Page 1: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 South BellSPRC Wrap-Up Meeting

April 2021

Page 2: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Project Page: https://projects.arlingtonva.us/projects/2001-clark-st/

TABLE OF CONTENTS1. Block Plan Updates 1:092. Program 1:503. Clark-Bell Realignment 5:454. Community Benefits Recap 9:12

Page 3: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

BLOCK PLAN

Page 4: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Block Plan Scenario Updates

Current Block Plan Scenario Proposed Block Plan Scenario

Page 5: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Final Proposed Block Plan Scenario

Final Proposed Block Plan Scenario illustrates:

• 60’ of separation that will be maintained between 2001 S. Bell and the future Crystal Plaza Apartments redevelopment

• Pedestrian connection and its relationship to future open space (Park 8)

Page 6: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

PROGRAM

Page 7: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Crystal City: Aerial Plan View

N

2000/2001 SITE

Page 8: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Existing Site

2000/2001 SITE

N

Page 9: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Aerial View Looking South

2000 S. Bell2001 S. Bell

Page 10: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

N

Parking Entry Off Alley

RIC

HM

ON

D H

WY

Pedestrian Connection

Retail Elevator to Garage & Underground

Residential EntryLoading

Loading

Site Plan Retail Entry

2000 S. Bell2001 S. Bell

Page 11: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 S. BELL ZONING SUMMARYZONING C-O CRYSTAL CITY

2000 S. BellHEIGHT 250’*

RESIDENTIAL GFA 367,040UNIT COUNT 338RETAIL GFA 12,244

PARKING SPACES** 157

*Excludes mechanical penthouse per Arlington County regulations**Garage is singular plate connecting both towers, inclusive of 5 visitor spaces

Page 12: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 & 2001 S. BELL ZONING SUMMARY

ZONING C-O CRYSTAL CITY

VEHICULAR BIKEBUILDINGS 2000 & 2001 S. Bell

SPACES 247 332*UNIT COUNT 758 -

RATIO .325 -*Exceeding Arlington County’s Bicycle Parking Requirements

Page 13: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 S. Bell Ground Floor

13

Angled loading docks and distinct loading zone to eliminate conflicts with

transitway

N

Simplified build to line, maintaining consistent

façade along Rt. 1

Residential entry setback creates outdoor

space to relieve pressure on the

sidewalk

Shifted building 6.5’ north and added 4-floor cantilever

element to accommodate gentler curve of Clark-Bell

Page 14: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 S. Bell – Podium/Ground Floor Updates

14

Page 15: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 S. Bell – Tower Views

20th StBell StFrom Route 1 South From Route 1 North

Page 16: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

CLARK-BELL REALIGNMENT

Page 17: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

17

Clark-Bell Alignment

Sector Plan: Proposed Final ConditionExisting Conditions

Interim Conditions/Phasing Not Included in Sector Plan

Page 18: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Clark-Bell Alignment

18

Coordinated a revised interim condition based on updated guidance from DES to address major concerns such as:

• Right-of-way services

• Sidewalk dimensions

• Additional detail for turning & loading movements

• Additional information on Clark-Bell alignment throughout the block over time

2000 S. Bell

2001 S. Bell

Page 19: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Ultimate S. Bell Street Alignment

19

Sections of Clark-Bell delivered with 2000 & 2001 S. Bell and southern end of the block will function in both the interim condition and ultimate condition per the Crystal City Sector Plan

Page 20: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

20

Streetscape Updates

5’ bike lanes with 2.5’ protection running N / S

along Clark-Bell

10’ dual direction bike lane

Page 21: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Clark-Bell Streetscape

Clark-Bell RoW Key Characteristics

Sector Plan 80’ • Single track, 6’ protected bike lane

Initial Proposal 72’ • Single track, 6’ protected bike lane

Final Proposal 76.5’ • Two separate single-direction, 5’ protected bike lanes

• 14’ sidewalks, 8’ clear sidewalk

Page 22: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Clark-Bell Streetscape

Initial Proposal Final Proposal

Crystal City Sector Plan

Page 23: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Connector Road Streetscape

Connector Road RoW Key Characteristics

Initial Proposal 35’ • Single track, 6’ protected bike lane

Final Proposal 38’ • Single, dual direction 10’ bike lane

Initial Proposal Final Proposal

Page 24: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

COMMUNITY BENEFITS RECAP

Page 25: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

2000 & 2001 S. Bell Specific Bonus Density & Community Benefits

25

Library Operations Support • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments:

$250K annually for 5 years; $1.25MOpen Space

• Design, construction, and easement for new pedestrian pathwayInfrastructure Improvements

• Realignment and easement dedication of Clark-Bell St.• Improvements to Rt.1 & 20th St. Intersection

Underground • Preservation and installation of improved underground connection

Sustainability • LEED Gold, Bird-Friendly Materials, Net-Zero Analysis & 12% over ASHRAE

Affordable Housing• Dedication of affordable units per Base Density requirements

Public Art • Doubling standard contribution to public fund: $150K Contribution

Page 26: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

26

COMMUNITY BENEFITSOPEN SPACE

Page 27: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Pedestrian Pathway

27

Page 28: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Pedestrian Pathway Connection and Future Open Space #8

N

28

Ped Pathway and Open Space #8 Area Overlap ≈ 1,700 SF

N

Page 29: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

29

COMMUNITY BENEFITSINFRASTRUCTURE IMPROVEMENTS

Page 30: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Clark-Bell St. Construction & Easement

30

Existing Conditions Sector Plan Phase to be delivered with 2000/2001

No interim conditions/phasing included in sector plan

Page 31: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Clark-Bell St. Construction & Easement

31

Page 32: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Rt 1 / 20th St. Intersection Improvements

32

Sector Plan

Page 33: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

33

COMMUNITY BENEFITSUNDERGROUND PRESERVATION & ENHANCEMENT

Page 34: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

N 34

Proposed Mid-path connection to open space

RIC

HM

ON

D

HW

Y

2001 S. Bell2000 S. Bell

Existing Route vs Proposed Connection

Crystal City Shops ExitExisting Underground Connection

Elevator connection between G1 & G2

Page 35: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Renderings

35

G1 Level

G2 Level

Page 36: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

36

COMMUNITY BENEFITSSUSTAINABILITY

Page 37: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Current Commitments:- LEED Gold- Bird Glass per Arlington Standards- 12% Energy Reduction above ASHRAE 90.1-202- Carbon Neutral Study

37

2000 & 2001 S. Bell St. Sustainability MeasuresPDSP Standard

- LEED Silver

Page 38: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

LEED Scorecard

Achieving LEED Gold

Page 39: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space

Benefits Recap

39

Library Operations Support • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP

commitments: $250K annually for 5 years; $1.25MOpen Space

• Design & installation of new pedestrian pathwayInfrastructure Improvements

• Realignment and easement dedication of Clark-Bell St.• Improvements to Rt.1 & 20th St. Intersection

Underground • Preservation and installation of improved underground connection

Sustainability • LEED Gold, Bird-Friendly Materials, Net-Zero Analysis & 12% over ASHRAE

Affordable Housing• Dedication of affordable units per Base Density requirements

Public Art • Doubling standard contribution to public fund to $150K

Page 40: 2000 South Bell - Projects & Planning · • Additional Funding for Library under 1901 S. Bell to be constructed per PDSP commitments: $250K annually for 5 years; $1.25M Open Space