North View of VC Glass in Exterior Windows W e e k l y R e p o r t : 5 / 3 1 / 1 0 - 6 / 4 / 1 0 North View of HQ Elevator Shaft at VCMEPRough-IninExhibitArea Scaffold at VC Exterior ColumnsTRANSCRIPT
![Page 1: 2010-06-04](https://reader036.vdocuments.mx/reader036/viewer/2022082901/568c0d551a28ab955a8c51d5/html5/thumbnails/1.jpg)
• Erect scaffolding at exterior columns at VC.
• Damproofing the exterior of the HQ is 95% complete.
• Installing stone at the main entrance to the HQ 80% complete.
• MEP rough-in in the exhibit areas of the VC is ongoing.
• Metal panel installation at the eyebrow is complete on the south side and 65% complete on the re-
mainder of the HQ.
• Caulking windows and installing trim caps on the southeast side of the HQ.
• Installing vanity supports at the toilet rooms.
• Started damproofing the exterior walls on the VC
• Framing and sheathing exterior walls at the VC is 90% complete.
• Continue to one side walls throughout the HQ.
Texas A&M University Agriculture Headquarters
Week ly Repor t : 5 /31 /10 -6 /4 / 10
North View of VC Glass in Exterior Windows
North View of HQ Elevator Shaft at VC MEP Rough-In in Exhibit Area
Scaffold at VC Exterior Columns
![Page 2: 2010-06-04](https://reader036.vdocuments.mx/reader036/viewer/2022082901/568c0d551a28ab955a8c51d5/html5/thumbnails/2.jpg)