Direct and indirect costs of flight delays:Punctuality as a cost factor

Moscow, August 6th, 2011

Page 2: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 2 -

Content

1. Dream or Reality: Delay Cost Management

2. Delay Cost Modeling – Delay Costing Practices

3. The Future: Delay Opportunity Cost Performance Management

4. Discussion

- 2 -

Page 3: 110830 Lufthansa Consulting Delay Cost En

42%

3%6%11%

33%

5%Airline

Security

Misc.

Other Weather

ATFCM

Other Airport

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 3 -

The majority of delays are airline related while the second largestdelay driver is Ground Handling according to Eurocontrol data

74

IATA delaycodes

Source: Eurocontrol. CODA Digest. Delays to Air Transport inEurope. Annual Report 2010.

1. Technical Delays

2. Ground Handling

3. Flight Ops and Crewing

Primary delay causes 2010

Page 4: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 4 -

Delays matter!Delay cost matter!

Individual Airline Delay Cost US Airline Industry Delay Cost

Source: National Center of Excellence for Aviation OperationsResearch: Total Delay Impact Study. A ComprehensiveAssessment of the Costs and Impacts of Flight Delay in the UnitedStates. Final Report — October, 2010.

Cost to USAirlines

8.3 BillionUS$

Cost to USPassengers

16.7 BillionUS$

Cost to US fromLost Demand

3.9 Bill. US$

Impact on GDP 4.0 Billion US$

TOTAL COST 32.9 Billion US$

Source: Lufthansa Consulting Research.

Page 5: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 5 -

On timePerformance

Productivity CustomerSatisfaction

The theory is straight forward: There is a correlation betweencustomer satisfaction – performance and productivity

- 5 -

Teaming up for Excellence

$$$$

Performance

Page 6: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 6 -

50

55

60

65

70

75

80

85

90

95

100

0 50000 100000 150000 200000 250000 300000

According to customer satisfaction delays made it to the internet:more and more internet service providers track & benchmark OTP

72.8%

Source: FLIGHTONTIME.info. Airline punctuality at uk airports

BritishAirways

Easyjet

Ryanair

Flybe

OTP

Number of departures

Scheduled Airline Departure On Time Performance 2010 within 15 min (UK)

68.6%

71.2%

80%

2010

2009

2008

2007

BMI

Lufthansa

Monarch

BMI Regional

Eastern Airways

Virgin Atlantic

Emirates

Iberia

BA CityflyerSwiss

Bmi baby

SAS

American Airlines

Page 7: 110830 Lufthansa Consulting Delay Cost En

- 7 -

Today the lawn is cut: handling fees shrink. Airlines have introducedtight service level agreements …… So what’s next ?

Too high

costs

1996

…... . .

.

… ….

25%

20%10 %

Cost Cutting

Ressourceallocation

Handling fees

Airline & Ground Handling /Airport System Partnership

Purchasing today

?

?

?OCC

HCC

SLA End of history ?

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 8: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 8 -

Customer Satisfaction

IATA delay codes are the element for performance managementBut delay costing and delay cost management is still in its infancy

Performance / OTP

ProfitablityTeaming up for Excellence

MIS

Dash Boards

Cockpits, etc.1

2

Airlines

82*

IATA delaycodes

478*

sub-delaycodes

Analytics,Forecasting

ABC ABM

BI

3

Tomorrow

BU

e.g. MIDT orCRM

COSTCost elements * Airline sample

DOCUnit Cost

Budget

Page 9: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 9 -

Content

1. Dream or Reality: Delay Cost Management

2. Delay Cost Modeling – Delay Costing Practices

3. The Future: Delay Opportunity Cost Performance Management

4. Discussion

- 9 -

Page 10: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 10 -

Westminster Report

2004

ATA USCarriers

2009

AirlineBusiness

Case

ITA Study

2000

Fuel X X X X

Maintenance X X X X

Crew X X X X

Airport Charges X X X

Aircraft Ownership X X X

Direct Operating Cost (DOC) 60,99 $ 40 – 66 €

Extra Gates and Ground Staff X X

Passenger Compensation X X X

Passenger Opportunity Cost X X

Total Unit Cost / delay minute 72 € 98,55 $ 66 € 87 – 126 €

Delay cost models target unit costs per delay minute or hourbased on annual / quarterly / monthly accounting figures

With delays airlines loose more than an image and customers - delays cost money

This is why stable operations pays off by all means

Page 11: 110830 Lufthansa Consulting Delay Cost En

The leading cost models applied at airlines (e.g. EUROCONTROL -University of Westminster) get more and more sophisticated

- 11 -

Source: EUROCONTROL Cost Benefit Analyses. Edition Number: 4.0. October 2009

Extra Gate and Ground Staff

Delay Cost = f(……..)

Tactical & Strategic Delays Length and Situation of Delays

+

+

+

CXX Cost = f(……..)

+ATA US Carriers 2009

COST

DOC

Unit Cost

BudgetCost elementCost element

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 12: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 12 -

Source: EVALUATING THE TRUE COST TO AIRLINES OF ONE MINUTE OF

AIRBORNE OR GROUND DELAY. Report Commissioned by thePerformance Review Commission: Unicersity of Westminster. May 2004

In general the cost models apply delay cost as an additive functionof cost – the cost of each delay event are defined as a linear function

Page 13: 110830 Lufthansa Consulting Delay Cost En

The cost of cancelation are defined as follows

CXX cost

in EUR

50 seat narrow body aircraft 3.400

120 seat narrow body aircraft 16.000

400 seat wide body aircraft 75.000

Per CXX 7.000

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 13 -

Source: EUROCONTROL Cost Benefit Analyses. Edition Number: 4.0. October 2009

Cancelation Cost

service recovery costs(passenger vouchers, drinks,telephone, hotel)

interline costs (rebookingrevenue)

loss of future value (individualpassenger delay expressed invalue)

operational savings (fuel, en-route charges, crew facilities,handling

outstations, lounges outstations,board supplies)

Costs not included are groundhandling costs, missed connectioncompensation, denied boardingcompensation and luggagedelivery costs.

COST

DOC

Unit Cost

BudgetCost element

CXX Cost = f(……..)

Page 14: 110830 Lufthansa Consulting Delay Cost En

- 14 -

The reality on delay costing …. we talk ‘Scheingenauigkeit’(apparent accuracy) … we talk legacy systems and methods

Delay Cost Matter – Ground Handling Conference Moscow, 2011

ERP Systems

Cost CenterAccounting

COST

DOC

Unit Cost

Budget

Delay Cost = f(……..)

Cost ElementAccounting

Cost ObjectAccounting

Route Profitability

Aircraft1328

Interviews

Personal cost

Maintenance: fixedmaintenance, direct var.maintenance, reserves, …

Personal: cockpit cost,cabin cost, station cost,handling cost, fuel, material

DOC (catering, landing,parking, etc.),

….

627 Department

Station

Projects

Tools or Ept.

Services

….

4

HOLDING & ApproachDeviations: Fuel Consumption

250

72 €

4

3 Technical cost

Miss Connex Cost(irregularities, loss of

revenue, drop in yields,dispo HCC, staff luggageservice, sations included

calc

Station handling overtime

Flight irreg. / luggage

Delivery delayed baggage

5Block time cost

….

+

+

+

765180

Page 15: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 15 -

Content

1. Dream or Reality: Delay Cost Management

2. Delay Cost Modeling – Delay Costing Practices

3. The Future: Delay Opportunity Cost Performance Management

4. Discussion

- 15 -

Page 16: 110830 Lufthansa Consulting Delay Cost En

Delay cost management is about managing complexity –airlines establish Hub Control Centers to reduce delay cost

On-Blocks Off-Blocks

Hub Airport

Off-Blocks

En-routeSpokeAirport

Take-Off Touchdown Take-Off Touchdown

SpokeAirport

On-Blocks

En-route

HubControlCenter

Ground Event

BaggageHandling

PassengerHandling

TurnaroundManagement

Airport

ATC

PunctualityCustomer Satisfaction ProfitabilityConnectivity

Outstation / Representation Outstation / Representation

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 17: 110830 Lufthansa Consulting Delay Cost En

- 17 -

This was the starting point: Ground OPS was a black box

on blocks off blocks

Ground Handling Activities

Minimum Ground Times

?

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 18: 110830 Lufthansa Consulting Delay Cost En

- 18 -

The objective was to manage and anticipate delay drivers toplan preventive actions and take recovery measures

on blocks off blocks

REFERENCE MODEL

Hub and ground handling activities

Recovery

Prediction of delayfollowed bypreventive action

Recovery

Prediction of delayfollowed bypreventive action

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 19: 110830 Lufthansa Consulting Delay Cost En

- 19 -

A core activity of the HCC is to monitor and manage theturnarounds

On-Blocks Off-Blocks

Hub Airport

Off-BlocksSpoke Airport

En-routeSpokeAirport

Take-OffSpoke Airport

Touchdown Take-Off TouchdownSpoke Airport

SpokeAirport

On-BlocksSpoke Airport

En-route

Airplane CharacteristicsAirbus A320

Crew

Dock bridge / stairs

Catering

Disembarking

Refueling

Cargo unloading / loading

Gate, embarking

Remove bridge / stairs

40 min 35 30 25 20 15 10 5 0

On blocks Off blocksFirst passenger on board

max. 1 min.

max. 5 min.

25 20

max. 10 min.

max. 12 min.

max. 14 min.

Last bulk freight/mail at the A/C

max. 12 min.

max. 14 min.

Contact position: First passenger on board

Remote position: Arrival of the first bus at A/C Remote position: Last bus at A/C

5

doors inparkCleaning max. 8 min.

Last opportunity to report irregularities / last orders

Positioning / Removal

Activity

Turnaround Mgmt

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 20: 110830 Lufthansa Consulting Delay Cost En

- 20 -

Source:

The building blocks of Hub Management at Lufthansa

Steering Passenger & BaggageConnection

Real-Time KPI ManagementTurnaround Management

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 21: 110830 Lufthansa Consulting Delay Cost En

- 21 -

Based on real-time delay forecasting the ground events are managedby speeding up the processes where needed

Turnaround Manager

Quick Cleaning

Increase Cleaning Crew

Leave Bag Behind

Increase Loading Crew

High Speed Catering

Increase Catering Crew

…….

Steering Activities

Real-Time KPI Management

Production

Time Stamps

Steering Action

Turnaround Management

Real-time Analysis

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 22: 110830 Lufthansa Consulting Delay Cost En

- 22 -

The Passenger and Baggage Connection Managementclassifies passengers based on rules and automatically calculatesand suggests steering actions

Steering Passenger & BaggageConnection

Real-Time KPI ManagementSteering Activities

Time Stamps

Steering Action

Real-time Analysis

Approach Priority

Gate Direct Service

Ramp Direct Service

Electrical Car Service

Connex Delay x> 10min

Connex Delay x>10 min

New Position

Roll Priority

…..

Delay Cost Matter – Ground Handling Conference Moscow, 2011

Page 23: 110830 Lufthansa Consulting Delay Cost En

Delay management needs to do a profit and loss analysisbased on a delay opportunity cost analysis

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 23 -

Delay Cost

Steering Unit Cost

OCC

Aircraft Reserves

Block time buffers

Version Change

Aircraft Change

Equipment Change

Diversion

Re-Routing

Cancellation

Connex Steering UnitCost HCC

Approach priority

Ramp transfer

Gate direct

Cart connex

Delay aircraft

New position

Roll priority

Turnaround SteeringUnit Cost HCC

Quick cleaning

Increase cleaningCrew

Leave baggage behind

Increase loading crew

High speed catering

Increase catering crew

Classic DOC

Holding & aapproachdeviations

Flight irreg. /baggage

Deliverydelayed baggage

PAXcompensation

Transit

Missed Connex

Delay Opportunity Cost

Profit and Loss Analysis

Cost Benefit Analysis

PAX Revenue

SteeringCost+

SLA Malus

Page 24: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 24 -

Delay management will need to forecast / simulate the effects of thesteering actions plus a deviation analysis plan vs. actual efficiency

Cost

Time2h1h 4h3h 6h5h 8h7h 9h

CXX

Aircraft Change Equipment Change Version ChangeOCC Delay Cost

Reduction Measures

HCC Delay CostReduction Measures

Approach Priority Ramp Transfer

Crew Change

Gate Direct New Position Roll Priority

Quick Cleaning Leave Bag behind Leave Bag behind

Opportunity Cost

Delay Cost Drivers

Increase Catering Crew

SteeringCost+

Page 25: 110830 Lufthansa Consulting Delay Cost En

Delay Cost Matter – Ground Handling Conference Moscow, 2011 - 25 -

Content

1. Dream or Reality: Delay Cost Management at Airlines

2. Delay Cost Modeling – Delay Costing Practices

3. The Future: Delay Opportunity Cost Performance Management

4. Discussion

- 25 -

Page 26: 110830 Lufthansa Consulting Delay Cost En

Thank you very much for your attention!

Any questions ?

Page 27: 110830 Lufthansa Consulting Delay Cost En

- 27 -

Contact

Lufthansa Consulting GmbHVon-Gablenz-Str. 2 – 650679 CologneGermany

Tel.: +49 (0)221 826 8107Fax: +49 (0)221 826 8260Mobile: +49 (0)151 58940507

e-mail: [email protected]

www.lhconsulting.com

Gesine VarfisManaging Consultant

Lufthansa Consulting GmbHTsvetnoy Blvd. 25, bld. 3, 6th floorMoscow 127051Russia

Tel.: +7 495 7987729Fax: +7 495 680 6304Mobile: +7 903 798 7729

e-mail: [email protected]

www.lhconsulting.ru

Askhat TorshinPermanent RepresentativeRussia, CIS and Baltic States