2010-01-15
DESCRIPTION
• Formed and poured the south entry stoop at the HQ • All the Air Handling Units will be delivered and placed on the HQ by the end of next week. • Started framing and forming for the upper roof at the VC. • Pouring the 37ft columns at the VC is ongoing. • Set the Energy Recovery Units on the roof on 1/12/10. • The installation of the west and east buck hoist is about 90% complete. • Placed the low roof at the VC on Tuesday 1/12/10. • Completed stair 1 at the HQ.TRANSCRIPT
• Installed the 40,000 gallon cistern tank on Wednesday 1/13/10.
• Set the Energy Recovery Units on the roof on 1/12/10.
• Completed stair 1 at the HQ.
• Placed the low roof at the VC on Tuesday 1/12/10.
• The installation of the west and east buck hoist is about 90% complete.
• Started framing and forming for the upper roof at the VC.
• Pouring the 37ft columns at the VC is ongoing.
• Started hanging the steel for stair 3 at the east end of the HQ.
• All the Air Handling Units will be delivered and placed on the HQ by the end of next week.
• Formed and poured the south entry stoop at the HQ
• Will place concrete pans at stair 2 beginning next week.
• Started putting sheetrock on interior partitions.
• MEP above ceiling rough-in is continuing up the building with the 1st
floor nearly complete.
Texas A&M University Agriculture Headquarters
Week ly Repo r t : 1 / 11 / 10 - 1 / 15 / 10
West View of VC Sheetrock on 1st Floor HQ
North View of HQ Buck Hoist Cistern Tank Delivery
Setting ERU on HQ Roof