Forming, reinforcing, and poring pile caps and shear walls Drilling and pumping auger cast piles Backfilling west side of building to sub grade Receiving and unloading reinforcing and tightening form systems Installing 30” storm sewer on the east side of the site. Finished sanitary sewer lines F Installation of electrical duct bank started Installation of electrical primary manholes complete. Forming shear walls and crawlspace walls is ongoing Start demo of approaches off of John Kimbrough. Site fills and grading ongoing Texas A&M University Agriculture Headquarters Weekly Report: 8/3/09-8/7/09 South View Pile Caps Crawlspace Walls South View East View Storm Sewer Line

Upload: texas-am-agrilife

Post on 23-Feb-2016

213 views

Category:

Documents


0 download

DESCRIPTION

• Receiving and unloading reinforcing and tightening form systems • Start demo of approaches off of John Kimbrough. • Forming shear walls and crawlspace walls is ongoing • Forming, reinforcing, and poring pile caps and shear walls • Drilling and pumping auger cast piles • Installation of electrical primary manholes complete. • Finished sanitary sewer lines F • Backfilling west side of building to sub grade • Site fills and grading ongoing Storm Sewer Line

TRANSCRIPT

Page 1: 2009-08-07

• Forming, reinforcing, and poring pile caps and shear walls

• Drilling and pumping auger cast piles

• Backfilling west side of building to sub grade

• Receiving and unloading reinforcing and tightening form systems

• Installing 30” storm sewer on the east side of the site.

• Finished sanitary sewer lines F

• Installation of electrical duct bank started

• Installation of electrical primary manholes complete.

• Forming shear walls and crawlspace walls is ongoing

• Start demo of approaches off of John Kimbrough.

• Site fills and grading ongoing

Texas A&M University Agriculture Headquarters

Week ly Repor t : 8 /3 / 09 -8 /7 / 09

South View Pile Caps

Crawlspace Walls South View East View

Storm Sewer Line