1.040/1.401 project management · work breakdown structure huna office building 7/15/2000 sample....
TRANSCRIPT
![Page 1: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/1.jpg)
1.040/1.4011.040/1.401
Project ManagementProject ManagementSpring 2007Spring 2007
PlanningPlanning
Dr. SangHyun Lee
Department of Civil and Environmental EngineeringDepartment of Civil and Environmental EngineeringMassachusetts Institute of Technology Massachusetts Institute of Technology
![Page 2: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/2.jpg)
Project Management PhaseProject Management Phase
FEASIBILITY DEVELOPMENT CLOSEOUT OPERATIONS
Fin.&Eval.
RiskEstimating
PlanningPlanning
DESIGNDESIGNPLANNING PLANNING
Organization
![Page 3: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/3.jpg)
OutlineOutline
Planning Planning –– Hierarchical Project StructuresHierarchical Project StructuresWork Breakdown StructureWork Breakdown Structure
Organization Breakdown StructureOrganization Breakdown Structure
Cost Breakdown StructureCost Breakdown Structure
![Page 4: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/4.jpg)
Planning ComponentsPlanning Components
What: Work Breakdown StructureWhat: Work Breakdown StructureHow: Plans and SpecificationsHow: Plans and SpecificationsWho: Organization Breakdown StructureWho: Organization Breakdown StructureHow much: Cost Breakdown Structure (via estimate)How much: Cost Breakdown Structure (via estimate)When: ScheduleWhen: Schedule
![Page 5: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/5.jpg)
OutlineOutline
Planning Planning –– Hierarchical Project StructuresHierarchical Project StructuresWork Breakdown StructureWork Breakdown Structure
Organization Breakdown StructureOrganization Breakdown Structure
Cost Breakdown StructureCost Breakdown Structure
![Page 6: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/6.jpg)
Work Breakdown StructureWork Breakdown Structure
A WBS is a deliverableA WBS is a deliverable--oriented grouping of project components oriented grouping of project components that organizes and defines the total scope of the projectthat organizes and defines the total scope of the project
Work not in the WBS is outside the scope of the projectWork not in the WBS is outside the scope of the project
WBS is usually an operative tool used by contractorsWBS is usually an operative tool used by contractors
First step towards constructing a scheduleFirst step towards constructing a schedule
Central role in project monitoring and controlCentral role in project monitoring and control
![Page 7: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/7.jpg)
WBS: ExampleWBS: Example
Source: Shtub et al., 1994
different summary level
Project
Site-Work On-Site Utilities Buildings
Grading andDrainage
PavingSurfaces
WaterSystem
UndergroundElectrical
WorkPackage
WorkPackage
WorkPackage
OfficeBuilding
MaintenanceBuilding
WarehouseBuilding
Drives Parking Architectural
Foundation Shell
Structural Mechanical Electrical
Level IMajor Facilities
Level IISub-Facilities
Level IIIWork Item
Level IVTasks
Level VWork Packages
Denotes continuedbreakdown
Illustrative Work Breakdown Structure (WBS)
Figure by MIT OCW.
![Page 8: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/8.jpg)
Work PackageWork Package
Lowest levelLowest level
Distinguish from OthersDistinguish from Others
Single Responsible OrganizationSingle Responsible Organization
Assigned Start and FinishAssigned Start and Finish
Assigned BudgetAssigned Budget
Limited DurationLimited Duration
![Page 9: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/9.jpg)
Types of WBSTypes of WBS
Project WBSProject WBS
Operative tool for monitoring and control contractor workOperative tool for monitoring and control contractor work
Contractual WBSContractual WBS
Defines the level of reporting that the seller will provide the Defines the level of reporting that the seller will provide the buyerbuyer
May include less detail than Project WBSMay include less detail than Project WBS
Agreed between owner and contractorAgreed between owner and contractor
![Page 10: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/10.jpg)
level 0
level 1
level 2
level 3
level 4
level 5
FunctionalFunctional ApproachApproach
GAS-STEAM COMBINED POWER PLANT
MAIN FUNCTIONS OF PLANT
UNITS
GAS INTERFACESSTEAM
TURBINE COMPRESSION STATIONGENERATOR
COMPRESSORS ENCLOSUREGAS TREATMENT
SUB-UNITS
WORK PACKAGES
ITEMS
COMPRESSOR 1 FOUNDATIONSCOMPRESSOR 2
DESIGN INSTALLATIONPROCUREMENT
![Page 11: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/11.jpg)
Physical Space ApproachPhysical Space Approach
ProjectProjectMain buildingMain building
1st floor1st floorStructuresStructuresPlumbingsPlumbingsElectricalElectricalHVACHVAC
2nd floor2nd floorService buildingService building
StructuresStructuresPlumbingsPlumbingsElectricalElectricalHVACHVAC
![Page 12: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/12.jpg)
Procedure ApproachProcedure Approach
ProjectProjectFeasibilityFeasibilityDesignDesign
BasicBasicDetailDetailBid documentsBid documentsShop drawingsShop drawings
BidBidConstructionConstruction
Foundations subcontractFoundations subcontractMain buildingMain building
PilesPilesConcrete foundationsConcrete foundations
Service buildingService buildingPilesPilesConcrete foundationsConcrete foundations
Steel erectionSteel erectionFinishingsFinishings
CommissioningCommissioning
![Page 13: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/13.jpg)
WBS: CSI Master Format WBS: CSI Master Format -- Example Example
Source: Schaufelberger et al., 2002
1 Job Site General conditions 9 Finishes:2 Site work: Drywall
Earthwork & Utilities Painting Paving Acoustical Ceilings Walks & Miscellaneous Sitework Floor Covering: Carpet
3 Concrete: Floor Covering: Ceramic, Vinyl, Base Purchase Reinforcement Steel 10 Specialties Foundations 11, 12, 13 Walls & Slabs
4 Masonry 14 Conveying Systems (Elevator)5 Structural and Miscellaneous Metals 15 Mechnical Systems:6 Wood & Plastic Plumbing
Rough Carpentry Fire Protection Finish Carpentry / Wood Floors HVAC
7 Thermal & Moisture Protection Controls Insulation 16 Electrical Systems Roof & Accessories Gutters & Downspouts
8 Doors, Windows, Glass Doors Windows & Storefront Door Hardware
Equipment, Furnishings, & Special Construction
NORTHWEST CONSTRUCTION COMPANY1242 First Avenue, Cascade, Washington 98202
(206) 239-1422
CSI Division Description CSI
Division Description
Work Breakdown StructureHuna Office Building
7/15/2000
Sample
![Page 14: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/14.jpg)
OutlineOutline
Planning Planning –– Hierarchical Project StructuresHierarchical Project StructuresWork Breakdown StructureWork Breakdown Structure
Organization Breakdown StructureOrganization Breakdown Structure
Cost Breakdown StructureCost Breakdown Structure
![Page 15: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/15.jpg)
Organization Breakdown StructureOrganization Breakdown Structure
Decomposition of necessary resources to perform jobDecomposition of necessary resources to perform job
Identification & organization of the resources responsible with Identification & organization of the resources responsible with carrying out activities associated with the projectcarrying out activities associated with the project
Used to keep track of specific work assignments & resource Used to keep track of specific work assignments & resource allocationsallocations
![Page 16: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/16.jpg)
Organization Breakdown StructureOrganization Breakdown StructureProject resourcesProject resources
Project management teamProject management team
Project managerProject manager
Construction superintendentConstruction superintendent
Field superintendentField superintendent
Office managerOffice manager
SchedulerScheduler
Accounter/controllerAccounter/controller
Field engineerField engineer
Construction forceConstruction force
WorkerWorker
SubcontractorSubcontractor
ElectricalElectrical
PlumbingPlumbing
InsulationInsulation
TankageTankage
RoadsRoads
![Page 17: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/17.jpg)
OBS/WBS OBS/WBS LinkagesLinkages
Source: Shtub et al., 1994
Project People
WBS OBS
MajorFacility
MajorGroup
Sub Facility Sub Group or Department
Work Item Discipline
Task 2Task 1 Task 3 Engineer A Engineer B Engineer C
WorkPackage 1
WorkPackage 2
WorkPackage 3
Denotes continuedbreakdown
Linking the WBS and OBS.
Figure by MIT OCW.
![Page 18: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/18.jpg)
OutlineOutline
Planning Planning –– Hierarchical Project StructuresHierarchical Project StructuresWork Breakdown StructureWork Breakdown Structure
Organization Breakdown StructureOrganization Breakdown Structure
Cost Breakdown StructureCost Breakdown Structure
![Page 19: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/19.jpg)
Cost Breakdown Structure (CBS)Cost Breakdown Structure (CBS)
Breakdown of the costs of the various components of the Breakdown of the costs of the various components of the structure including all work done by the subcontractorsstructure including all work done by the subcontractors
Serves as a basis for subsequent monthly pay requests by the Serves as a basis for subsequent monthly pay requests by the contractorcontractor
Used to continuously compare costs as they actually occur Used to continuously compare costs as they actually occur with the budgetwith the budget
![Page 20: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/20.jpg)
Cost Breakdown Structure (CBS)Cost Breakdown Structure (CBS)
Source: Shtub et al., 1994
100 Clearing & Grubbing 245 Precast Concrete101 Demolition 260 Concrete forms102 Underpinning .01 footings103 Earth Excavation .05 grade beams104 Rock Excavation .07 slab on grade105 Backfill .08 beams115 Wood structural piles .10 slab116 Steel structural piles .11 columns117 Concrete structural piles .12 walls121 Steel sheet piling 280 Structural Steel240 Concrete poured 350 Masonry
.01 footings .01 8 in. block
.05 grade beams .02 12 in. block
.07 slab on grade .06 common brick
.08 bcarns .20 face brick
.10 slab on forms .60 glazed tile
.11 columns 400 Carpentry
.12 walls 440 Millwork
.16 stairs 500 Miscellaneous Metals
.20 expansion joints .01 metal door frames
.40 screeds .20 window sash
.50 float finish .50 toilet partitions
.51 trowel finish 560 Finish Hardware
.60 rubbing 620 Paving
.90 curing 680 Allowance685 Fencing
Project Work Accounts .100 - .699
MASTER LIST OF PROJECT COST ACCOUNTSSubaccounts of General Ledger Account 80.000
PROJECT EXPENSE
![Page 21: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/21.jpg)
Two Main ApproachesTwo Main Approaches
CBS = WBSCBS = WBS
CBS is the project cost control structureCBS is the project cost control structure
CBS CBS ≠≠ WBSWBS
CBS is the corporate multiCBS is the corporate multi--project cost control structureproject cost control structure
Usually the case of a firm that has an integrated cost control sUsually the case of a firm that has an integrated cost control systemystem
![Page 22: 1.040/1.401 Project Management · Work Breakdown Structure Huna Office Building 7/15/2000 Sample. Outline Planning Planning –– Hierarchical Project StructuresHierarchical Project](https://reader030.vdocuments.mx/reader030/viewer/2022040217/5d5ce25688c993be038b4cb6/html5/thumbnails/22.jpg)
Diverse CombinationsDiverse Combinations
WBS + OBS: Task assignmentsWBS + OBS: Task assignments
CBS + OBS: Budget monitoring of crews, etc.CBS + OBS: Budget monitoring of crews, etc.
OBS + Schedule: TimeOBS + Schedule: Time--specific crew assignmentsspecific crew assignments
CBS + Schedule: Cost monitoringCBS + Schedule: Cost monitoring