©2009 Office of Massachusetts Attorney General Martha Coakley
Transmission Planning & Construction
“When, Where, How Much and Who Pays”
-Comments by Fred Plett,-Utility Analyst
![Page 2: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/2.jpg)
Page 2 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
Joint Coordinated System Plan
• Midwest ISO, TVA, SPP, PJM, MAPP,NYISO, and ISO-NE • 20% wind scenario • Transmission Dakotas to the Northeast• $80 Billion• 2024 Benefit – Cost Ratio of 1.0!!• If wind projects get built• Transmission cost may be 3-4 times higher!
![Page 3: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/3.jpg)
Page 3 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
• Testimony in Favor• ITC Holdings, Inc
- Green Power Express • Energy Futures Coalition
- JCSP studies, 3-1 BC Ratio• FERC Chair Wellinghoff
Subcommittee on Energy & EnvironmentThe Future of the Grid: Proposals for Reforming National Transmission
Policy
![Page 4: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/4.jpg)
Page 4 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
New England Transmission
Renewables in Northern NH and ME
• Northern New England View• Economic Development Opportunity• Socialized Rate-Based Transmission Costs
• Massachusetts View• “Build it and they will come” not Desirable• Giant Generator Interconnect
• Generator Responsible
• Costs Certain, Benefits Not
![Page 5: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/5.jpg)
Page 5 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
Hydro-Québec TransÉnergie,
NU and NSTAR HVDC Model
• Des Cantons, Québec - NH• US portion built by NU and NSTAR• Cost of Service Recovery from HQ US• Hydropower Sale to include Transmission
Cost• 25 Year Transmission, Purchase Agreements
All – In Cost Must Be Competitive!
![Page 6: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/6.jpg)
Page 6 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
Local vs. Midwest
• 100 – 250 Miles vs. 1,800 Miles!• Same Discussions - Who Pays, Who
Benefits• Costs Certain, Benefits Conditional –
But Costs Likely Lower Locally
![Page 7: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/7.jpg)
Page 7 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
Distances
![Page 8: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/8.jpg)
Page 8 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
Discussion Requirements
• Bottom Up Planning• Stakeholder Input and Acceptance• Proven Benefit Cost Ratio• Purchase Power Agreements
• Performance Warranties
All-In Costs must Benefit Consumers!
![Page 9: ©2009 Office of Massachusetts Attorney General Martha Coakley Transmission Planning & Construction “When, Where, How Much and Who Pays” -Comments by Fred](https://reader031.vdocuments.mx/reader031/viewer/2022032415/56649efc5503460f94c0fce3/html5/thumbnails/9.jpg)
Page 9 ©2009 Office of Massachusetts Attorney General Martha Coakley Fred PlettPresentation to NASUCA
June 30, 2009
Project Cost Control
• Helps Ensure Positive Benefit Cost Ratios
• Projects get built, may go into formula rates (non-Merchant projects)
• Should FERC be more aggressive in Prudence Reviews?