5/31/2018 Untitled Page
http://environmentclearance.nic.in/auth/ECReport_new.aspx?pid=11005&status=Found 1/3
Project Details1.
Whether it is a violation case and application is being submitted under Notification No.S.O.804(E) dated 14.03.2017 ? : No
Project Details1.
i. Proposal No. : IA/CG/MIN/32238/2015
ii. MoEFCC File No. : J-11015/400/2015-IA.II(M)
iii.Short narrative of the project: Capacity expansion of Bailadila Iron Ore Project, Deposit no:14/11C from 12 to 20 MTPA of M/s. NMDC Limited at Kirandul, South Bastar Dantewada District,Chhattisgarh.
iv. Project Sector : Mining Projects
v. Company/Proponent : NMDC LIMITED
vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1. Chhattisgarh Dantewada Dantewada
2. Chhattisgarh Dantewada Dantewada
3. Chhattisgarh Dantewada Dantewada
4. Chhattisgarh Dantewada Dantewada
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded ECCompliance report
viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report
ix.Date of TOR Granted 12 Jan 2016
x.TOR letter issued by Ministry: Annexure-TOR letter
ix.Date of Submission for EC: 31 May 2018
x.Project Type: Expansion
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.2.
i.EIA/EMP: Annexure-EIA/EMP
ii.Risk Assessment: Annexure-Risk Assessment
EC Report
5/31/2018 Untitled Page
http://environmentclearance.nic.in/auth/ECReport_new.aspx?pid=11005&status=Found 2/3
iii.Public Hearing: Annexure-Public Hearing
iv. Date of Public Hearing: 06 Aug 2017
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter: Annexure-Cover Letter
vii.Remarks: With reference to EAC (NCM) meeting held on 22nd March 2018 and subsequentletter no: J/11015/400/2015.IA.II(M) dated 12/4/2018 received from MoEFCC, NMDC issubmitting separate lease wise application for getting lease wise E.C. Accordingly, the presentapplication is for Bailadila Deposit-14 ML (322.368 Ha) for obtaining E.C for capacity expansionof ROM Iron Ore from existing 5.0 to 10.0 MTPA at Kirandul, South Bastar Dantewada District,C.G.
Additional Detail Sought: NIL3.
Accredited Consultant Details4.
i. Accreditation status : Yes
ii. Accreditation No. : QCI NABET ENV ACO 17 0285
iii. Name of Consultant: VIMTA LABS LIMITED
iv. Address : 142 IDA PHASE II CHERLAPLLY HYDERABAD 500051
v. Mobile No.: 9000711309
vi. Landline No.: 04027264141
vii. Email Id: [email protected]
Undertaking5.
I hereby give undertaking that the data and information given in theapplication and enclosures are true to be best of my knowledge and beliefand I am aware that if any part of the data and information found to be falseor misleading at at any stage, the project will be rejected and clearancegiven, if any to the project will be revoked at our risk and cost.
i. Name of Applicant : C
ii. Designation : EXECUTIVE DIRECTOR
iii. Name of Company(Applicant Name should not be given here) : M JAYAPAL REDDY
5/31/2018 Untitled Page
http://environmentclearance.nic.in/auth/ECReport_new.aspx?pid=11005&status=Found 3/3
iv. Address : REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLS MASAB TANKHYDERABAD 500028
v. Uploaded copy of documents in support of the competence/authority of the personmaking this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making thisapplication to make application on behalf of the User Agency
5/31/2018 Untitled Page
http://environmentclearance.nic.in/auth/ECReport_new.aspx?pid=11007&status=Found 1/3
Project Details1.
Whether it is a violation case and application is being submitted under Notification No.S.O.804(E) dated 14.03.2017 ? : No
Project Details1.
i. Proposal No. : IA/CG/MIN/32238/2015
ii. MoEFCC File No. : J-11015/400/2015-IA.II(M)
iii.Short narrative of the project: Capacity expansion of Bailadila Iron Ore Project, Deposit no:14/11C from 12 to 20 MTPA of M/s. NMDC Limited at Kirandul, South Bastar Dantewada District,Chhattisgarh.
iv. Project Sector : Mining Projects
v. Company/Proponent : NMDC LIMITED
vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1. Chhattisgarh Dantewada Dantewada
2. Chhattisgarh Dantewada Dantewada
3. Chhattisgarh Dantewada Dantewada
4. Chhattisgarh Dantewada Dantewada
vii. Uploaded EC Compliance report by rigional office of MoEFCC: Annexure-Uploaded ECCompliance report
viii. Certified Monitoring report by RoMoEF: Annexure-Uploaded Monitoring report
ix.Date of TOR Granted 12 Jan 2016
x.TOR letter issued by Ministry: Annexure-TOR letter
ix.Date of Submission for EC: 31 May 2018
x.Project Type: Expansion
Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.2.
i.EIA/EMP: Annexure-EIA/EMP
ii.Risk Assessment: Annexure-Risk Assessment
EC Report
5/31/2018 Untitled Page
http://environmentclearance.nic.in/auth/ECReport_new.aspx?pid=11007&status=Found 2/3
iii.Public Hearing: Annexure-Public Hearing
iv. Date of Public Hearing: 06 Aug 2017
v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document
vi. Uploaded Cover Letter: Annexure-Cover Letter
vii.Remarks: With reference to EAC (NCM) meeting held on 22/3/2018 and subsequent letter no:J-11015/400/2015.IA.II(M) dated 12/4/2018 received from MoEFCC, NMDC is submittingseparate lease wise application for getting lease wise E.C. Accordingly, the present application isfor Bailadila Deposit-14 NMZ ML (506.742 Ha) for obtaining E.C for capacity expansion of ROMIron Ore from existing 5.5 to 8.5 MTPA at Kirandul, South Bastar Dantewada District, C.G.
Additional Detail Sought: NIL3.
Accredited Consultant Details4.
i. Accreditation status : Yes
ii. Accreditation No. : QCI NABET ENV ACO 17 0285
iii. Name of Consultant: VIMTA LABS LIMITED
iv. Address : 142 IDA PHASE II CHERLAPALLY HYDERABAD 500051
v. Mobile No.: 9000711309
vi. Landline No.: 04027264141
vii. Email Id: [email protected]
Undertaking5.
I hereby give undertaking that the data and information given in theapplication and enclosures are true to be best of my knowledge and beliefand I am aware that if any part of the data and information found to be falseor misleading at at any stage, the project will be rejected and clearancegiven, if any to the project will be revoked at our risk and cost.
i. Name of Applicant : C
ii. Designation : EXECUTIVE DIRECTOR
iii. Name of Company(Applicant Name should not be given here) : M JAYAPAL REDDY
5/31/2018 Untitled Page
http://environmentclearance.nic.in/auth/ECReport_new.aspx?pid=11007&status=Found 3/3
iv. Address : REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLS MASAB TANKHYDERABAD 500028
v. Uploaded copy of documents in support of the competence/authority of the personmaking this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making thisapplication to make application on behalf of the User Agency
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 1/9
APPENDIX I(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate,Kindly upload supporting documentunder 'Additional Attachments if any' at the last part of the Form1. Please note that all suchAnnexures must be part of single pdf document.
(I) Basic InformationS.No. Item Details
Whether it is a violation case andapplication is being submitted underNotification No. S.O.804(E) dated14.03.2017 ?
No
1.
Name of the Project/s Bailadila Iron Ore Mine, Deposit-11 Mining Lease (874.924Ha) of M/s. NMDC Limited
Brief summary of project Annexure-Brief summary of projectProposal Number IA/CG/MIN/75153/2018Project Cost (in lacs) 46963
2. S. No. in the schedule 1(a) Mining of minerals Project Sector Non-Coal Mining
3.Proposed capacity/area/length/tonnage tobe handled/command area/leasearea/number or wells to be drilled
11.30 Million tons per annum ROM Iron Ore. ha.
4. New/Expansion/Modernization New
5. Existing Capacity/Area etc. 874.924 ha.
6. Category of project i.e. 'A' or 'B' A
7. Does it attract the general condition? Ifyes, please specify No
8. Does it attract the specific condition? Ifyes, please specify No
9.Location of the project Kirandul, South Bastar Dantewada District of Chhattisgarh
StateShape of the project land Block (Polygon)
Uploaded GPS file Annexure-GPS file Uploaded copy of survey of India Toposheet Annexure-Survey of india toposheet
Plot/Survey/Khasra No. Forest compartment No 1842 to 50, 1852 to 54, 1856, 1860in Bacheli Forest Range, Dantewada Forest Division, C.G.
Town / Village KirandulState of the project Chhattisgarh
Details of State of the project
S.no State Name District Name Tehsil Name
(1.) Chhattisgarh Dantewada Dantewada
10.Nearest railway station along with distancein kms Kirandul, 1 km
Nearest airport along with distance in kms Raipur, 431 km
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 2/9
11. Nearest Town/City/District Headquartersalong with distance in kms
Dantewada , 40 km
12.Village Panchayats, Zila Parishad, MuncipalCorporation, Local body (Complete postaladdress with telephone nos. to be given)
Nagar Palika Parishad Kirandul South Bastar Dantewada DtCG
13. Name of the Applicant C
14. Registered Address REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLSMASAB TANK HYDERABAD 500028
15.
Address for correspondance:Name of the Company NMDC LIMITEDName of the Applicant CDesignation (Owner/ Partner/ CEO) EXECUTIVE DIRECTORPin code 494001E-mail [email protected] No. 040-23538773Fax No. 040-23536760Copy of documents in support of thecompetence/authority of the personmaking this application to make applicationon behalf of the User Agency .
Annexure-Uploaded Copy of documents in support of thecompetence/authority
16. Details of Alternative Sites examined, ifany. Location of these sites should beshown on a toposheet
No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinkedproject has been submitted? N/A
19. If Yes, MoEF file number N/ADate of submission N/A
20. If No, Reason N/A
21. Whether the proposal involves Approval/ Clearance under: if yes, details of the same andtheir status to be given(i) Whether the proposal involvesapproval/clearance under the Forest(Conservation) Act,1980?
No
(ii) Whether the proposal involvesapproval/clearance under the wildlife(Protection) Act,1972?
No
(iii) Whether the proposal involvesapproval/clearance under the C.R.Znotification, 2011?
No
22. Whether there is any GovernmentOrder/Policy relevent/relating to the site? No
23. Whether any Forest Land Involved? YesArea of Forest land Involved (hectares) 874.924 ha.
24. Whether there is any litigation pendingagainst the project and/or land in which theproject is proposed to be set up?
No
(a) Name of the Court N/A(b) Name of the Sub court N/A(c) Case No. N/A(d) Orders/directions of the court, if any N/A
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 3/9
and relevance with the proposed project
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will causephysical changes in the locality (topography, land use, changes in water bodies, etc.)
S.NoInformation/Checklist confirmation Yes/No
Details there of (with approximatequantities/rates, wherever possible) with
source of information data
1.1
Permanent or temporary change in landuse, land cover or topography includingincrease in intensity of land use (withrespect to local land use plan)
Yes
Bailadila Iron Ore Project (Dep-11ML) is an existingiron ore mining project and there will be change in theland use, land cover or topography as per approval ofFC. The land use of M.L. area comprises of area underMining, waste dumps, roads, infrastructure, etc.,created for production of iron ore.
1.2 Clearance of existing land, vegetation andbuildings? Yes It is already operating mine. Hence Clearance of
vegetation is not required.
1.3 Creation of new land uses? No Not Applicable.
1.4 Pre-construction investigations e.g. borehouses, soil testing? No Not Applicable.
1.5 Construction works? No Not Applicable.
1.6 Demolition works? No Not Applicable.
1.7 Temporary sites used for constructionworks or housing of construction workers? No Not Applicable.
1.8
Above ground buildings, structures orearthworks including linear structures,cutand fill or excavations and fill orexcavations
No Not Applicable.
1.9 Underground works including mining ortunneling? No Not Applicable.
1.10 Reclamation works? YesReclamation of mined out areas and waste rock dumpswill be carried out as per IBM approved ProgressiveMine Closure Plan.
1.11 Dredging? No Not Applicable.
1.12 Offshore structures? No Not Applicable.
1.13 Production and manufacturing processes? Yes
The production process comprises of drilling, blastingand excavation. ROM from 11A is transported to CPlocated in Dep-10ML which is common for both 10 and11A mine. ROM of Dep-11B is fed into CP located inDep-11 ML from where it is transported to SP-I & SP-II located in the adjacent mining lease 14 NMZ. ROMof Dep-11C is fed into CP & SP located in Dep-14 NMZ.Final products Lump ore, CLO & Fine Ore are stackedat LP at Kirandul / Bacheli for dispatch to customersthrough Railway wagons.
1.14 Facilities for storage of goods or materials? Yes Storage facility of material already available at project.
1.15 Facilities for treatment or disposal of solidwaste or liquid effluents?
Yes Waste rock material excavated from mining operationis dumped in identified places as per IBM approvedmining plan. Solid Waste generation is negligiblehowever used oil/cotton waste is disposed of throughauthorized agencies. Presently Screening plants are
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 4/9
operated by Dry screening process, which do notproduces slimes.
1.16 Facilities for long term housing ofoperational workers? Yes Facilities are available in the existing NMDC Township
at Kirandul and Bacheli Complex.
1.17 New road, rail or sea traffic duringconstruction or operation? No Not Applicable.
1.18
New road, rail, air water borne or othertransport infrastructure including new oraltered routes and stations, ports, airportsetc?
No Not Applicable.
1.19Closure or diversion of existing transportroutes or infrastructure leading to changesin traffic movements?
No Not Applicable.
1.20 New or diverted transmission lines orpipelines? No Not Applicable.
1.21Impoundment, damming, culverting,realignment or other changes to thehydrology of watercourses or aquifers?
No Not Applicable.
1.22 Stream crossings? No Not Applicable.
1.23 Abstraction or transfers of water fromground or surface waters? No Mining activity is carried out at hill top and chances of
intersecting ground water table do not arise.
1.24 Changes in water bodies or the landsurface affecting drainage or run-off? No Not Applicable.
1.25Transport of personnel or materials forconstruction, operation ordecommissioning?
No Transport of personnel is by the existing road.
1.26 Long-term dismantling or decommissioningor restoration works? No All dismantling or decommissioning of restoration work
shall be carried out as per the approved IBM PMCP.
1.27Ongoing activity during decommissioningwhich could have an impact on theenvironment?
No Not Applicable.
1.28 Influx of people to an area in eithertemporarily or permanently? No
NMDC is already having township at Kirandul andBacheli for accommodating employees of project.There will not be any major influx of people to thisarea.
1.29 Introduction of alien species? No Not Applicable.
1.30 Loss of native species or genetic diversity? No Not Applicable.
1.31 Any other actions? No Not Applicable.
2 Use of Natural resources for construction or operation of the Project (such as land, water,materials or energy, especially any resources which are non-renewable or in short supply):
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
2.1 Land especially undeveloped or agriculturalland (ha) No No undeveloped or agricultural land is involved in the
project.
2.2 Water (expected source & competing users)unit: KLD No Existing Source: Malangir Nallah, Bacheli Nallah,
Kirandul Nallah, Galli Nallah. Competing users: NIL
2.3 Minerals (MT) No Not Applicable
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 5/9
2.4 Construction material – stone, aggregates,sand / soil (expected source – MT)
No Not Applicable
2.5 Forests and timber (source – MT) No Not Applicable
2.6Energy including electricity and fuels(source, competing users) Unit: fuel(MT),energy (MW)
Yes
Power is supplied by Chhattisgarh State ElectricityBoard from sub-station at Kirandul and Bacheli wherepower is stepped down from grid voltage- 132KV to33KV and is distributed to the different sub-stations ofthe mine for further distribution and control.
2.7 Any other natural resources (useappropriate standard units) No Not Applicable
3Use, storage, transport, handling or production of substances or materials, which could beharmful to human health or the environment or raise concerns about actual or perceived risks tohuman health
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
3.1
Use of substances or materials, which arehazardous (as per MSIHC rules) to humanhealth or the environment (flora, fauna,and water supplies
Yes
The approval granted by CECB for Bacheli and Kirandulcomplex the Authorization for Handling of HazardousWastes such as used oil, waste filters and scum of ETPeffluent.
3.2Changes in occurrence of disease or affectdisease vectors (e.g. insect or water bornediseases)
No Not Applicable.
3.3 Affect the welfare of people e.g. bychanging living conditions? Yes
The project is already generating permanentemployment to around 1626 people and alsotemporary employment to around 1000 people. Theliving conditions and welfare of people are beingimproved by social welfare schemes of NMDC underCSR policy in nearby surrounding villages.
3.4Vulnerable groups of people who could beaffected by the project e.g. hospitalpatients, children, the elderly etc.
No Not Applicable.
3.5 Any other causes No Not Applicable.
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
4.1 Spoil, overburden or mine wastes Yes
It is estimated that 80.2 MT of waste will be generatedduring entire life of mine. Waste rock material shall bedumped at identified locations as per approved miningplan.
4.2 Municipal waste (domestic and orcommercial wastes) Yes
There will be marginal generation of municipal solidwaste from the employees at then mine site from thecanteen which is disposed of in an environmentfriendly manner.
4.3 Hazardous wastes (as per Hazardous WasteManagement Rules) Yes Used oil and Cotton waste is being disposed of through
authorized vendor from CECB.
4.4 Other industrial process wastes No The screening plants are operated in dry screening
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 6/9
process, which do not produces slime.
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge fromeffluent treatment No Scum of ETP will be disposed of as per M&H Rules.
4.7 Construction or demolition wastes No Not Applicable.
4.8 Redundant machinery or equipment No Not Applicable.
4.9 Contaminated soils or other materials No Not Applicable.
4.10 Agricultural wastes No Not Applicable.
4.11 Other solid wastes No Not Applicable.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
5.1 Emissions from combustion of fossil fuelsfrom stationary or mobile sources Yes Periodical maintenance of HEM machinery is being
done to avoid excessive emissions.
5.2 Emissions from production processes Yes
Fugitive dust emissions generated during miningprocess are mitigated by wet drilling practices andregular water sprinkling on mine haul roads, atdumper platform, at all transfer points and etc.
5.3 Emissions from materials handling includingstorage or transport Yes Mist water is being sprayed at all dust prone locations.
5.4 Emissions from construction activitiesincluding plant and equipment No Not applicable
5.5Dust or odours from handling of materialsincluding construction materials, sewageand waste
Yes Dust generated during handling of waste for whichadequate mitigation measure are taken.
5.6 Emissions from incineration of waste No Not applicable
5.7 Emissions from burning of waste in open air(e.g. slash materials, construction debris) No Not applicable
5.8 Emissions from any other sources No Not applicable
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
6.1 From operation of equipment e.g. engines,ventilation plant, crushers Yes
Noise is generated from Crushers, shovels, dumpers,drills, dozers and blasting activities. Noise level insideoperator cabins is maintained below 75 to 85 dbA.Required noise control equipment’s like mufflers,acoustics enclosures are installed at noise prone areas.Ear muffs are being used by operators and helpers.Regular maintenance of mining machinery is helping inreducing the noise levels. Rubber lined screens areused in plants to control noise levels.
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 7/9
6.2 From industrial or similar processes Yes The main source of noise generation from the minearea are from drilling, blasting and mining machineriesi.e. diesel operated HEMM. The noise control measuresbeing adopted for controlling the noise levels.
6.3 From construction or demolition No Not Applicable
6.4 From blasting or piling Yes
Noise is generated during Blasting operations, whichare restricted to the minimum by proper blast design,proper stemming of holes, ensuring free face forblasting. Noise and vibration are attenuated with theuse of nonel for in-hole delay and HTD (Handy TrunkDelay) for surface delay. The Blasting is carried out inaccordance with the Explosive Act and MMR 1961.
6.5 From construction or operational traffic No Not Applicable
6.6 From lighting or cooling systems Yes Negligible
6.7 From any other sources No Not Anticipated
7 Risks of contamination of land or water from releases of pollutants into the ground or intosewers, surface waters, groundwater, coastal waters or the sea:
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
7.1 From handling, storage, use or spillage ofhazardous materials Yes Negligible
7.2From discharge of sewage or othereffluents to water or the land (expectedmode and place of discharge)
Yes Effluents from service center are treated in EffluentTreatment Plant.
7.3 By deposition of pollutants emitted to airinto the land or into water Yes Negligible
7.4 From any other sources No Not Anticipated
7.5Is there a risk of long term build up ofpollutants in the environment from thesesources?
No Not Anticipated
8 Risk of accidents during construction or operation of the Project, which could affect humanhealth or the environment
S.NoInformation/Checklist confirmation Yes/No
Details thereof (with approximatequantities/rates, wherever possible) with
source of information data
8.1From explosions, spillages, fires etc fromstorage, handling, use or production ofhazardous substances
Yes
There is no production of any hazardous substances.Fire in conveyor belt will be controlled by Fire Fightingequipment provided inside the plant. Fire fightingtraining is being provided to the employees for takingthe precaution for any type of accidents.
8.2 From any other causes No Not Anticipated
8.3
Could the project be affected by naturaldisasters causing environmental damage(e.g. floods, earthquakes, landslides,cloudburst etc)?
No The project site falls in earthquake zone-II as per BIS1983 (part-1):2002.
9 Factors which should be considered (such as consequential development) which could lead to
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 8/9
environmental effects or the potential for cumulative impacts with other existing or plannedactivities in the locality
S.No Information/Checklist confirmation Yes/NoDetails thereof (with approximate
quantities/rates, wherever possible) withsource of information data
9.1
Lead to development of supporting utilities,ancillary development or developmentstimulated by the project which couldhave impact on the environment e.g.:
Supporting infrastructure (roads,power supply,waste or waste watertreatment, etc.)housing developmentextractive industriessupply industriesOther
Yes
It is already existing iron ore mining project. Allnecessary facilities are available at the project site.Sufficient infrastructure facilities like road network,railway line, power supply, etc., are available. Theexiting township at Kirandul and Bacheli complex areself sufficient in all respect with all services andamenities. The township will cater the requirement ofadditional manpower.
9.2 Lead to after-use of the site, which couldhave an impact on the environment No Not Anticipated
9.3 Set a precedent for later developments No Not Anticipated
9.4Have cumulative effects due to proximity toother existing or planned projectswith similar effects
Yes
Apart from this project, there are other working Dep-sas Dep- 10, Dep- 5,Dep- 14, Dep- 14 NMZ and EssarBeneficiation plant, which could have cumulative effecton the environment.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.)Proposed project location boundary
1
Areas protected under internationalconventions, national or local legislationfor their ecological, landscape, cultural orother related value
No Not Applicable
2
Areas which are important or sensitive forecological reasons - Wetlands,watercourses or other water bodies, coastalzone, biospheres, mountains, forests
Yes
RF exists within the Mining lease area and also in10 km radius of proposed project site. Thedistance and direction of water bodies is givenbelow: 1) Kirandul nalla within Ml area 2)Malangir nalla, 4.5km, SSE 3) Gallinalla, 1.1 km,W 4) Koyar Nadi, 4.9 KM, NE
3
Areas used by protected, important orsensitive species of flora or fauna forbreeding, nesting, foraging, resting, overwintering, migration
No Not Applicable
4 Inland, coastal, marine or undergroundwaters No Not Applicable
5 State, National boundaries No Not Applicable
6Routes or facilities used by the public foraccess to recreation or other tourist,pilgrim areas
No Not Applicable
7 Defence installations No Not Applicable
8 Densely populated or built-up area No Not Applicable
9 Areas occupied by sensitive man-madeland uses (hospitals, schools, places of
Yes Primary, Secondary, High schools and Collegespresent in 10km radius. Similarly Health care
5/31/2018 Report Part 1
http://environmentclearance.nic.in/auth/FORM_A_PDF.aspx?cat_id=IA/CG/MIN/75153/2018 9/9
Additional Attachments, if any
Attached File
Letter of grant of renewal of Mining Lease for BLD DEP 11 from 2017 to 2037
Environmental clearance for Bld Deposit-11A mine (Dep-11 ML) under EIA 2006notification
Environmental clearance for Bld Deposit-11B mine (Dep-11 ML) under EIA 1994notification
Integrated Environmental clearance for Bld Deposit-14/11C Project (Dep-14 ML, 14NMZ ML & 11 Part ML) under EIA 2006 notification
Forest clearance for diversion of 874.924 Ha Forest land under F.C. Act 1980
worship, community facilities) centers and Hospitals also exists.
10Areas containing important, high quality or scarceresources.(ground water resources,surfaceresources,forestry,agriculture,fisheries,tourism,minerals)
No Not Applicable
11
Areas already subjected to pollution orenvironmental damage.(those whereexisting legal environmental standards areexceeded)
No Not Applicable
12
Areas susceptible to natural hazard whichcould cause the project to presentenvironmental problems (earthquakes,subsidence, landslides, erosion, flooding orextreme or adverse climatic conditions)similar effects
No Not Applicable
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of coveringletter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(onlysingle pdf file) Annexure-Additional attachments
5 Uploaded Approval of mining Plan Annexure-Uploaded Approval of mining plan
(V) UndertakingI hereby give undertaking that the data and information given in the application and enclosuresare true to be best of my knowledge and belief and I am aware that if any part of the data andinformation found to be false or misleading at any stage, the project will be rejected andclearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of Applicant CDesignation EXECUTIVE DIRECTORName of Company (Applicant Nameshould not be given here) NMDC LIMITED
Address REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLSMASAB TANK HYDERABAD 500028