2- idb s procurement policies and procedures for goods, works … · |4 ii) idb procurement...
TRANSCRIPT
|
Participate in Haiti’s Reconstruction
Montreal September 23, 2010
Procurement Policies and Procedures for Goods, Works
and Consulting Services
Sabine Engelhard, Lead Procurement SpecialistProject Procurement, Financial Management and Portfolio Monitoring Division (VPC/PDP)
| 1
I. Overview: Project cycle and procurement process
II. Procurement Policies
III. Responsibilities in the Procurement Process
IV. Basis for contract award and right to complain
V. Where to find information and documents
Procurement of Goods, Works & Consulting Services – Topics Overview
| 2
PROCUREMENTARRANGEMENTS
•Procurement Plan•Institutional Capacity Evaluation
•Project risk Evaluation
IdentificationPreparation
Analysis Approval
Execution and Supervision
6 Months4-8
Years
ProjectProfile(PP)
Loan Proposal
ProjectOperational Document
(POD)
Programming
ProcurementProcess
I) Overview: Project cycle and procurement process
| 3
Procurement process: Who are your counterparts?
• Procurement contracts with Executing Agencies in projects financed by the IDB
• Goods & Works• Consulting Services
• Procurement contracts with the IDB
• Consulting services for project preparation, technical cooperation
95%
5%
| 4
II) IDB Procurement Policies – for Sovereign Guaranteed Operations
Basic Policy Principles: Economy, Efficiency, Transparency, Equality, Competition and due process – Apply in general to IDB financed operations
Current Policies adopted in Jan. 2005: GN-2349-7 (http://idbdocs.iadb.org/wsdocs/getdocument.aspx?docnum=774392)GN2350-7 (http://idbdocs.iadb.org/wsdocs/getdocument.aspx?docnum=774394)
Almost identical to those used by other MDB’s
Some Specifics:� Eligibility� Nationality� Origin of goods
| 5
Basic Policy Principles: Economy, Efficiency, Transparency, Equality, Competition and due process are observed
Appendix 4 of Policies (GN2349-7) (GN2350-7)
Borrower (generally private sector) responsible for procurement
Private sector/commercial procurement practices acceptable to the Bank• IDB reviews such practices/procedures to ensure the
result in competitive market prices and needs of project are met.
IDB loan proceeds must be used to procure goods, works and services from IDB member countries.
IDB Procurement Policies - Provisions for Non Sovereign Guaranteed Operations (NSG)
|
IDB Procurement Policies - Provisions for Non Sovereign Guaranteed Operations (NSG)
When providing guarantees for NSG:
� Selection procedures for support in project preparationare requested from a shortlist
� Registration available to firms: www.iadb.org/resources/business/doingBusiness/formConsultant.cfm
When SCF Department lends to Sovereign Guarantee Borrowers, both Policies GN-2349-7 and GN-2350-7 apply fully for this portion of the loan.
6
| 7
Specific Procurement Notice (Advertising)
Bidding documents
Clarifications
Bid Submission
Payment for documents
Bid evaluation
Public bid opening
Bid results & notification
Public Access to Database
Award of Contract and Signing
Procurement Plan
Procurement Processfor Works and
Goods
| 8
Procurement Process for the Selection of Consulting Services
Issuance of Request for Proposals
Clarifications
Proposals Submission
Proposal evaluation
Proposals results and notification
Public Access to Database
Award of Contract and Signing
Procurement Plan
Short List of Firms to be invited
Request for expressions of interest (Advertising)
Technical Proposals opening-Evaluation-Price Proposals
Opening-Evaluation
| 9
* Includes all the projects bidding processes
Procurement Policies - Publicity
General Procurement Notice (GNP) *
• Published once within 30 days of loan’s approval by the Board of Directors in:� United Nations periodical “Development Business” (online)� IDB’s web site - Procurement Portal immediately thereafter:
http://www.iadb.org/procurement
| 10
Specific Procurement Notice (SPN)*
• Required for International Competitive Bidding (ICB) - published in:
� United Nations periodical “Development Business” (online)
� IDB’s web site - Procurement Portal immediately thereafter
• Required for National Competitive Bidding (NCB) published in:� The Country’s official web site for advertising government
business opportunities; or
�One local newspaper of wide circulation
Procurement Policies – Publicity (Cont.)
| 11
Procurement Methods for Goods and Works
Procurement Plan specifies the method to be used for each Procurement process
All methods open to bidders from member countries
Methods:� International Competitive Bidding (ICB)� National Competitive Bidding (NCB)�Shopping (comparison of at least 3 price quotations)
NCB may be used for procurement under the threshold amounts
| 12
Days from publication of Specific Procurement Notice (SPN) to deadline for submission of bids or submission of Prequalification Request
� Prequalification Applications 45 days
� Bids� Goods 45 days
� Small Works 45 days
� Major Works 90 days
Goods and Works Prequalification & Bid Preparation Time
| 13
Consulting Services- Selection Methods: Procurement Plan will specifies which method should be used
Six selection methods:� Quality & Cost Based Selection (QCBS)
� Quality Based Selection (QBS)
� Least Cost Based Selection (LCBS)
� Fixed Budget Based Selection (FBBS)
� Selection Based on Qualifications (CQS)
� Single Source Selection (SSS) (non competitive)
Basis for contract award for consulting Services
| 14
Days from publication of SPN to deadline for submission of proposals
� Request for Expressions of Interest 14 days
� Request for Proposal (shortlist: 6 firms) 30 days
Consulting Services Proposal Preparation Time
| 15
Issue clear and balanced bidding documentsProvide sufficient time for bidders to prepare bidsProvide timely responses to bidders questionsEvaluate bids based only on criteria established in biddingdocumentsAward the procurement contractCommunicate results to all partiesAddress complaints promptly and fairly
Executing Agency Responsibilities
III) Responsibilities in the procurement process
| 16
• Carefully analyze ALL requirements of the bidding documents or request for proposal documents
• Strictly comply with the instructions and specifications-terms of reference in the bidding/request for proposals documents
• Require clarifications to documents in writing
• Review bid/proposal for compliance with the requirements before submitting
• Submit bid/proposal with enough time to arrive before deadline
Bidder’s Responsibilities
Responsibilities in the procurement process
| 17
Bank Responsibilities
• Oversees the application of IDB procurement policies and procedures
• Reviews the procurement process ex-ante or ex-post (based on evaluation of institutional capacity) to determine adherence to IDB procurement policies
Responsibilities in the procurement process
| 18
For Goods & Works: The Bidder whose bid has been determined to have the lowest evaluated bid price and is substantially responsive to the bidding documents
IV) Basis for contract award and right to complain
Basis for contract award for goods and works
| 19
The Consulting Firm with the best evaluated proposal
depending on the selection method
Basis for contract award for Consulting Services
| 20
Difference in procedures from procurement of Goods and Works:
� Emphasis on technical competence/capacity and qualifications over price
� Invitations sent to a Short List of Consulting Firms (6)
Basic for Contracting Award
| 21
• Bidders/consulting firms may submit a complaint in writing at anystage of the procurement process
• Procurement process is not suspended when complaint is submitted
• Contracting Agency resolves the complaint
• If Bank determines that its procurement policies have not beenadhered to, Bank can declare misprocurement
� Bank cancels portion of the loan allocated to the process that was declared misprocured
Right to File a Complaint
|
IDB dedicated web page to HAITI
www.iadb.org/haiti/?lang=en
22
VI) Where to find information and documents
IDB procurement portal Free www.iadb.org/procurement
United Nations Development Business on line: US $550/ per yearwww.devbusiness.com
| 23
Type of ProcurementSpecial
ProvisionsWorks Goods Consulting firms
Threshold
amounts
(US$000)
ICB Shopping ICB Shopping
Shortlist comprised
entirely national
firms
>1,000 <1,000 >250 <250 <100
Advertising Mandatory in
UNDB and IDB
website
National optional
National or
international
invitation
Mandatory in
UNDB and IDB
website
National
optional
National or
international
invitation
As per IDB Policies
Time periods
for
prequalificatio
n
If used
Minimum
1 week
N/A If used
Minimum
1 week
N/A N/A
Time period for
receiving bids Minimum
2 weeks
Minimum 3
business days
Minimum
2 weeks
Minimum
3 business days
Minimum
2 weeks
Limited
International
Bidding
Time period: Minimum 2 weeks
Minimum 3 firms
Time period: 2 weeks minimum
Minimum 3 firms
N/A
HAITI - Special Procurement Provisions to Address Emergency caused by the January 12, 2010, earthquake (OP-387-1)
These procurement provisions are available in addition to current IDB Procurement Policies. Using them is an option for a 12 months period up to December 31, 2010-This period might be extended.
| 24
1,800TBD 300 1,100-1,400Investment needs (timing TBD)
Reconstruction of devastated zones
National transport network
Cyclone preparation & disaster risk management
Regional development & urban renovation (excl. electrification)
National electrification program
Land management & local development
Temporary & permanent housing
Education (school relaunch & construction)
Healthcare, food security &
nutrition
Water & sanitation
Re-launching central administrations
Justice and security
1
2
3
4
5
6
Agricultural production8
9
10
11
12
13
14
Watershed management7
NorthernPole
(100,000 jobs in
garments, tourism & agriculture
+Improved
livelihoods for 100,000 small-scale
farmers)
Wider Artibonite
Pole
(Improved livelihoods for 150,000 small-scale
farmers)
Southern Pole
(50,000 jobs in garment, tourism & agriculture
+Improved livelihoods for 120,000 small-scale
farmers)
Port-au-Prince
Pole
(Number of jobs TBD)
15 16 17 18
Territorial rebuilding
Economic rebuilding
Social rebuilding
Institutional rebuilding
Mapping of country strategic priorities and investment needs PRELIMINARY
NUMBERS
Investment need
* The time frame for some investments in not specified; generally speaking the amounts indicated are to be spend within a 3 year periodSource: GoH Lancement du Plan D’Action Pour Le Relevement et le Developpement d’Haiti (Mai 2010); IDB sector specialists
575
2,041
130
1,200
825
580
450
737,6
600
2,370
980
250
320
355
11,413,6
$ 200/million; 5 year period (Starting in 2010- all non-reimbursable)
| 25
IDB is capable of leading 6 priority development axes where it has the experience and expertise to drive the process
Assessment of IDB’s ability to take the lead based on
▪ Existing IDB project pipeline
▪ Past experience and expertise
▪ Relationship with relevant GoH stakeholders
▪ Relative strength/ reputation compared to other donors
Limited potential to take the lead
Strong potential to take the lead
▪ Education▪ National transport network▪Water & sanitation▪ Agricultural production▪ Private sector development*
▪ Northern pole
▪Wider Artibonite pole
▪ Request from the GoH▪ Strong presence and current strategic approach▪ Strong expertise and leadership▪ Pipeline of existing agriculture projects, strong expertise▪ Recognized leadership & innovative approach with both grants and reimbursable funding▪ Pipeline of existing projects (industrial park, tourism) ▪ Pipeline of existing agriculture projects, strong expertise
3
4
13
11
9
5
17
7
1
6
16
122
8
10
* Not mentioned as separate development axis in Government plan but Private Sector Development is integral part of several axes
Source: IDB internal analysis
DISCUSSED DRAFT
▪ Reconstruction of devastated areas▪ Disaster risk management ▪ Regional development and urban renovation ▪ Electrification program▪ Land management and local development▪Watershed management▪ Housing▪ Healthcare, food security & nutrition▪ Relaunching central administrations▪ Justice and security▪ Port-au-Prince pole▪ Southern pole
141518
26
| 27
| 28
| 29
| 30
| 31
IDB Procurement Portal – Projects in the Pipeline
| 32
Example from UNDB-IDB Procurement Notices
| 33
• RSS stands for “Really Simple Syndication”
• It is an easy way to stay updated automatically with relevant information from specific websites
• Automated notifications will appear every time your favorite websites post something new
• To enable this, a Web site will make a feed, or channel, available, just like any other file or resource on the server
Procurement Web Page RSS
|
Tips
34
• Familiarize yourself with the IDB Procurement Policies and Standard Procurement Documents
• Check the Procurement Portal of the IDB web site
WWW.IDB.org/pocurement to learn about:• Projects Pipeline• Follow up on Projects in Execution
• Consider joint ventures with local firms
• Learn local business practices
|
Questions?
|