Page 1: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 1

SCT Services Installation

ID week full report (July 4)SCT Cables Web page http://www-atlas.lbl.gov/ciocio/SCTcables/Workpackage https://edms.cern.ch/document/593278/

Page 2: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 2

Type II/III cables – Installation

• 3594 cables installed and testedAll 2112 barrel cables (sectors 1,3,7,9,11,15)All endcap cables for sectors 1,3,7,9

494 (sector 11&15) will be installed in August

Yield: <1% cables with defects or to replace

- Mechanical defects- Damage during installation or preparation- Failed electrical test (most probably due to splice damage) after installation (replaced)

Additional inspection of damage and final verification that individual wires are strongly fixed inside the JST and FCT when they will be disconnected from dPP1.

Page 3: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 3

Type II-III and Fibre Cables by Sector

S5

S3 S7

S1 S9

S15 S11

S13

US PP3 racks

USA PP3 racks

384 Barrel

494 EC

384 Barrel

494 EC

336 Barrel

247 EC

336 Barrel

247 EC

336 Barrel

247 EC

336 Barrel

247 ECLevel 7

Level 6

Level 2

Level 8

Level 5 & 2

Level 1 & 2

18 Fibre cables (EC)

27 Fibre cables (9 EC, 18 Barrel)

18 Fibre cables (Barrel)

27 Fibre cables (9 EC, 18 Barrel)

27 Fibre cables (9 EC, 18 Barrel) 27 Fibre cables (9 EC, 18 Barrel)

• Fibre Cables to USA15

Page 4: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 4

SCT Cables by Sectors Sequence• Sector 5 (top) and Sector 13 (bottom)

– heater cables, and DCS cables (completed)

• Sector 9 - Installation completed on May 1– 878 SCT cables (384 Barrel, 494 EC)– 18 Fibre cables (EC)

• Sector 3 - Installation started on May 2 – completed on June 4– 583 SCT cables (336 Barrel, 247 EC)– 27 Fibre cables (9 EC,18 Barrel)

• Sector 1 - started in parallel mid May – completed on June 13– 878 SCT cables (384 Barrel, 494 EC)– 18 Fibre cables (Barrel)

• Sector 7 – started on June 7 – completed on June 29– 583 SCT cables (336 Barrel, 247 EC)– 27 Fibre cables (9 EC,18 Barrel)

• Sectors 11, 15 – 336X2 barrel cables installed – July 18– 583 + 583 SCT cables (336 Barrel, 247 EC)– 27 + 27 Fibre cables (9 EC,18 Barrel)

• Installation sequence in a sector is:– Tubes, fibres, heater cables, SCT cables, (Muon cables), – TRT cables, pixel cables

Page 5: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 5

Type IV Cables - Installation

• All type IV cables (2044+spares) going from PP3 racks in the ATLAS cavern to PS racks in US15 installed (+ connectors)

• Type IV going to USA15 almost completed– 64 double harnesses to install (128 cables)– 6 more days

• Testing in racks after installation and first cut ongoing

Completed installation is expected in one week

Page 6: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 6

Type IV – Connectors in situ

• All connectors (2000+) in US15 completed on March 10 (a few were left but they are done now)

• Many racks are tested before and after plug into PS (Petr with Prague team)

• Very good yield but some rework was necessary • One rack (the very first one made more than an year ago) needs

cables rerouting (cables were cut too long by previous company)

• 2+1 CPE techs returned in mid-April for a few weeks– US side was reworked– Started 2 USA racks but left again because more USA15 racks

were needed to be completed for the full team to operate efficiently

• A team of 6 techs (1 supervisor) will return this week

• Estimated completion of connectors in USA racks: End of August

Page 7: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 7

PP3

• Assembly and Installation completed • Checks for shorted units and problems in progress• Plug-in of type IV cables• Problems found after installation in the last few months

– Insulation– Sliding units in subracks – Failed units (2+)

PP3 units installed in racksChannel

Spare units in racks

42614088

173

PP3 - failed (back for inspection and rework) 10

Subracks (30 PP3 units in a shell) 137

Subracks - special (shells of 30 partially filled with PP3 and the rest with empty boxes)

9

Subracks – mini(shells of 5 units for spares PP3 in a full rack)

4

ExtraPP3 units

Shells

Mini shells

Empty boxes

2

2

4

110

Page 8: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 8

Installation & Testing Activities

Type IV

Acceptance test (done)

Test in rack after installation

Test of cut cables after connector in situ work

Plug-in cables into PS crates Test with feedtrough

Type II-III Preparation ----ALL DONEAcceptance test (partial)

Visual inspection

Folding the shield and cut it the right amount, fix it

Organize boxes with right cables to send for installation

Type II-III Installation

Mount dPPB1 and dPPF1

(Barrel) Squeezing the cables to fit between pin and clamp holder

Plug-in of the delicate JST/FCI connectors to dPPB1

Placing the clamp (now), placing the clip (later) -- DONE

(ENDCAP) crimp group of drain wires in a ferrule and catch the ferrule with the grub screws into clamp’s holes

Plug in the dPPF1

Type II-III Testing

Type II-III replacing bad cables

PP3

Burn-in of units -- DONE

Assembly into subracks -- DONE

Installation into racks of subracks -- DONE

Plug-in the cables to PP3

Test of whole chain

Page 9: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 9

Schedule

• Type II-III barrel installation completed today Endcap cables of sector 11&15 to install after the Solenoid Field Mapping (July 19- Aug 14)

• Type II-III installation mid-July (Barrel) end of August (last

Endcap cables – 494)

• Type IV installation 24 July• Connector in situ+testing end of August• PS crates end-July (US side) – September (USA side)• PP3 assembly, installation end-July

• All cables plugged into PP3 mid-July- begin August (type IV) end-August (type II-III)

• Test of whole chain now – mid September

Page 10: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 10

Plan

Page 11: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 11

PS priorities

Page 12: 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

18 July 2006 A.Ciocio -SCTSG 12

Issues• PP3

– We find problems as we plug in and test– Type IV all connected by end of July– Hopefully OK when Type III are connected

• Tester– Different flavor that work with different configuration of cable

chain– Multiple laptops failure (~ok now)– Need help at CERN of experts (Ljubljana) when testing whole

chain• Defective dPPF1

– Some faulty cables were actually due to a bad channel on dPP1 (3 endcap 3 barrel)

– Still missing some dPPF1• Connector in situ

– Delay will move installation of PS later • Need more HELP with testing until end of August (mid September)