![Page 1: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/1.jpg)
1/27
ea technology
DCHP Field TrialsPractical Experiences with the WhisperGen
Project Manager : Rob GreenPresented by Yvonne Dickson
![Page 2: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/2.jpg)
2/27
Overview
• Introduction to the WhisperGen• History of EA Technology’s involvement• WhisperGen & the Stirling Cycle• Field trials• Performance
– Does it save money?– Does it reduce CO2 emissions?
![Page 3: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/3.jpg)
3/27
• Floor-mounted boiler replacement
• External combustion• Stirling cycle
What is the WhisperGen
![Page 4: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/4.jpg)
4/27
WhisperGen in the home
WhisperGen
microCHPunit
GRID ELECTRICITYIMPORT / EXPORT
GAS100%
EXHAUST10%
GENERATION10 %
HEAT80 %
![Page 5: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/5.jpg)
5/27
Project History• 1999 - studies of commercial viability• 2000 - lab demo of Mk I WhisperGen• 2001 - Mk I
• 3 trial houses + test house + lab endurance• 2002 - alpha trial Mk II
• 13 houses + lab endurance (4)• 2003 - beta trial Mk III
• 15 Chester + 13 Ipswich + lab (Mk II & III)• 2003 / 4 - Mk IV
• pre-launch checks - 3 Chester houses
![Page 6: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/6.jpg)
6/27
Powergen market launch 2004• EA Technology training of installers• Monitoring for Carbon Trust & DTI
Project History (2)
![Page 7: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/7.jpg)
7/27
Piston
RegeneratorGas Flame
Cooling Circuit
The Stirling Cycle
Piston
Gas
![Page 8: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/8.jpg)
8/27
The Stirling Cycle
![Page 9: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/9.jpg)
9/27
compression at constant temperature
The Stirling Cycle
![Page 10: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/10.jpg)
10/27
displacement / regeneration at constant volume
The Stirling Cycle
![Page 11: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/11.jpg)
11/27
expansion at constant temperature
The Stirling Cycle
![Page 12: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/12.jpg)
12/27
displacement / regeneration at constant volume
The Stirling Cycle
![Page 13: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/13.jpg)
13/27
WhisperGen & the Stirling Cycle
ReturnFlow
Generator
Wobble Yoke
Air
GasHOT END
COLD END
Exhaust Cooler
4 CylinderNitrogen FilledStirling Engine
![Page 14: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/14.jpg)
14/27
WhisperGen
• Mk IV current– 0.85 kWe / 6 kW t– 1.2 kWe / 8 kW t
• Mk V soon– ~ 1 kWe / 7 kW t to ~ 1 kWe / 15 kW t
![Page 15: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/15.jpg)
15/27
The need for field trials
Prototype:– Ease of installation– Reliability– Operational experience– Control systems– User acceptability– Performance / Economics– Improvements
![Page 16: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/16.jpg)
16/27
The need for field trials (2)
Market ready:• Carbon Trust
– CO2 emissions– Product accreditation
• DTI / electricity suppliers– Electricity metering / settlement
![Page 17: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/17.jpg)
17/27
EA Technology Field Trials
![Page 18: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/18.jpg)
18/27
What to measure?
• Electricity kWh– Generation– House in and out
• Heat output• Gas input• Temperatures?
![Page 19: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/19.jpg)
19/27
Findings
• Range of house types & occupancy patterns– Both affect run hours– Occupant behaviour – big variable
• Sales + Accreditation?• User acceptability
– Noise– Speed of response
![Page 20: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/20.jpg)
20/27
Electricity
-1
-0.5
0
0.5
1
1.5
2
2.5
3
00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00
time
kW (a
vera
ge o
ver 1
5 m
in)
14/02/02House useHouse ImportHouse ExportWG Export
![Page 21: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/21.jpg)
21/27
Electricity
-1
-0.5
0
0.5
1
1.5
2
2.5
3
00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00
time
kW (a
vera
ge o
ver 1
5 m
in)
17/04/02House useHouse ImportHouse ExportWG Export
![Page 22: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/22.jpg)
22/27
Electricity
-1
-0.5
0
0.5
1
1.5
2
2.5
3
00:00 02:00 04:00 06:00 08:00 10:00 12:00 14:00 16:00 18:00 20:00 22:00 00:00
time
kW (a
vera
ge o
ver
15 m
in)
09/03/02House useHouse ImportHouse ExportWG Export
![Page 23: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/23.jpg)
23/27
Economics – does it save money?
• Well matched (application & engine)– £150 to £200 / year (~ €250 / year)
• Need long run hours– Occupancy pattern– House heat loss (need large houses)
• Mk V
![Page 24: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/24.jpg)
24/27
Government targets CO2
- Global warming / Kyoto- dCHP high priority
• dCHP in context of house- 60 WhisperGen sites to be monitored
- 40 Powergen- 20 Northern Ireland
Carbon Trust Monitoring Trial
![Page 25: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/25.jpg)
25/27
Carbon Trust Method
Pulses (Gas, electric, heat)
Temperatures Logger / receiver
Telemetry systemGSM
![Page 26: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/26.jpg)
26/27
Does it save CO2?
• Comparing against?– Boiler (B rated 86%+, A rated ~93%)– Central power station
• If dCHP overall efficiency >= boiler efficiency– Obviously reduces CO2 emissions
• If dCHP overall efficiency < boiler efficiency– Not so clear cut
![Page 27: 1/27 ea technology DCHP Field Trials Practical Experiences with the WhisperGen Project Manager : Rob Green Presented by Yvonne Dickson](https://reader036.vdocuments.mx/reader036/viewer/2022062412/5a4d1b017f8b9ab059986d81/html5/thumbnails/27.jpg)
27/27
Conclusions• WhisperGen is commercially available
– Stirling Cycle, External Combustion• Field trials are essential to prove:
– Customer acceptability, reliability, use patterns export (utilisation) etc. etc.
• Occupant behaviour has a big effect• Mk V should expand market for WhisperGen• Saves CO2?