1.0 · web viewfigure 2: the level 2 and level 3 work breakdown structure for sphenix mie table 5a:...

60
1 sPHENIX Preliminary Project Execution Plan May 2018

Upload: others

Post on 06-Apr-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

1

sPHENIX Preliminary Project Execution PlanMay 2018

Page 2: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

2

Submitted by:

Edward O’Brien DatesPHENIX Project Director

Glenn Young DatesPHENIX Project Manager

Maria Chamizo-Llatas DateDirector, Detector Projects

Berndt Mueller DateAssociate Laboratory Director Nuclear and Particle Physics

Lloyd Nelson, Federal Project Director DateBrookhaven Site Office, DOE

David Mitchell, Contracting Officer DateBrookhaven Site Office, DOE

Robert Gordon, Acting Manager DateBrookhaven Site Office, DOE

Elizabeth Bartosz DateProgram Manager for Nuclear Physics Instrumentation Office of Nuclear Physics, DOE

James Hawkins DateProgram Manager for Major Initiatives Office of Nuclear Physics, DOE

Jehanne Gillo, Director DateFacilities and Project Management DivisionOffice of Nuclear Physics, DOE

Concurrence:

Steve Meador, Associate Director DateOffice of Project Assessment, Office of Science, DOE

Approval:

Page 3: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

3

Timothy Hallman, Project Management Executive DateAssociate Director of the Office of Nuclear PhysicsOffice of Science, DOE

Page 4: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

4

Preliminary Project Execution Planfor the

Super Pioneering High Energy Nuclear Ion eXperiment(sPHENIX)Change Log

Revision HistoryRev. Date ReasonInitial Release May 2018

Page 5: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

5

List of AcronymsALD Associate Laboratory DirectorAS Acquisition StrategyASE Accelerator Safety EnvelopeAY Actual Year DollarsBHSO Brookhaven Site OfficeBNL Brookhaven National LaboratoryC-AD Collider-Accelerator DivisionCAM Control Account MangerCCB Change Control BoardCD Critical DecisionCY Calendar YearDOE U.S. Department of EnergyEIA Electronic Industries AllianceEMCal Electromagnetic CalorimeterES&H Environment, Safety and HealthEVMS Earned Value Management System FPD Federal Project DirectorFPM Federal Program ManagersFY Fiscal YearHCal Hadronic CalorimeterHQ DOE HeadquartersIPR Independent Project ReviewIPT Integrated Project TeamISM Integrated Safety ManagementISMS Integrated Safety Management SystemKPP Key Performance ParameterL2 Level 2L3 Level 3LCC Life Cycle CostsLHC Large Hadron ColliderLRP Long Range PlanMIE Major Item of EquipmentMOA Memorandum of AgreementNEPA National Environmental Policy ActNP Nuclear PhysicsNPP Nuclear and Particle PhysicsNSAC Nuclear Science Advisory CommitteeONP DOE’s Office of Nuclear Physics OPA Office of Project Assessment; Department of EnergyOPC Other Project CostsOPPO Office of Project Planning and OversightOSH Occupational Safety and HealthPARSIIe Project Assessment and Reporting System IIePB Performance BaselinePC Project ControlsPCR Project Change RequestPKPP Preliminary Key Performance ParametersPPEP Preliminary Project Execution PlanPEP Project Execution PlanPHAR Preliminary Hazard Analysis ReportPHENIX Pioneering High Energy Nuclear Interaction experimentPME Project Management ExecutivePMG Project Management GroupPOB Project Oversight BoardQA Quality AssuranceQAP Quality Assurance Plan

Page 6: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

6

QCD Quantum ChromodynamicsQGP Quark Gluon PlasmaR&D Research & DevelopmentRHIC Relativistic Heavy Ion ColliderRLS Resource Loaded ScheduleRM Risk ManagementRMP Risk Management PlanSAD Safety Assessment DocumentSBMS Standards Based Management SystemSC Office of ScienceSiPM Silicon PhotomultiplierssPHENIX Super Pioneering High Energy Nuclear Interaction experimentSTAR Solenoidal Tracker at RHICSVAR Security Vulnerability Assessment ReportTEC Total Estimated CostTPC Time Projection ChamberUPP Ultimate Performance ParametersUSI Unreviewed Safety IssueWBS Work Breakdown StructureWP Work Packages

Page 7: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

1

sPHENIX Preliminary Project Execution Plan

1.0 INTRODUCTION.........................................................................................................................3

1.1 Project Background...................................................................................................................3

1.2 Justification of Mission Need....................................................................................................3

2.0 PRELIMINARY PROJECT BASELINE....................................................................................4

2.1 Preliminary Scope Baseline.......................................................................................................4

2.2 Preliminary Cost Baseline.........................................................................................................6

2.3 Preliminary Schedule Baseline.................................................................................................6

2.4 Work Breakdown Structure...................................................................................................10

2.5 Preliminary Funding Profile...................................................................................................12

3.0 LIFE CYCLE COST...................................................................................................................13

4.0 ACQUISTION APPROACH......................................................................................................13

5.0 Tailoring Strategy........................................................................................................................14

6.0 MANAGEMENT ORGANIZATION AND STRUCTURE......................................................15

6.1 Department of Energy.............................................................................................................16

6.2 Project Management Executive..............................................................................................16

6.3 Federal Program Manager......................................................................................................16

6.4 Federal Project Director..........................................................................................................17

6.5 BNL Associate Laboratory Director......................................................................................18

6.6 BNL Co-Director of the Office of Project Planning and Oversight (OPPO).......................18

6.7 sPHENIX Project Director......................................................................................................18

6.8 sPHENIX Project Manager.....................................................................................................20

6.9 sPHENIX Project Scientist......................................................................................................21

6.10 sPHENIX Resource Coordinator............................................................................................22

6.11 sPHENIX Project Engineer.....................................................................................................22

6.12 sPHENIX Chief Mechanical Engineer...................................................................................23

6.13 sPHENIX Project Controls Manager.....................................................................................23

6.14 Project System/Integration Office..........................................................................................24

6.15 sPHENIX Level 2 Managers...................................................................................................24

6.16 Project Management and Project Support Offices................................................................25

6.17 Integrated Project Team.........................................................................................................25

Page 8: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

2

7.0 Baseline Change Control.............................................................................................................26

8.0 PROJECT MANAGEMENT OVERSIGHT.............................................................................27

8.1 Risk Management including the Risk Management Plan.....................................................27

8.2 Project Reporting Commissioning..........................................................................................28

8.3 Earned Value Management System........................................................................................28

8.4 Project Review.........................................................................................................................29

8.5 Engineering and Technical Readiness....................................................................................29

8.6 Analysis of Alternatives and Conceptual Design Report......................................................29

9.0 ENVIRONMENT, SAFETY, SECURITY, HEALTH AND QUALITY.................................29

9.1 Institutional Requirements.....................................................................................................30

9.2 Organizational Requirements.................................................................................................30

9.3 National Environmental Protection Act.................................................................................30

9.4 Safeguards and Security..........................................................................................................31

9.5 System Engineering.................................................................................................................31

9.6 Value Management..................................................................................................................31

9.7 Value Engineering....................................................................................................................32

9.8 Configuration Management....................................................................................................32

9.9 Quality Assurance....................................................................................................................33

10.0 TRANSITION TO OPERATIONS............................................................................................34

11.0 PROJECT CLOSE OUT.............................................................................................................34

APPENDIX A INTEGRATED PROJECT TEAM CHARTER.....................................................35

A.1 Project Summary........................................................................................................................35

A.2 IPT Members..............................................................................................................................35

A.3 Operating Principles...................................................................................................................35

A.4 Team Responsibilities.................................................................................................................36

APPENDIX B PRELIMINARY UPP’S..........................................................................................36

List of Tables:..........................................................................................................................................36

List of Figures:.........................................................................................................................................37

Page 9: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

3

1.0 INTRODUCTION

1.1 Project Background

The Preliminary Project Execution Plan (PPEP) describes the management and project execution processes that will be used to ensure that the sPHENIX MIE will be completed on time and within budget, meeting all of its Threshold Key Performance Parameters (KPPs). The Preliminary PEP defines the preliminary project scope, describes the organizational framework and overall management system for the project. It identifies roles and responsibilities for project participants. It also describes the formal change control process by which the project scope, schedule and budget can be revised. The PPEP will be reviewed, revised and updated as appropriate with the final PEP completed at CD-2/CD-3.

The sPHENIX MIE will be a major upgrade to the PHENIX experiment that will enable the precision characterization of jets produced in AA, pA and pp collisions at the RelativisticHeavy Ion Collider (RHIC) located at Brookhaven National Laboratory (BNL). The experiment will also collect a large sample of upsilons with a mass resolution that allows for their separation into three mass states, and the study of their behavior on different distance scales. sPHENIX provides excellent opportunities complimentary to measurements being made at the Large Hadron Collider (LHC) at CERN, and extends the RHIC physics program in ways that fully exploits RHIC’s unique performance capabilities.

1.2 Justification of Mission Need

The mission of the Office of Science (SC) is to deliver the scientific discoveries and major scientific tools that transform our understanding of nature and advance the energy, economic, and national security of the United States. SC accomplishes this mission through the direct support of research, construction, and operation of national scientific user facilities, and the stewardship of ten world-class national laboratories. The SC national laboratories collectively comprise a preeminent federal research system that develops unique, often multidisciplinary, scientific capabilities beyond the scope of academic and industrial institutions, to benefit the nation’s researchers and national strategic priorities.

The Nuclear Physics (NP) program plans, constructs, and operates major scientific user facilities and fabricates experimental equipment to serve researchers at universities, national laboratories, and industrial laboratories as part of its strategic mission. The program provides world-class, peer- reviewed research results in the scientific disciplines encompassed by the NP mission areas under the mandate provided in Public Law 95-91 that established the Department of Energy (DOE).

Page 10: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

4

The DOE NP program addresses three broad, interrelated scientific thrusts in pursuit of its mission: Quantum Chromodynamics (QCD), Nuclei and Nuclear Structure and Astrophysics, and investigations of Fundamental Symmetries using neutrons and nuclei. sPHENIX addresses goals within the “QCD investigations” within the NP program. Over the last two decades, the heavy ion nuclear physics component of the QCD scientific thrust has focused on the discovery and characterization of the Quark Gluon Plasma (QGP): a form of matter believed to have last naturally existed in the universe approximately one microsecond after the Big Bang. Since the discovery of the QGP at the BNL RHIC over ten years ago, and subsequent confirmation by experiments at CERN’s LHC, a number of important characteristics of the QGP have been measured. Though great progress has been made over the last twenty years, the 2015 Nuclear Science Advisory Committee (NSAC) Long Range Plan (LRP) identified a vital QGP-related research question that remains unaddressed. The field must “probe the inner workings of the quark gluon plasma by resolving the properties at shorter and shorter length scales.” A virtually identical goal was recommended in the 2010 National Academy Study,” Nuclear Physics, Exploring the Heart of Matter.” The sPHENIX MIE enables the pursuit of this directive at RHIC. The LRP states: “This program requires large samples of jets in different energy regimes, with tagging of particular initial states, for example, in events with a jet back-to-back with a photon. The full power of this new form of microscopy will only be realized when it is deployed at both RHIC and the LHC, as jets in the two regimes have complementary resolving power and probe QGP at different temperatures, with different values of the length scale at which bare quarks and gluons dissolve into a near perfect liquid”. sPHENIX is needed to make these measurements feasible. Neither the existing STAR nor PHENIX experiments can make the required measurements with the necessary sensitivity.

Obtaining the scientific goals of sPHENIX has been identified by both the recent NSAC LRP and the National Academy study as needed to carryout NP’s scientific mission. There is currently a gap in capabilities that needs to be addressed in order to reach those goals.

2.0 PRELIMINARY PROJECT BASELINE

This section documents the project’s preliminary Performance Baseline (PB) that consists of the scope, cost, schedule (time line to the CD-4 date), funding profile, and other related information. Lower tier documents will capture the details and plans for resource cost/schedule/scope and project life cycle from the project initiation through the start of operations to the project closeout.

2.1 Preliminary Scope Baseline

The preliminary scope baseline for the sPHENIX Project is:

A Time Projection Chamber (TPC), Electromagnetic Calorimeter (EMCal), a Hadronic

Page 11: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

5

Calorimeter (HCal) all covering 2 in azimuth. The TPC and HCal have pseudorapidity coverage of -1.1 ≤ ≤ 1.1. The EMCal has pseudorapidity coverage of -0.85 ≤ ≤ 0.85

A Minimum Bias Trigger detector (MBD) Readout electronics to fully instrument the TPC, EMCal, HCal and MBD A Data Acquisition system with the capability to readout the TPC, EMCal, HCal and

MBD with an event rate and data-logging rate commensurate with the sPHENIX physics goals.

A DAQ/Trigger system that can provide minimum bias and energy cluster triggers at a rate necessary to carry out the sPHENIX physics program in AA, pA and pp collisions at RHIC.

Project Management to carry the project scope through to a successful on time and on budget completion.

The preliminary KPPs are shown in Table 1. The Threshold KPPs are the minimum parameters against which the project performance is measured at CD-4 project completion. The Objective KPPs are the stretch performance parameters that will be achievable within the CD-2 project scope, cost and schedule baseline when established. The KPPs are chosen because they comprise a set of minimum test results that once demonstrated, will allow one to conclude with confidence that sPHENIX will be able to meet its mission need after a period of commissioning, calibration and data-taking. The KPPs define tests for each of the sPHENIX Level 2 deliverables. The tests will establish that the subsystems are working at a performance level that is consistent with their design. The difference between the Threshold and Objective KPPs is essentially the difference between the expected Level 2 subsystem performance soon after initial power-up and the performance after a period of debugging and maintenance. In addition to these KPPs, preliminary Ultimate Performance Parameters (UPPs) have been defined. The UPPs are listed in Appendix B, Table 8 and describe the performance needed after project completion to realize the scientific goals of the project.

System Demonstration or Measurement Threshold KPP’s Objective KPP’s

Time Projection Chamber Preinstall,Bench Test

≥ 90% live channels based onlaser, pulser, cosmics

≥ 95% live channels based onlaser, pulser, cosmics

Time Projection Chamber Preinstall,Bench Test

Ion Back Flow ≤ 2% perQuad GEM Module

Same

Time Projection ChamberPreinstall,Bench Test w/comics

≥ 90% single hit

efficiency / mip track

≥ 95% single hit

efficiency / mip track

Time Projection ChamberFront End Electronics

Preinstall,Bench Test

Cross talk ≤ 2% each channels Same

EM Calorimeter Preinstall,Bench Test

≥ 90% live channels basedon LED, cosmics

≥ 95% live channels basedon LED, cosmics

Hadronic Calorimeter Preinstall,Bench Test

≥ 90% live channels based onLED, cosmics

≥ 95% live channels based onLED, cosmics

Page 12: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

6

EM Calorimeter Preinstall,Bench Test

Each sector with an absoluteenergy pre-calibration to a precision of ≤ 35% RMS

Same

Hadronic Calorimeter Preinstall,Bench Test

Each sector with an absoluteenergy pre-calibration to a precision of ≤ 20% RMS

Same

Min Bias Trigger Detector Preinstall,Bench Test

≥ 90% live channels basedon laser.120 ps/channels timing resolution w/ Bench Test

≥ 95% live channels basedon laser.100 ps/channels timing resolution w/ Bench Test

DAQ/Trigger Event rate 10 kHz with randompulser

15 kHz with randompulser

DAQ/Trigger Data LoggingRate

10 GBit/s with pulser Same

Table 1: Table of Preliminary Key Performance Parameters

2.2 Preliminary Cost Baseline

The preliminary Total Project Cost range of the sPHENIX MIE is $26.5-34.5M AY $. The breakdown by WBS Level 2 can be seen in Table 2. The preliminary cost baseline includes the contingency estimate of an overall average cost contingency of 30%. The contingency was based on a graded contingency rating given to each WBS element where the grade applied was determined from the confidence in the choice of a specific item, source of pricing information, maturity of the design, and other similar factors.

WBS Level 2 WBS Description Cost in AY K$1.1 Project Management 1,4711.2 Time Projection Chamber 3,4841.3 EM Calorimeter 5,8731.4 Hadron Calorimeter 3,4641.5 Calorimeter Electronics 4,5571.6 DAQ/Trigger 1,5501.7 Min Bias Trigger Detector 132

Sub-total 20,531Contingency 6,019Total Project Cost 26,550

Table 2: sPHENIX MIE Total Project Cost in AYk$.

2.3 Preliminary Schedule Baseline

The Level 1 Critical Decision (CD) milestones of the Major Item of Equipment (MIE) are seen in Table 3. The MIE, CD-4 date is Q1 FY2023, which includes 14 months of schedule contingency. The sPHENIX Project Summary Schedule is shown in Figure 1. The Project early

Page 13: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

7

completion date is October 2021. The major milestones of the Level 2 subsystem that are the MIE deliverables can be seen in Table 4. The integrated Resource-Loaded Schedule (RLS) has a Critical Path (CP) that goes through the procurement, fabrication and assembly of the EMCal prototype. It proceeds through Calorimeter Electronics procurement, fabrication and assembly of the Silicon Photomultipliers (SiPM). Finally the CP goes through EMCal Module/Sector (production) fabrication and assembly, followed by EMCal sector testing. The RLS CP is shown in Figure 1.

A CD-3A authorization will be requested at the time of CD-1 for long lead time procurements that are needed early in the project in order to meet the project completion milestone and have sPHENIX ready to take data from RHIC collisions in Calendar Year (CY) 2023. A CD-3 authorization will be requested at the same time as CD-2 authorization. The plan is based on the assessment by the project team that the technical design and R&D of all Level 2 systems will be 90% complete in the aggregate at the time of the CD-2 review. The scope of the long lead procurements is: Scintillating Tiles for the HCal, SiPMs for the EMCal and HCal readout, Scintillating Fibers Production order (50% of total) for the EMCal, Tungsten Powder Production Order (50% of Total) for the EMCal and the cost is $4,363K including 30% contingency. These are long lead procurements because they are on or near the critical path, or are part of components/systems on or near the critical path or are a risky procurement from a foreign vendor.

Milestone Schedule Date

CD-0, Approve 9/16/2016 (A)CD-1/3A, Approve Alternative Selection and Cost Range, Long Lead Procurements Q4 FY 2018

CD-2/3, Approve Performance Baseline Q4 FY 2019

CD-4, Approve Project Completion Q1 FY 2023Table 3: Table of sPHENIX MIE Critical Decision Milestones

Page 14: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

8

Figure 1: sPHENIX MIE Summary Schedule. The red line shows the project critical path.

Page 15: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

9

WBS Level 2 Project Milestones Scheduled Dates1.02.06 TPC DAM Production Readiness Review Q4FY181.05.02 HCal Preproduction Electronics Complete Q2FY191.02.02 TPC Module Production Readiness Review Q2FY191.04.02 Outer HCal Lifting Fixture and Support Design Complete Q4FY191.05.01 EMCal/HCal Sensor Production: - Delivery Complete Q2FY201.05.02 HCal SiPM Boards Assembly Complete: Production Q2FY201.02.01 GEM Production Complete Q3FY201.04.02 First Outer HCal Sector Ready to Install Q3FY201.06.04 Timing System Production: Timing System Ready to

Operate

Q3FY201.05.02 HCal Electronics Complete: Production Q4FY201.02.04 TPC R3 Production Ends Q4FY201.06.02 Trigger LL1 Preproduction Complete Q1FY211.04.02 Last Outer HCal Sector Ready to Install Q1FY211.02.07 TPC Cooling System Complete Q1FY211.02.01 TPC Ready to Install (Assembly Complete) Q2FY211.05.02 EMCal Electronics Complete Q3FY211.05.03 Calorimeter Electronics Complete Q3FY211.03.01 EMCal Final Blocks Arrive at BNL Q4FY211.07.04 Min Bias Detector Ready to Install Q4FY211.06.01 DAQ Production: DAQ Ready to Operate Q4FY211.03.02 EMCal Ready to Install Q1FY221.01.01 Early Project Completion Q1FY22

Table 4: Level 2 Subsystem Milestones of the sPHENIX MIE

Page 16: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

10

2.4 Work Breakdown Structure

The sPHENIX MIE has been organized into a WBS that is documented in the WBS dictionary.The Level 2 WBS is the Control Account level for the project and can be seen in Figure 2.

Figure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE

Page 17: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

11

Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX MIE. The WBS Dictionary describes the project scope to Level 3 of the WBS 1.1 – 1.4.

Page 18: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

12

Table 5b: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX MIE.The WBS Dictionary describes the project scope to Level 3 of the WBS 1.5 – 1.7.

2.5 Preliminary Funding Profile

The Total Project Cost for sPHENIX is estimated to be in a range $26.5-34.5M AY. The funding profile is shown in Table 6. This project is implemented with existing funding from within the RHIC facility operations budget provided by NP within the Office of Science.

Funding Profile in AY k$

PriorYrs FY17 FY18 FY19 FY20 FY21 FY22 Total

Pre-R&D

R&D 1,513 4,260 350 6,123CDR 100 200 300

Construction 5,310 6,560 4,610 3,647 20,127Pre-Ops

TEC 5,310 6,560 4,610 3,647 20,127

OPC 1,613 4,460 350 6,423

Total Project Cost 1,613 4,460 5,660 6,560 4,610 3,647 26,550

Table 6: Preliminary Funding Profile

Page 19: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

13

3.0 LIFE CYCLE COST

The costs are discussed for the three phases of the sPHENIX life cycle:

Conceptual Design and R&D Fabrication Operations

The project life cycle costs for the OPC, fabrication and operation of sPHENIX is estimated to be approximately $86.5–94.5M AY. This includes the cost of sPHENIX fabrication and five years of sPHENIX Operations. There is confidence in the estimate for sPHENIX operating costs because the scale and complexity of sPHENIX is known to be very similar to the PHENIX experiment as determined by staff members of the sPHENIX Management team who were involved in PHENIX Operations throughout the experiment’s 16 year operating period. The size of the sPHENIX operating support team, as well as annual consumable and maintenance costs, is estimated to be very similar to that of the PHENIX experiment. The operating costs of 10M in FY16 dollars escalated to the sPHENIX operating period of FY23-FY27 at 2% escalation per annum results in a five year sPHENIX operating cost of $60M AY. The estimate presumes that after five years of operations, the sPHENIX Detector is re-purposed for other research activities.

The capital value of sPHENIX will be added to the capital value of the RHIC facility at the completion of the sPHENIX project. It is expected that sPHENIX will operate until the end of the operations of the RHIC facility. At the end of RHIC operations, sPHENIX will either be re-purposed for an application that is commensurate with the future science mission of facilities currently in use by RHIC, such as an Electron Ion Collider, or it will be decommissioned. The cost of re-purposing is not included in the Lifetime Costs due to the negligible costs estimated for repurposing sPHENIX equipment for future use.

4.0 ACQUISTION APPROACH

Acquisition of sPHENIX will be conducted by BNL. BNL will direct the sPHENIX project management team in the execution of the project and delegate to the team its authority for project execution. The BNL sPHENIX Project Office will manage the distribution-to and expenditure-of DOE funds including collaborating sPHENIX institutions. The project scope to be accomplished at collaborating institutions will be documented in Memoranda of Agreements between BNL and collaborating institutions. Statements of work between BNL and the collaborating institutions, including frequent milestones, will be used to track progress of their contributions to the project. The acquisition approach for the project is described in detail in the sPHENIX Acquisition Strategy (AS).

BNL will collaborate and work with many institutions, including other DOE National Labs and Universities (i.e. Stony Brook University). BNL will be responsible for overall project

Page 20: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

14

management but collaborators have will hold key roles as the WBS Level 2 Managers, Level 3 Managers and Control Account Managers.

5.0 Tailoring Strategy

DOE Order 413.3B allows for the development of a Tailoring Strategy for each project, based on the risk, complexity, visibility, cost, safety, security, and schedule of the project. The requirements of the Order are to be applied on a tailored basis as appropriate to the project. Tailoring is subject to the Project Management Executive’s (PME) approval and is identified prior to the impacted Critical Decision and approved as early as possible. The sPHENIX MIE strategy has been tailored to allow for the early procurement of long lead-time items starting in FY19. The project will ask for CD-3A approval on specific long lead-time items at the CD-1/3A review. The long lead-time items include Silicon Photomultipliers for the calorimeters, scintillating tiles for the HCal, tungsten powder and scintillating fibers for the EMCal. Aspects of the sPHENIX design associated with the long lead-time items have been quickly brought to a mature state. In addition, due to the advanced nature of both the R&D and detector design, the sPHENIX MIE is proposing a concurrent CD-2/CD-3 review. The project will have a single CD-4 (Approve Project Completion) milestone.

Page 21: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

15

6.0 MANAGEMENT ORGANIZATION AND STRUCTURE

Figure 3: The sPHENIX Organization Chart

The sPHENIX MIE is managed inside the Nuclear and Particle Physics Directorate at BNL. The sPHENIX effort divides into the seven WBS elements shown in Table 2 that are known as the Level 2 deliverables. The organization of Level 2 Managers, Level 3 Managers and Control accounts can be seen in Figure 2. Level 2 managers are each responsible for one of the seven items. They report directly to the sPHENIX Project Management team. The Project Management team reports directly to the BNL office of the Associate Lab Director who in turn reports to the Federal Project Director (FPD) in BHSO. The responsibilities of the members and organizations managing the sPHENIX MIE are as follows:

Page 22: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

16

6.1 Department of Energy

Funding for the sPHENIX MIE is redirected funds from the RHIC Facility Operations provided by NP with the DOE SC. The SC Office of Project Assessment (OPA) provides independent oversight of the project. The Deputy Director for Science Programs in DOE SC approves deviations and Level 0 baseline changes.

6.2 Project Management Executive

The Associate Director of the Office of Nuclear Physics in the DOE Office of Science will serve as the PME. The PME has full responsibility for project planning and execution, and for establishing broad policies and requirements for achieving project goals. The Director of the Facilities and Project Management Division in NP concurs on project documentation submitted to the PME for approval and provides general guidance to the Project and Program Directors.The PME:

Approves Critical Decisions Ensures that the FPD appointed to the project is qualified and has appropriate

communication and leadership skills prior to designation Approves the Acquisition Strategy and Project Execution Plan. Initiates definition of mission need and objectives of the project. Approves Level 1 baseline changes Initiates formal periodic reviews of the project Provides HQ technical guidance and resources to the FPD and Federal Program Manager. Supports and recommends funding for the construction of this project.

6.3 Federal Program Manager

The Federal Program Manager (FPM) serves as the primary DOE NP point of contact for the sPHENIX MIE and is charged to fulfill NP responsibilities for project funding, coordination, oversight, and communication with other HQ offices. The DOE FPM:

Functions as DOE HQ point-of-contact for project matters. Serves as the representative in communicating the interests of the SC program. Coordinates with FPD, IPT, other SC Staff offices, and DOE HQ program offices, as

needed to execute the project. Assists with budget formulation. Reviews and provides recommendations to senior management on Level 0 and 1 baseline

changes. Conducts monthly or quarterly project reporting/meetings.

Page 23: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

17

Reviews documents (Mission Need Statement, AS, PPEP, IPT Charter, etc.) and recommends approval.

Reviews project progress reports and deliverables. Supports formal periodic reviews of the project, including DOE independent project

reviews and tracks issues to resolution Enter the monthly project assessment within the Project Assessment and Reporting

System (PARSIIe)

6.4 Federal Project Director

The FPD is from the Brookhaven Site Office (BHSO) and leads the sPHENIX Integrated Project Team (IPT) and implements DOE Order 413.3B via a tailored approach that optimizes control, progress, performance, and success of the sPHENIX MIE. The FPD:

Serves as the single point of contact between Federal and contractor staff for all matters relating to the project and its performance.

Appointed as the Contracting Officers Representative, as determined by the Contracting Officer.

Prepares and maintains the IPT Charter and operating guidance with IPT support and ensures that the IPT is properly staffed. Defines and oversees the roles and responsibilities of each IPT member.

Leads the IPT and provides broad program guidance. Delegates appropriate decision-making authority to the IPT members.

Ensures development and implementation of key project documentation. Defines project cost, schedule, performance, and scope baselines. Ensures design, construction, environmental, safety, security, health, and quality efforts

performed comply with the contract, public law, regulations, and Executive Orders. Ensures timely, reliable, and accurate integration of contractor performance data into

the project’s scheduling, accounting, and performance measurement systems, to include Project Assessment and Reporting System (PARSIIe).

Evaluates and verifies reported progress. Makes projections of progress and identifies trends

Approves changes in compliance with the approved change control process documented or referenced in the PEP. Provides recommendations for Level 0 and 1 Project Change Requests (PCRs).

Page 24: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

18

6.5 BNL Associate Laboratory Director

The Associate Laboratory Director (ALD) for the Nuclear and Particle Physics of BNL.

Represents BNL in its capacity as Lead Laboratory, and ensures BNL Lead Laboratory responsibilities are met in executing the project within scope, cost, and schedule in a safe and responsible manner.

Closely monitors the progress of the sPHENIX MIE. Organizes periodic independent reviews to be carried out by committees under his

charge. Appoints the sPHENIX Project Director Ensures access to laboratory/contractor resources, systems, and capabilities required to

execute the project. Approves major subcontracts Identifies the redirection of funding that supports the funding profile of the project and

allows the continuation of support for other operational priorities.

6.6 BNL Co-Director of the Office of Project Planning and Oversight (OPPO)

The Co-Director of the Office of Project Planning and Oversight for the Nuclear and Particle Physics Directorate of BNL:

Oversees the sPHENIX MIE for the BNL Nuclear and Particle Physics Directorate. Chairs the Project Management Group (PMG) whose function is to provide expert

project management and technical advice to both the ALD for Nuclear and Particle Physics and the sPHENIX Project Management team.

Facilitates the coordination of different aspects of the sPHENIX upgrade program Organizes periodic internal independent cost and schedule, technical reviews as

appropriate for the monitoring of the progress of the project, cost and schedule performance and major project risks.

6.7 sPHENIX Project Director

The sPHENIX Project Director leads the sPHENIX Project Management team. The Project Director is appointed by and reports directly to the BNL ALD for Nuclear and Particle Physics, and to the FPD and FPM through the ALD’s office. The sPHENIX Project Director is responsible for ensuring that the delivered sPHENIX MIE meets the CD-0 mission need. The Project Director is responsible for ensuring that adequate direct, indirect, and support resources are available for the successful execution of the sPHENIX MIE. The Project Director provides senior management oversight, provides direct access to the BNL Nuclear and Particle Physics ALD and BNL Laboratory Director, and reviews and approves all PCRs before submission for

Page 25: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

19

DOE approval. The responsibilities of the Project Director include, but are not limited to, the following list. The Project Director:

Approves the project organization in consultation with the ALD and the OPPO for Detector Projects

Oversees the sPHENIX Project Manager and supports the DOE BHSO FPD in implementing project processes.

Represents the project in interactions with the DOE Collaborates with the Project Manager and the Project Scientist to provide overall

direction to the project. Establishes clear and achievable project objectives (KPPs) in consultation with the FPM

and FPD. Successfully executes the sPHENIX MIE scope. Assembles the staff and resources necessary to complete the sPHENIX MIE. Collaborates with the Project Manager in appointing Level 2 Managers, Level 3

Managers and Control Account Managers (CAMs) for the project whom will be responsible for managing bid package(s), overseeing daily technical and managerial oversight of specific assigned WBS tasks from design through construction, and for preparing change requests in conformance with Baseline Change control.

Manages the completion of Project deliverables as defined in the PEP. Ensures that the project deliverables meet sPHENIX functional requirements. Ensures timely resolution of critical issues within Project Director’s control Identifies risks to scientific and technical performance; works with the Project Manager

to control project risks. Defines areas of collaboration and relationship between sPHENIX other BNL

departments and divisions, and other institutions participating in sPHENIX. Develops appropriate Memoranda of Agreement (MoA) and collaborative agreements.

Works with Project Manager, Resource Coordinator and Project Engineer to define the WBS structure and to establish intermediate milestones

In consultation with the Project Scientist and Resource Coordinator, allocates Management Reserve and contingency funds according to the procedure defined in the Baseline Change Controls Procedure.

Provides monthly financial reports to DOE-ONP and the BNL Director of OPPO for Detector Projects.

Approved major subcontracts. Implements a performance measurement system. Assures that work is performed in compliance with the BNL Environmental, Safety and

Health requirements.

Page 26: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

20

6.8 sPHENIX Project Manager

The sPHENIX Project Manager reports to the sPHENIX Project Director and is responsible for the successful execution and closeout of the sPHENIX MIE. Authority flows from the sPHENIX Project Director to Project Manager by delegation of all day-to-day decision-making. The Project Manager manages design, development and delivery of all sPHENIX deliverables, and ensures compliance to cost, schedule, and technical performance. The responsibilities of the Project Manager include, but are not limited to, the following list.

Oversees the sPHENIX design, construction and acceptance. Establishes technical and administrative controls and monitoring to ensure the project is

executed within the approved cost, schedule, and technical scope Identifies and manages project risks. Leads project meetings, participates in management meetings, and communicates project

status and issues. Implements an Earned Value Management System (EVMS) to track performance against

the approved project baseline. Submits Project Change Requests (PCRs) to the Project Director for review and approval

prior to Project Director’s submission of the PCR to DOE for review and approval. Balances the demand for project quality, scope, time, and cost. Collaborates with the Project Director and Project Scientist in setting the direction of the

sPHENIX MIE. Collaborates with the Project Director to assemble the staff and resources necessary to

complete the sPHENIX MIE. Collaborates with the Project Director in appointing Level 2 Managers, CAMs and Level

3 Managers for the project whom will be responsible for managing bid package(s), overseeing daily technical and managerial oversight of specific assigned WBS tasks from design through construction, and for preparing change requests in conformance with Baseline Change Control.

Communicates the functional requirements to the Level 2 managers, Level 3 managers and CAMs

Ensures that all sPHENIX MIE deliverables meet the technical and performance requirements

Executes the project in compliance with the National Environmental Policy Act (NEPA) and other applicable ES&H rules and regulations.

Ensures that safety, environmental, quality assurance safeguards and security responsibilities and requirements are integrated into all phases of the project, and that project activities are conducted in a safe and environmentally-sound manner.

Directs the work of the Project Systems Scientist and Systems Integration Office Develops and maintains project documentation. Prepares and submits monthly and quarterly progress reports to DOE.

Page 27: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

21

6.9 sPHENIX Project Scientist

The sPHENIX Project Scientist is responsible for ensuring that the project meets the sPHENIXExperiment objectives as described in the approved Mission Need Statement (CD-0). The Project Scientist reports to the Project Manager. The responsibilities of the Project Scientist include, but are not limited to the following:

Provides the project with oversight regarding the technical specifications to ensure that the project will meet the sPHENIX scientific goals.

Communicates with the sPHENIX project team and the Co-Spokespersons to negotiate any revisions or clarifications to sPHENIX scientific and technical requirements.

Works with the sPHENIX engineering team to ensure that the science requirements flow to the sPHENIX MIE components, and that the performance requirements are being adequately verified.

Works with the Project Director, Project Manager and Project Engineer to evaluate the impact of design or performance revisions to scientific requirements.

Collaborates with the Project Director and Project Manager in setting the technical direction and defining the technical requirements of the sPHENIX MIE.

Communicates the functional requirements to the Level 2 managers, Level 3 managers and CAMs.

Ensures that all sPHENIX MIE deliverables meet the technical and performance requirements necessary to meet Mission Need.

Serves as a member of the Integrated Project Team.

Page 28: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

22

6.10 sPHENIX Resource Coordinator

The sPHENIX Resource Coordinator is responsible for managing all activities of the sPHENIX Project Office. The Resource Coordinator is appointed by and reports directly to the sPHENIX Project Director. The responsibilities of the Resource Coordinator include, but are not limited to, the following list. The Resource Coordinator:

Oversees the management of the sPHENIX budget, sPHENIX labor (reporting), Resource Loaded Schedule, Risk Registry and the Earned Value Management system.

Ensures sPHENIX MIE compliance with DOE 413.3B regulations. Supervises the sPHENIX Project Management Office Provides regular budget and labor data reports to the Project Director. Prepares reports

for BNL and DOE as required. Develops and Implements the sPHENIX Procurement Plan. Develops and maintains project documentation on sPHENIX fiscal, project and labor

matters. Advises the Project Director on all matters relating to project resources including,

budgets, labor, property, space and facilities. Serves as sPHENIX liaison with BNL Procurement and Property Management for

contract administration, procurements and property issues.

6.11 sPHENIX Project Engineer

The sPHENIX Project Engineer is responsible for managing all engineering activities within the sPHENIX Project. The Project Engineer is appointed by and reports directly to the sPHENIX Project Director. The responsibilities of the Project Engineer include, but are not limited to, the following list.The Project Engineer:

Supervises all engineering associated with the sPHENIX MIE including all day-to-day engineering activities. Assigns engineering responsibilities as appropriate.

Supervises the sPHENIX Project Support Office. Collaborates with the Project Director to assemble the staff and resources necessary to

complete the sPHENIX MIE. Is responsible for the Scheduling and Management of Design, Safety and Readiness

reviews. Coordinates the reviews together with the assistance of the Project Manager, Chief Mechanical engineer and the ESH Coordinator.

Under the direction of and by delegation from the Project Director, the Project Engineer executes project scope and supplies the engineering deliverables associated with the MIE and other sPHENIX parallel efforts under the direction of and as designated by the Project Director.

Page 29: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

23

6.12 sPHENIX Chief Mechanical Engineer

The sPHENIX Chief Mechanical Engineer oversees the mechanical engineering content of all tasks within the sPHENIX Project scope. He is appointed by and works directly for the sPHENIX Project Director. The Chief Mechanical Engineer:

Serves as the Integration Engineer in the Office of System Integration Supervises all technicians working on sPHENIX MIE activities at BNL. Monitors all

technical activities at sPHENIX MIE remote sites and provides regular reports on those activities to the Project Director, Project Manager and Project Engineer.

Assists the Project Engineer in the scheduling, planning and oversight of Design, Safety and Readiness reviews

Communicates all the mechanical engineering requirements to the Level 2 managers and the Control Account Managers.

6.13 sPHENIX Project Controls Manager

The sPHENIX Project Controls (PC) Manager is the Level 2 Manager for sPHENIX MIE WBS 1.1 Project Management. The Project Controls Manager is responsible for monitoring and reporting the EVMS of the Project. The PC is appointed by and works directly for the sPHENIX Project Director. The Project Controls Manager:

Monitors and report the EVMS of the Project including uploading monthly financial information to DOE via PARSIIe.

Manages the Risk Registry and Risk Mitigation Plan. Updates the Resource-Loaded Schedule under direction of the Project Director, Project

Manager or Resource Coordinator. Advises the Project Director in all matters of Project Controls including Cost, Schedule,

Earned Value, Contingency, Risk and Risk Mitigation Develops and provides sPHENIX MIE documentation and reports as requested by the

Project Director, Project Manager or Resource Coordinator for all reviews, including sPHENIX DOE-OPA reviews, BNL Director’s reviews.

Provides Project Controls data to the sPHENIX MIE team and participates in monthly and quarterly reporting.

Page 30: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

24

6.14 Project System/Integration Office

The sPHENIX Project System/Integration Office is responsible for managing the sPHENIX team responsible for assuring that all sPHENIX Level 2 components are fully integrated into the global sPHENIX design, have well-defined interface points with other subsystems and closely associated parallel projects such as the components of the Infrastructure and Facility upgrade or the Intermediate Tracker. The Project System/Integration Office:

Leads a system integration team containing the sPHENIX Integration Engineer, technical and engineering representatives from each of the Level 2 subsystems and representatives from each component of parallel projects closely associated with sPHENIX such as the Infrastructure and Facility upgrade.

Holds regular meetings of the system integration team. Mediates integration disputes between subsystems and identifies and resolves all system

interface issues. Reports to the Project Manager

6.15 sPHENIX Level 2 Managers

The sPHENIX Level 2 Managers are also the Control Account Managers. Each sPHENIX Level 2 Manager is responsible for one of the seven sPHENIX MIE components: Project Management, Time Projection Chamber, EM Calorimeter, Hadronic Calorimeter, Calorimeter Electronics, DAQ/Trigger, and Minimum Bias Trigger Detector. They report directly to the sPHENIX Project Manager, and working together with the Project Management team are responsible for the design, construction, installation, and testing of their subsystem, in accordance with the performance requirements, schedule, and budget. The sPHENIX Level 2 Managers:

Execute the activities within their Control Accounts within the time and budget constraints stated in the Resource-Loaded Schedule (RLS).

Collaborate with the sPHENIX Project Management team to assemble the staff, resources, and schedule needed to complete the subsystem;

Collaborate with the Project Director, Project Manager and Project Scientist to define, manage, and coordinate scientific requirements; communicate the subsystem design requirements to the staff;

Ensure that subsystems meet sPHENIX system design requirements, including interfaces; Carry out the design, construction and assembly of the subsystem in accordance with the

scope, schedule, and budget, assuming funding and resources as described in the PEP; Control project risks within the WBS Level 2 and update the Risk Registry and Risk

Management Plan as appropriate together with the Project Director and Project Manager. Submit Baseline Change Proposals when changes affect technical, cost or schedule

deliverables Generate and archive the WBS Level 2 project documentation;

Page 31: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

25

Provide regular reports on the status of the subsystem to the Project Manager; Provide oversight of sPHENIX quality assurance program and implement QA within

their relevant sPHENIX MIE subsystem; Provide monthly EVMS reports of the subsystem to Project Controls. Ensure the work is performed safely and in compliance with the Integrated Safety

Management System (ISMS) rules.

6.16 Project Management and Project Support Offices

The Project Management Office is overseen by the Resource Coordinator. The Project Management Office includes the Project Controls Manager and the Resource Coordinator. The Project Support Office is overseen by the Project Engineer. The Project Support Office contains the Environment Safety and Health Manager, the Quality Assurance Manager and the Software Support Manager. The Project Management Office and Project Support Office each have specific responsibilities for project documentation preparation, administration and archiving their respective documents.

6.17 Integrated Project Team

The IPT mission is to provide strategic planning, coordination, and communication for the sPHENIX Project to ensure the project’s objectives are achieved on schedule, within budget, and consistent with quality, environmental, safety, and health standards. The IPT insures that project management is carried out with integrity and in compliance with applicable laws. The team generally meets every two weeks, depending on project activities, supplemented with specific issue-resolution meetings. It is the responsibility of the FPD to ensure the necessary skills are always represented to meet project needs. The IPT members:

Support the FPD. Work with DOE BHSO Contracting Officer to develop a project Acquisition Strategy and

Acquisition Plan, as applicable. Ensure project interfaces are identified and defined Assist with completion of the project environment, safety, health, security, risk, and

quality assurance requirements. Identify and define appropriate and adequate project technical scope, schedule and cost

parameters Perform periodic reviews and assessments of project performance and status against

established performance parameters, baselines, milestones, and deliverables. Plan and participate in project reviews, audits, and appraisals as necessary. Review and comment on project documents and deliverables (e.g. drawings,

specifications, procurements, and construction packages). Review changes requests (as appropriate) and supports the CCB as requested Participate, as required, in Operational Readiness Reviews or Readiness Assessments.

Page 32: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

26

Members of the IPT are the Federal Project Director (chair), the Federal Program Manager, the sPHENIX Project Director, the sPHENIX Project Manager, the sPHENIX Project Scientist, the sPHENIX Project Engineer and the sPHENIX Resource Coordinator. Changes in IPT membership will be documented as revisions to the Charter, with approval from the FPD. The Appendix A lists the IPT Charter

7.0 Baseline Change Control

Changes to the technical, cost, and schedule baselines established at CD-2/CD-3 will be controlled using the thresholds described in Table 4. Project Change Requests (PCRs) will be approved as necessary to modify the project baseline. To initiate a baseline change, the Project Director, the Project Manager, Project Engineer, or a Level 2 Manager submits a PCR form to the sPHENIX Change Control Board (CCB). The CCB advises the FPD on actions to be taken on PCRs. All PCRs become part of the permanent project documentation maintained by the Project Manager. All Level 3 PCRs will be approved by the Project Director. All PCRs above Level 3 thresholds will be either endorsed or rejected by the Project Director. If endorsed, the PCR will be submitted by the Project Director to the FPD. All PCRs surpassing the Level 3 thresholds will be reviewed by the Change Control Board and acted on by the FPD as recommended. For PCRs exceeding the thresholds for Level 2, the FPD will forward the PCR to DOE Headquarters with the CCB recommendation. The CCB consists of the Federal Project Director (chair), the sPHENIX Project Director, the sPHENIX Project Manager, the sPHENIX Project Engineer and the sPHENIX Resource Manager. Technical experts will be included in the CCB as appropriate.

If a PCR is approved, a copy of the approved PCR, together with any qualifications or further analysis or documentation generated in considering the request, is returned to the requester and copies are sent to the official at the next higher control level and to the Project Director for filing. If approval is denied, a copy of the PCR, together with the reasons for denial, is returned to the requester, and a copy is filed. The official at the next higher control level may review the granted change to ensure proper application of the procedure and consistency of the change with the goals and boundary conditions of the project. Any contingency usage will require the approval of the FPD or PME as defined through the change control process. After the cumulative threshold has been reached and the next higher authority has been notified and has approved the changes, the cumulative cost thresholds will reset.

Page 33: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

27

Deputy Director for SC:

Change Control Level 0

Project Management Executive: Associate Director of Science for Nuclear Physics:

Change Control Level 1

Federal Project Director*:

Change Control Level 2

sPHENIX Upgrade Project Director

Change Control Level 3

Scope Any changes in scope and/or performancethat affects theability to satisfy the mission need

Any changes that negatively impact achieving the KPP’s as defined in the PEP.

Changes in scope affecting the technical performance WBS Level 2 components that do not affect the KPP’s or major changes in the technology or approach to Level 2 WBS components.

Changes to technical scope below the FPD threshold.

Cost Any increase in theTotal Project Cost of the Project as stated in the PEPTable 2.

Cumulative allocation of $3.5M of contingency.** Or any change to TEC or OPC that does not increase the Total Project Cost.

Any cumulative change of > $1.5M in a WBS Level 2.** Or any contingency usage*.

Change in cost below the FPD threshold.

Schedule Any delay in Critical Decision -4, Approve Project Completion.

Any delay to a Critical Decision Level 1 milestone as shown in Figure 2 (with the exception of CD-4).

Any delay greater than or equal to three months to a schedule milestone shown in Table 3.

Any delay below the FPD threshold in a schedule milestoneas shown in Table 3

Table 7: Baseline Change Control Thresholds and Authorities*Any contingency usage will require the approval of the FPD. **After the cumulative threshold has been reached and the associated change approved, the cumulative cost thresholds will be reset.

8.0 PROJECT MANAGEMENT OVERSIGHT

8.1 Risk Management including the Risk Management Plan

The management and mitigation of the risks to the project cost, schedule, and technical performance are described in the sPHENIX Risk Management Plan (RMP), and are managed in accordance with BNL Standards Based Management System (SBMS) requirements. The sPHENIX RMP provides a structured and integrated approach for identifying, evaluating, mitigating, and tracking project risks to increase the probability of project and activity success by bringing attention to problem areas early and reducing the amount of costly rework in the future. The management of Environment, Safety, and Health (ES&H) risks is handled separately through the Brookhaven National Laboratory ISMS. These ES&H risks are considered negligible at this time. Anticipated project risks will be managed at every stage of the project life cycle in order to minimize chances of risks becoming real problems. Abatement strategies iteratively developed and refined during regular sPHENIX meetings will be based upon risk

Page 34: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

28

category as well as lessons learned from projects of similar scope and complexity. A risk registry will be used as a project-wide risk-monitoring tool, while the accountability will be achieved by assigning risk ownership based on the identified risk level. The sPHENIX project team together with the Level 2 Managers and CAMs has developed a preliminary risk registry.

Contingency is one of the major resources available to deal with unexpected problems during project execution. The management of contingency, cost and schedule, and performance risks is closely linked. Proactive risk identification and mitigation can therefore reduce pressure on contingency, by reducing the probability of events that could require the use of contingency.

A detailed Risk Management Plan that describes the project’s risk identification and management approach and an associated risk registry has been developed. The major risks currently identified and the risk management approaches are identified in the Risk Registry. Risk Management meetings will be held with the Level 2 Managers on a monthly basis after CD-1.

8.2 Project Reporting Commissioning

The sPHENIX MIE will provide the FPD and the FPM a monthly project progress report in a format agreeable to DOE, and consistent with requirements in the EVMS description document. After CD-2 approval, the report will include the latest earned value data together with a variance analysis. The FPD will report monthly status in the DOE PARS IIe system, with the sPHENIX Project Controls Manager providing an upload of monthly cost information following CD-2 approval. The FPM will organize regular project performance meetings, nominally annually, with the project personnel, the Project Management Executive, and OPA. The project will also schedule regular IPT calls, quarterly or more frequently, as appropriate. Other organizations or personnel who may also participate in these calls include the Project Management Executive, HQ personnel, OPA, and others as necessary. The purpose of these calls is to provide updates on project progress and to anticipate, discuss, and resolve issues.

8.3 Earned Value Management System

BNL uses an Earned Value Management System (EVMS) to integrate the project management elements required to effectively plan, organize, and control complex projects. The BNL-EVMS is designed to provide project managers with a comprehensive system that develops and maintains the baseline; tracks project cost, schedule, and scope; and allows for the generation of timely performance measurement data and reports. Performance measurement reports provide management with objective project information critical to monitoring progress, identifying significant issues, and implementing corrective actions as needed.

DOE-funded projects at BNL are executed under the requirements of DOE Order 413.3B Change 4, Program and Project Management for the Acquisition of Capital Assets. The BNL-EVMS

Page 35: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

29

complies with the Electronic Industries Alliance (EIA) Standard 748C (2013), Earned Value Management Systems, approved March 1, 2013. It is industry best practice, and DOE’s standard for EVMS. The BNL-EVMS meets the requirements of Office of Management and Budget Circular No. A-11 (2016), Part 7, Appendix J–Principles of Budgeting for Capital Asset Acquisitions. Section 300: Planning, Budgeting, Acquisition, and Management of Capital Assets. The BNL-EVMS is a key component of the organization, methods, and procedures adopted by BNL to ensure that its mission and functions are properly executed. The Office of Project Assessment has certified the BNL-EVMS since 2007 with re-certification reviews conducted every two years.

Technical performance will be monitored throughout the execution of the project to insure conformance to technical performance requirements. Design reviews prior to fabrication, and performance testing of the completed system components will be used to ensure that the equipment meets the functional requirements.

8.4 Project Review

The DOE OPA will conduct Independent Project Reviews (IPR) of the project status and management prior to each CD and typically annually after CD-2. The Project will also organize Final Design reviews by teams external to the project. Additional external and independent technical reviews, as applicable, may be performed including Conceptual, Preliminary and Final Design reviews. The Project team will also perform internal production readiness reviews as part of the production process. The Co-Director of the OPPO will organize reviews as appropriate to monitor sPHENIX technical issues, cost and schedule performance and critical issues. The reviews will be carried out by externals teams that will have membership taken from the PMG, BNL Project Oversight Board subcommittee (POB) and additional outside experts.

8.5 Engineering and Technical Readiness

Project management will assess engineering and technology readiness through design reviews, IPRs, and other independent technical reviews.

8.6 Analysis of Alternatives and Conceptual Design Report

The Alternative Analysis is documented in the sPHENIX Analysis of Alternatives document. The proposed conceptual design for sPHENIX is described in the Conceptual Design Report prepared for the sPHENIX MIE for CD-1.

9.0 ENVIRONMENT, SAFETY, SECURITY, HEALTH AND QUALITY

Page 36: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

30

9.1 Institutional Requirements

The Environmental, Safety and Health (ES&H) requirements for the proposed sPHENIX Experiment begin with BNL’s Institutional Assessment Process as related to Accelerator Safety. These requirements are delineated by DOE Order 420.2C “Safety of Accelerator Facilities”. Oversight is conducted by the Operations Management Division of the DOE Site Office (BHSO). This is not limited to just ionizing radiation hazards from beams or sources. It is for analysis of the other two non-standard industrial safety hazards, namely, large volumes of flammable gas and the potential for oxygen deficiency from helium, nitrogen, or other inert gases.

9.2 Organizational Requirements

The BNL organizational requirements for compliance with ES&H are implemented by the Collider Accelerator Department (C-AD), Occupational Safety and Health (OSH), and Environmental programs. They are employed at the job level, are described in detail on the C-AD ES&H webpage and are compared to the ISMS for DOE. Additionally, guidance is also provided by the BNL Standards Based Management System (SBMS) in the Accelerator Safety subject area. The DOE O 420.2C Accelerator Safety Program must include a Safety Assessment Document (SAD), Accelerator Safety Envelope (ASE) and Unreviewed Safety Issue (USI) process. The sPHENIX Experiment is planned to be constructed in the existing RHIC 1008 Facility following PHENIX removal and repurposing. The conceptual designs, thus far, reveal that sPHENIX will be a similar experiment to PHENIX, from an ES&H perspective, of lesser scope with the added feature of a superconducting main magnet. Therefore, the hazards and controls for sPHENIX are expected to be similar to those previously included in the C-AD 2011 SAD (up for 2016 revision). Nevertheless, mainly due to the addition of helium cooling, sPHENIX shall undergo a USI screening, evaluation and disposition workflow. By definition, a USI is a significant increase in the probability of, or consequences from: 1) A planned modification that creates a previously unanalyzed postulated accident or condition that could result in a significant adverse impact; or 2) A previously analyzed postulated accident or condition. The USI process starts by using a C-AD USI Checklist that asks a set of questions. Once answered, the checklist returns an evaluation with either a positive or negative result. A negative result requires no further action in regards to the SAD or ASE. If positive, a Preliminary Hazard Analysis Report (PHAR) is then sent to the Accelerator Safety Committee, the Experimental Safety Committee, and eventually DOE for approval. After BHSO approval, any resulting affects to the SAD and ASE are first added as appendices to the SAD prior to its five-year revision cycle.

9.3 National Environmental Protection Act

Page 37: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

31

In accordance with NEPA (required by DOE Order 451.1B), an Environmental Evaluation Notification Form has been completed for the sPHENIX MIE by the BNL Environmental Protection Division. This document was submitted to DOE- BHSO on April 16, 2016 for review and NEPA determination as required by 10 CFR 1021 which are DOE’s Rules for Implementing NEPA. The Categorical Exclusion was approved. A preliminary Hazard Analysis Report has also been developed. The report concludes that all hazards identified are similar in nature and magnitude to those already found in other types of nuclear or particle physics projects. The impact of any hazard will be minor off-site and negligible on-site. The Hazard Analysis Report will be updated as required.

9.4 Safeguards and Security

The plan for equipment safeguards and cyber-security at the 1008 facility during the construction and operation of the sPHENIX MIE has been evaluated by the BNL Protection Division and Information Technology Department. The assessment of both groups is that our equipment safeguards and cyber-security plans are valid, and will meet the BNL criteria established for both areas. The safeguards and security issues for this project are considered small and manageable with standard BNL practices currently in place. The project does not require a Security Vulnerability Assessment Report (SVAR) or additional security requirements that are not already addressed by current Brookhaven policies and procedures. The project will use the existing program and policy that is already approved by DOE.

9.5 System Engineering

The project will use a tailored systems engineering approach to execute and manage the project including performing value management analysis and value engineering studies; specification and design development; verification, and reviews; risk analysis and management; coordination of fabrication of equipment and systems; and other interface management activities. The Systems Engineering function within the sPHENIX MIE will be led by the Project Engineer, with responsibilities that include quality assurance oversight, and management. The Project Engineer will work with the Chief Mechanical Engineer, and the sPHENIX Detector Integration Task Force to manage the interfaces between the subsystems. The Project Engineer will lead, and organize technical subsystems reviews, and assessments as appropriate.

9.6 Value Management

The project will use a tailored systems engineering approach to execute and manage the project including performing value management analysis and value engineering studies; specification and design development, verification, and reviews; risk analysis and management; and coordination of fabrication of equipment and systems, and other interface management activities. The Systems Engineer will provide high-level systems engineering and value management oversight of all aspects of the project. The System Engineer will participate in, and frequently

Page 38: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

32

lead, technical alternatives studies to determine the best, most cost effective, design solutions. Value management and optimization, by seeking the lowest cost and risk solution to each design problem, will be a continuous process throughout the sPHENIX Project.

9.7 Value Engineering

The project will perform Value Engineering assessment as part of the conceptual, preliminary and final design process to define the scope of work that would be affordable given the prescribed budget, the expertise of the participating sPHENIX institutions, funding sources and agreements with the various institutions. The review teams will evaluate alternative design approaches and evaluate the flexibility of the design for present and future research as appropriate. The Value Engineering approach will determine the impacts on cost (both project and life-cycle) of any suggested changes to the design. Additionally, the project team will perform informal Value Engineering evaluations throughout the duration of this MIE.

9.8 Configuration Management

The sPHENIX MIE will adhere to the configuration management requirements described in the BNL Standards-Based Management System (SBMS). Configuration management is used to identify and document the configuration of the end products and control changes to the configuration during the life cycle. The Project Manager together with the Project Engineer and Chief Mechanical Engineer has initiated a configuration management system on sPHENIX, which will ensure the delivery of complete as-built documents at the close of the project. Documents defining the configuration of the project baseline will be maintained through the formal baseline change control process, as described in Section 7 of this PPEP. Configuration definition documents consist of the following:

Critical Decision Record Documents

Acquisition Strategy

Project Execution Plan

Safety and Hazard Analysis Report

Quality Assurance Plan

Risk Management Plan

Design Documents

WBS Dictionary

Procurement specification documents for technical equipment

Approved Baseline Change Proposals

Page 39: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

33

9.9 Quality Assurance

The sPHENIX MIE will be conducted in accordance with the BNL Quality Assurance (QA) Program that applies to all work conducted at BNL. The program conforms to the requirements of DOE Order 414.1D, Quality Assurance. These requirements include:

Program

Personnel training and qualifications

Quality improvement

Documents and records

Work processes

Design

Procurement

Inspection and acceptance testing

Management assessment

Independent assessment

A QA Plan has been developed to integrate the program requirements that apply to all sPHENIX work. The primary objective of this plan is to implement quality assurance criteria in a way that achieves the project’s performance goals, taking into account the work to be performed and the associated environmental, safety and health hazards. Effective implementation of the QA Plan will enable the project to:

Design in quality and reliability

Promote early detection of problems to minimize failure costs and impact on schedule

Develop appropriate documentation to support upgrade and operational requirements

Define general requirements for design and readiness reviews for all aspects of the

project.

Assure that personnel are trained before performing critical activities, especially those

that have environmental, safety, health and quality consequences.

The sPHENIX Project Director is responsible for achieving performance goals. The sPHENIX Level 2 Managers are responsible for implementing the QA Plan within their subsystem. The sPHENIX QA Coordinator is responsible for ensuring that a quality system is established, implemented, and maintained in accordance with requirements, and for providing oversight and support to the project participants to ensure a consistent quality program.

Page 40: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

34

10.0 TRANSITION TO OPERATIONS

The sPHENIX MIE deliverables shall include all scope delineated in section 2, including all deliverable listed items and tasks mentioned in the WBS with performance satisfying the Threshold KPPs. The management and organization of operations including installation and commissioning is outside the scope of the sPHENIX MIE project, and will be summarized in the sPHENIX Transition to Operations Plan to be developed in support of CD-4. The Transition to Operations plan will include a schedule for accomplishing the UPPs and will be tracked to completion.

11.0 PROJECT CLOSE OUT

When the project nears completion, a project closeout plan will be developed and implemented.

The following activities will be discussed in the closeout plan:

Project lessons learned.

How all contract obligations, products, services, and deliverables have been completed

and accepted by the client.

How project team members will be informed that the work is complete and that they are

no longer authorized to charge to project charge codes.

How subcontractors/vendors are notified of the closeout, and how a formal request is

submitted to BNL to de-obligate balances and/or accrue outstanding costs and resolve/de-

obligate outstanding balances. De-obligation and contract close out requires formal

concurrence of vendors.

How costs associated with closed charge codes must be cleared.

A Draft Project Closeout Report will be developed prior to CD-4 approval and the Initial Project Closeout Report will be developed after the project is complete. The completion report will contain the final cost of the project, project lessons learned, and performance achieved at project completion. As part of project closeout, the project will finalize PARS IIe reporting. The initial Project Closeout Report will be submitted to the FPD within 90 days after CD-4 is achieved

Page 41: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

APPENDIX A INTEGRATED PROJECT TEAM CHARTER

A.1 Project Summary

Under the sponsorship of DOE NP program, the sPHENIX MIE will be a major upgrade to the PHENIX experiment that will enable the precision characterization of jets produced in AA, pA and pp collisions at RHIC. In addition, the experiment will collect a large sample of upsilons with a mass resolution that allows for their separation into three mass states, and study of their behavior on different distance scales. The sPHENIX scientific program promises to break new ground by making measurements in kinematic regimes that compliment those under study at the Large Hadron Collider (LHC) and extend in important ways to previous studies carried out at RHIC. sPHENIX extends the capabilities of PHENIX and STAR, and provides complimentary measurements to that of the LHC, including overlapping measurements that are critical to understanding the results observed at both CERN and BNL.

The DOE Office of Science approved Critical Decision (CD)-0 for the sPHENIX MIE on September 27, 2016.

A.2 IPT Members

The IPT is led by the Federal Project Director (FPD) and includes members from functional areas critical to the success of the project. The FPD will work in partnership with IPT members and others in the pursuit of project goals as described in the PPEP and other project documents. As needed, the IPT may call on additional subject matter experts in safety health, legal, quality assurance, communication, and other areas, at DOE BHSO, and BNL.

A.3 Operating Principles

Hold open discussions

Have a qualified, empowered team members

Encourage consistent, success-oriented, proactive participation

Commit to DOE Integrated Safety Management principles as appropriate for

commercially available services

Commit to DOE High Performance Computing and Networking Facilities Management

Plan principles

Have reasoned disagreement as appropriate

Practice early issue identification and resolution

The IPT will meet monthly or as necessary throughout the project and a status meeting is held every two weeks.

Page 42: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

36

A.4 Team Responsibilities

The team is responsible for assuring the success of the overall project, in terms of cost, schedule and scope. Specifically, the team will: Oversee development of project definition, technical scope, and budget to support Mission Need. Make sure project documents such as Project Execution Plan and Acquisition Strategy properly reflect project technical and management requirements. Develop the performance measures, and monitor and evaluate project performance throughout the project’s life cycle. Oversee the project, ensuring all project requirements are fulfilled in a safe and cost efficient manner, and that the resource meets operational capabilities established in the PPEP.

APPENDIX B PRELIMINARY UPP’S

UPPs for measurements at 10% central Au+Au RHIC events at the average RHIC store luminosity.

Upsilon (1S) mass resolution ≤ 125 MeV

≥ 90% Tracking Efficiency

≤ 10% momentum resolution at 40 GeV /c

≤ 150% / √Ejet jet energy resolution for R=0.2 jets

≤ 8% single photon energy resolution at 15 GeV

Table 8: Table of Preliminary Ultimate Performance Parameters. UPPs for measurements made at 10% central Au+Au RHIC events at the average RHIC store luminosity

List of Tables:

Table 1: Table of Preliminary Key Performance Parameters ………………………...............5,6Table 2: sPHENIX MIE Total Project Cost in AYk$..................................................................6Table 3: Table of sPHENIX Critical Decision Milestones………………………………....…..7Table 4: Level 2 Subsystem Milestones of the sPHENIX MIE…………………………...........9Table 5: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure…….….11,12Table 6: Preliminary Funding Profile…………………………………………………...…......12Table 7: Baseline Change Control Thresholds and Authorities…………………………….....27Table 8: Table of Preliminary Ultimate Performance Parameters……………………….........36

List of Figures:Figure 1: sPHENIX MIE Summary Schedule……………………………….……………........8Figure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX…………..…...10

Page 43: 1.0 · Web viewFigure 2: The Level 2 and Level 3 Work Breakdown Structure for sPHENIX MIE Table 5a: WBS Dictionary at the Level 2 and Level 3 Work Breakdown Structure for the sPHENIX

37

Figure 3: The sPHENIX Organization Chart…………………………………………….…....15