1 september 2007 tango meeting a.buteau icaleps 2005 status report soleil september 2007

10
ICALEPS 2005 1 September 2007 – Tango Meeting A.Buteau Status report SOLEIL September 2007

Upload: ada-oneal

Post on 18-Jan-2018

219 views

Category:

Documents


0 download

DESCRIPTION

3 September 2007 – Tango Meeting – A.Buteau ICALEPS 2005  274h 40; 55%  11h 57; 2%  178h 08; 36%  33h 41; 7% Machine Physics Machine+BL time Beamline RadioProtection Beam statistics during July Run

TRANSCRIPT

Page 1: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20051September 2007 – Tango Meeting – A.Buteau

Status reportSOLEIL

September 2007

Page 2: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20052September 2007 – Tango Meeting – A.Buteau

Accelerator status

• Accelerator is now in routine operation• Beam is now mainly produced for

beamlines• There is only 2 day/week for

Machine tests since last spring• We also have to face short periods of

time (about 1 week) for maintenance between runs

Page 3: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20053September 2007 – Tango Meeting – A.Buteau

274h 40; 55% 11h 57; 2%

178h 08; 36%

33h 41; 7%

Machine Physics

Machine+BL time

Beamline

RadioProtection

Beam statistics during July Run

Page 4: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20054September 2007 – Tango Meeting – A.Buteau

BEAMLINES; 02h 28

UTILITIES; 02h 00

OTHER; 01h 59

VACCUUM; 03h 14

LINAC; 00h 18

ID; 00h 21

PS; 00:41RF; 00:55

RFPSuppliesLINACInsertionsVaccuumBeamlinesUTILITIESOTHER

Statistics of failures during July Run

Tango is not in the statistics !!

Page 5: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20055September 2007 – Tango Meeting – A.Buteau

Accelerator status : Control facts

• Software development are still significant for :• Insertions devices installation and commissioning• Slow and feedforward feedbacks

• Major Machine operation requests are focused on : • Enhancements and bug fixes on DeviceServers,

ATK, Archiving systems, starter, statical database, global supervision of Control system

• Remote access a few applications (MAMBO for instance) through WEB interfaces

• New Linux Servers have to be installed to support the increase of monitoring applications (trends,alarms,etc.)

Page 6: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20056September 2007 – Tango Meeting – A.Buteau

Accelerators : next steps

Recovery procedures are to be written for many systems

Architecture for Oracle Database must be extended for HDB and TDB new

requirementsMore attributes to be stored Extension of retention period of attributes for TDB

New diagnostics, insertions, and operation tools are still to be developped

Page 7: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20057September 2007 – Tango Meeting – A.Buteau

Tango facts

Last meeting, in March Now in september

Page 8: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20058September 2007 – Tango Meeting – A.Buteau

Beamlines status

10 beamlines are now beeing commissionedDIFFABSTEMPOODESAMBADESIRSCASSIOPEEPROXIMASWINGSMISMARS

First beam on the MARS beamline

Page 9: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 20059September 2007 – Tango Meeting – A.Buteau

Tango facts on beamlines

SWING beamline

PROXIMA beamline

12 Tango Control System in operationMore than 3000 devices

Page 10: 1 September 2007  Tango Meeting  A.Buteau ICALEPS 2005 Status report SOLEIL September 2007

ICALEPS 200510September 2007 – Tango Meeting – A.Buteau

Next steps on beamlines

On the major part of the beamlines software installation (i.e DeviceServers, java

applications) for « Expert Users » is almost finished

First sequence acquisitions have been done We are now preparing the « Regular operation

phase » :GUI acquisition application developmentHigh level process DeviceServers development

Still a difficult period