allgood Rd.)

Metro Atlanta NCHRP 3-70 Test Corridors

Page 11: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

National Cooperative Highway Research Program NCHRP 3-92• Update of the HCM• Incorporate NCHRP reports, reliable

peer-and agency-reviewed methods• Places Bike, Ped, Transit QOS/LOS

measures on par with MV measures• Acknowledges the “new” approach of

asking “customers” for performance measures

Page 12: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• “First Down” Measures – how progress is marked

• MMLOS Players & Referees

– MPOs, ARC and a State DOT

– NCHRP

– TRB’s HC & QS Committee

• The Playbook: Contents of the Highway Capacity

Manual Update

• Playing in the Game

The Game Plan…

Page 13: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

(Chapters 16 & 17 - “Complete Streets LOS”)

New Highway Capacity Manual

Page 14: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

CompleteStreetsLOSFDOT’s Quality / Level of Service Handbook 2002 (and 2009 update)

Page 15: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Highway System Structure

• Points

• Segments

• Facilities

• Corridors

• Areas

Page 16: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Arterial Bicycle LOS Model

Bicycle LOS = a1(Seg) + a2(exp(Int)) + a3(Cflt)Where

Seg = length weighted avg. Segment Bicycle LOS Model

exp = exponential function

Int = average Intersection Bicycle LOS Model

Cflt = number of conflicts per mile (e.g., driveways, unsig. Int.)

a1, a2, a3 = coefficients

Page 17: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

SegmentSegment Bicycle LOSBicycle LOS ModelModel

Seg = 0.507 Ln (Seg = 0.507 Ln (V/(4*PHF*LV/(4*PHF*L)) + 0.199SP)) + 0.199SPtt*(1+10.38*(1+10.38HVHV))22 + +

7.066(1/7.066(1/PCPC))22-0.005(-0.005(WWee))22+ 0.760+ 0.760

Page 18: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Ln = natural log

PHF = Peak Hour Factor

L = total number of directional through lanes

V = Directional motorized vehicle volume (V>4*PHF*L)

SPt = Effective speed factor = 1.1199ln(S-20)+0.8103

S= Average running speed of motor vehicles (mph)

HV = Proportion Heavy Vehicles

PC = FHWA’s five point pavement service rating conditions

We = Average effective width of the outside through lane

Seg = Seg = 0.507 Ln (VV/(/(44**PHFPHF**LL))) + + 0.1990.199SPSPtt**(1+10.38(1+10.38HVHV))22 + +

7.066(7.066(1/1/PCPC))2 2 - - 0.0050.005((WWee))22+ + 0.7600.760

Page 19: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Effective Pavement Width Effects….

Page 20: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

MV Volume Effects….

Page 21: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Pavement Condition Effects….

Page 22: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Ln = natural log

PHF = Peak Hour Factor

L = total number of directional through lanes

V = Directional motorized vehicle volume (V>4*PHF*L)

SPt = Effective speed factor = 1.1199ln(S-20)+0.8103

S= Average running speed of motor vehicles (mph)

HV = Proportion Heavy Vehicles

PC = FHWA’s five point pavement service rating conditions

We = Average effective width of the outside through lane

Seg = Seg = 0.507 Ln (VV/(/(44**PHFPHF**LL))) + + 0.1990.199SPt*SPt*(1+10.38(1+10.38HVHV))22 + +

7.066(7.066(1/1/PCPC))2 2 - - 0.0050.005((WWee))22+ + 0.7600.760

Page 23: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Arterial Bicycle LOS Model

Bicycle LOS = a1(Seg) + a2(exp(Int)) + a3(Cflt)

Where

Seg = length weighted avg. Segment Bicycle LOS Model

exp = exponential function

Int = average Intersection Bicycle LOS ModelCflt = number of conflicts per mile (e.g., driveways, unsig. Int.)

a1, a2, a3 = coefficients

Page 24: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

IntersectionIntersection Bicycle LOSBicycle LOS

IntBLOS = IntBLOS = - 0.2144 - 0.2144 WWtt

+ 0.0153 + 0.0153 CDCD

+ 0.0066 + 0.0066 (V(Volol1515 / / LL))

+ 4.1324 + 4.1324

Wt = total width of outside through lane and shoulder /

bike lane (if present)CD = crossing distance, the width of the side street

(including auxiliary lanes and median)Vol15 = volume of directional traffic during a 15-minute time

periodL = total number of through lanes on the approach to the

intersection

Page 25: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

IntBLOS = - IntBLOS = - 0.21440.2144WWtt + + 0.01530.0153CDCD + + 0.0066 (0.0066 (VVolol1515//LL))

+ 4.1324 + 4.1324

CDCD

Page 26: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Arterial Bicycle LOS Model

Bicycle LOS = a1(Seg) + a2(exp(Int)) + a3(Cflt)Where

Seg = length weighted avg. Segment Bicycle LOS Model

exp = exponential function

Int = average Intersection Bicycle LOS Model

Cflt = number of conflicts per mile (e.g., driveways, unsig. Int.)

a1, a2, a3 = coefficients

Page 27: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Pedestrian LOS ModelPedestrian LOS Model

Overall LOS Model:

= Worse of (Density LOS, Roadway Environ.LOS)

Density LOS = letter grade of LOS for “crowding” density of sidewalks, walkways and street corners

Roadway-Ped LOS = letter grade of LOS for urban street based on ped. safety / comfort factors reflecting interaction with motor vehicles

Photo by SCI

Page 28: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

From Chapter 18 of the 2000 HCM

LOS Min. Ped Space per Person (SF)

Equivalent Max Flow Rate per Unit Width of Sidewalk

(peds/hr/ft)

A > 60 ≤ 300

B >40 ≤ 420

C >24 ≤ 600

D >15 ≤ 900

E >8 ≤ 1380

F ≤ 8 >1380

Pedestrian Density LOS ModelPedestrian Density LOS Model

Page 29: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Pedestrian LOS ModelPedestrian LOS Model

Two Roadway Environment models…modified by…

PedLOS = (a1PSegmentSegment + a2PInt Int +c) (RCDFRCDF)

PSeg = Segment Pedestrian LOS value

PInt = Intersection Pedestrian LOS value

RCDF = Roadway Crossing Difficulty Factor

a1, a2 = coefficients

c = constant

Page 30: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Segment Pedestrian LOS

Seg LOS = -1.2276 ln (Wt + fp x %OSP + fb x Wb + fsw x Ws) +

0.0091(Vol15/L) + 0.0004 SPD2 + 6.0468 Where:

Ped Seg LOS = Pedestrian level of service score for a segment ln = Natural log Wt = Width of outside lane plus shoulder / bike lane fp = On-street parking effect coefficient (= 0.20)

%OSP = Percent of segment with on-street parking fb = Buffer area coefficient (= 5.37 for trees spaced 20 feet on center)

Wb = Buffer width (distance between edge of pavement and sidewalk, in feet)

fsw = Sidewalk presence coefficient (= 6 - 0.3Ws) Ws = Width of sidewalk Vol15 = Volume of motorized vehicles in the peak 15 minute period L = Total number of directional through lanes SPD = Average running speed of motorized vehicle traffic (mi/h)

Page 31: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Segment Pedestrian LOS

Seg LOS = -1.2276 ln (Wt + fp x %OSP + fb x Wb + fsw x Ws) +

0.0091(Vol15/L) + 0.0004 SPD2 + 6.0468 Where:

Ped Seg LOSS = Pedestrian level of service score for a segment ln = Natural log Wt = Width of outside lane plus shoulder / bike lane fp = On-street parking effect coefficient (= 0.20) %OSP = Percent of segment with on-street parking fb = Buffer area coefficient (= 5.37 for trees spaced 20 feet on center) Wb = Buffer width (distance between edge of pavement and sidewalk, in feet) fsw = Sidewalk presence coefficient (= 6 - 0.3Ws) Ws = Width of sidewalk Vol15 = Volume of motorized vehicles in the peak 15 minute period L = Total number of directional through lanes SPD = Average running speed of motorized vehicle traffic (mi/h)

Page 32: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Segment Pedestrian LOS

Seg LOS = -1.2276 ln (Wt + fp x %OSP + fb x Wb + fsw x Ws) +

0.0091(Vol15/L) + 0.0004 SPD2 + 6.0468 Where:

Ped Seg LOSS = Pedestrian level of service score for a segment ln = Natural log Wt = Width of outside lane plus shoulder / bike lane fp = On-street parking effect coefficient (= 0.20) %OSP = Percent of segment with on-street parking fb = Buffer area coefficient (= 5.37 for trees spaced 20 feet on center) Wb = Buffer width (distance between edge of pavement and sidewalk, in feet) fsw = Sidewalk presence coefficient (= 6 - 0.3Ws) Ws = Width of sidewalk Vol15 = Volume of motorized vehicles in the peak 15 minute period L = Total number of directional through lanes SPD = Average running speed of motorized vehicle traffic (mi/h)

Page 33: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Pedestrian LOS ModelPedestrian LOS Model

Two Roadway Environment models…modified by…

PedLOS = (a1PSegment + a2PInt Int +c) (RCDF)

PSeg = Segment Pedestrian LOS value

PInt = Intersection Pedestrian LOS value

RCDF = Roadway Crossing Difficulty Factor

a1, a2 = coefficients

c = constant

Page 34: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Intersection Pedestrian LOS

Ped Int LOS (Signal) = 0.00569 (RTOR+PermLefts) + 0.00013 (crossingTrafVol x

TrafSpeed) + 0.0681 (# LanesCrossed 0.514) + 0.0401ln(PedDelay) – RTCI

(0.0027PerpTrafVol – 0.1946) + 1.7806 WhereRTOR+PermLefts = right-turn-on-red vehicles plus number of motorists making a permitted left turn in a 15 minute period PerpTrafVol*PerpTrafSpeed = Product of the traffic in the outside through lane of the street being crossed and the midblock 85th percentile speed of traffic on the street being crossed in a 15 minute period

LanesCrossed = The number of lanes being crossed by the pedestrian PedDelay = Average number of seconds the pedestrian is delayed before being able to cross the intersection

RTCI = Number of right turn chanmelization islands on the crossing.

Page 35: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Pedestrian LOS ModelPedestrian LOS Model

Two Roadway Environment models …modified by…

PedLOS = (a1PSegment + a2PInt +c) (RCDFRCDF)

PSeg = Segment Pedestrian LOS value

PInt = Intersection Pedestrian LOS value

RCDF = Roadway Crossing Difficulty Factor

a1, a2 = coefficients

c = constant

Page 36: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Roadway Crossing

Difficulty Factor

RCDF = Max[0.80, Min{[(XLOS#-NXLOS#)/7.5 + 1.00],1.20}]

Where

RCDF = Roadway crossing difficulty factor

XLOS# = Roadway crossing difficulty LOS Number

NXLOS# = Non-crossing Pedestrian LOS number

= (0.318 PSeg + 0.220 PInt + 1.606)

Pseg = Ped. Segment LOS number (computed per equation #20)

Pint = Ped. Intersection LOS number (computed per equation #21)

Page 37: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Divert to Signal LOS

Total Ped Deviation Delay =

Ped Geometric Delay + Ped Control Delay

Where,Ped Geometric Delay = 2/3*(block length)/ped walking speed

Ped Contol Delay = (cycle length – green time)2/(2*cycle length)

Covert to numerical LOS per HCM methodology for wait delay

Page 38: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Pedestrian LOS ModelPedestrian LOS Model

Two Roadway Environment models…modified by…

PedLOS = (a1PSegmentSegment + a2PInt Int +c) (RCDFRCDF)

PSeg = Segment Pedestrian LOS value

PInt = Intersection Pedestrian LOS value

RCDF = Roadway Crossing Difficulty Factor

a1, a2 = coefficients

c = constant

Page 39: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

What Affects TransitTransit Riders?

• Frequency of Service

• Speed of (Vehicle) Travel

• Passenger Load

• On-time Reliability

• Pedestrian Access

• Bus StopAmenities

Page 40: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

National Guidance

Page 41: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

NCHRP 3-70 Transit LOS (Urban Arterial

Corridor) Model

Transit LOS = 6.0 - 1.50 x Wait-RideScore

+ 0.15 x PedLOSarterial

Level of Service Score

A ≤ 2.0

B > 2.0 and ≤ 2.75

C > 2.75 and ≤ 3.5

D > 3.5 and ≤ 4.25

E > 4.25 and ≤ 5.0

F > 5.0

•TCRP Report 95•TCRP Project A-23A•National Transit Database•TRL Report 593

Page 42: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• “First Down” Measures – how progress is marked

• MMLOS Players & Referees

– MPOs, ARC and a State DOT

– NCHRP

– TRB’s HC & QS Committee

• The Playbook: Contents of the Highway Capacity

Manual Update

• Playing in the Game

The Game Plan…

Page 43: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

(Chapters 16 & 17 - “Complete Streets LOS”)

New Highway Capacity Manual

Page 44: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Reliable Measures

• Fuel Savings

• Emissions / GHG

• Health Savings

• Economic Effects

• Motor Vehicle LOS

• Bicycling LOS

• Pedestrian LOS

• Transit LOS

Page 45: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Page 46: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Report Output for Corridor Investments

Societal benefits:

• Fuel Savings

• CO2 Emissions Savings

• Health Cost Savings

Page 47: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

• ARC, Cobb & Fulton Counties

• NCHRP Report 616http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_616.pdf

• FDOT’s Q/LOS Handbookhttp://www.dot.state.fl.us/planning/systems/sm/los/pdfs

• www.sprinkleconsulting.com

• 888 - 462 - 3514 Peyton McLeod or Bruce Landis

• Upcoming Highway Capacity Manual

Your Resources…

Page 48: 2010 Update Highway Capacity Manual Highway Capacity Manual ARC’s Multi-modal LOS Analysis Highway Capacity Manual …a Level Playing Field… Bruce W. Landis,

2010 Update Highway Capacity Manual

Bruce W. Landis, P.E., AICPVice President

Sprinkle Consulting, Inc.

[email protected]