Installed the 40,000 gallon cistern tank on Wednesday 1/13/10. Set the Energy Recovery Units on the roof on 1/12/10. Completed stair 1 at the HQ. Placed the low roof at the VC on Tuesday 1/12/10. The installation of the west and east buck hoist is about 90% complete. Started framing and forming for the upper roof at the VC. Pouring the 37ft columns at the VC is ongoing. Started hanging the steel for stair 3 at the east end of the HQ. All the Air Handling Units will be delivered and placed on the HQ by the end of next week. Formed and poured the south entry stoop at the HQ Will place concrete pans at stair 2 beginning next week. Started putting sheetrock on interior partitions. MEP above ceiling rough-in is continuing up the building with the 1st floor nearly complete. Texas A&M University Agriculture Headquarters Weekly Report: 1/11/10-1/15/10 West View of VC Sheetrock on 1st Floor HQ North View of HQ Buck Hoist Cistern Tank Delivery Setting ERU on HQ Roof

Upload: texas-am-agrilife

Post on 09-Mar-2016

215 views

Category:

Documents


0 download

DESCRIPTION

• Formed and poured the south entry stoop at the HQ • All the Air Handling Units will be delivered and placed on the HQ by the end of next week. • Started framing and forming for the upper roof at the VC. • Pouring the 37ft columns at the VC is ongoing. • Set the Energy Recovery Units on the roof on 1/12/10. • The installation of the west and east buck hoist is about 90% complete. • Placed the low roof at the VC on Tuesday 1/12/10. • Completed stair 1 at the HQ.

TRANSCRIPT

• Installed the 40,000 gallon cistern tank on Wednesday 1/13/10.

• Set the Energy Recovery Units on the roof on 1/12/10.

• Completed stair 1 at the HQ.

• Placed the low roof at the VC on Tuesday 1/12/10.

• The installation of the west and east buck hoist is about 90% complete.

• Started framing and forming for the upper roof at the VC.

• Pouring the 37ft columns at the VC is ongoing.

• Started hanging the steel for stair 3 at the east end of the HQ.

• All the Air Handling Units will be delivered and placed on the HQ by the end of next week.

• Formed and poured the south entry stoop at the HQ

• Will place concrete pans at stair 2 beginning next week.

• Started putting sheetrock on interior partitions.

• MEP above ceiling rough-in is continuing up the building with the 1st

floor nearly complete.

Texas A&M University Agriculture Headquarters

Week ly Repo r t : 1 / 11 / 10 - 1 / 15 / 10

West View of VC Sheetrock on 1st Floor HQ

North View of HQ Buck Hoist Cistern Tank Delivery

Setting ERU on HQ Roof