1 ‘ohana delay line installation at the summit friday, october 13th 06 pierre fedou, lesia
TRANSCRIPT
3
Background
‘Ohana will connect
CFHT and Gemini telescopes
Via a fiber link
Main sub systems:
- Injection modules
- Optical fiber links
- Delay Line, our topic today
- Beam combiner and IR camera
4
Background
CFHT Jun and Aug 02,
J, H, K band
Keck I, Dec 02, K
Gemini, Jul 03,
H, K
Injection modules status
5
Background
Keck, installation Aug 04
Tests: Dec 04, Jun 05, K band
May 06, H and K
Fiber link status
7
Delay Line
• Designed in 03 and before• Built and tested, in France, mid 04 to mid 06• Now ready to be re-installed at CFHT
8
Delay Line
Input #1Input #2
Output #1 Output #2Central carriage
Translating stage Translating stage
Fast scan
9
Delay Line
3 or 4 missions of 3 weeks
Oct 06 Hardware
Jan 07 Opto-mechanical & first lignment
Mar 07 Alignment continued
May 07 Optional
10
Delay line subsystem
• Translating stage Aerotech
• Translating stage Schneeberger
• Central carriage
• Railways
• 6 metallic frames
• Fast Scan
• One computer
15
Module #6
Module #5
rails
Schneeberger trans. stage
Schneeberger end, looking outside
Central carriage
19
Delay line
• Our goals for this mission
• Opening crates
• Moving “big hardware” in Coude Room
• Make first alignment of structure
• Rails positioning 1 mm over 12.50 m
22
7 crates: 6 + 1
2 metallic frames
2 metallic frames
Aero metallic frame
Schnee metallic frame
Rails
Aerotech on its stone bed
The 7th crate concerns injection modules
Delay line
Open question:
where do we stock this 7th?
Closed? Opened?
36
Delay line
Aerotech side
Schnee side
Beam combiner Table
Total Length = 14390mm
Total Width = 930mm
38
Delay line
Week #1, Monday 16th : crates opened and all heavy parts moved in the Coude Room, Day Crew and Meudon
Week #2, Monday 23rd : small pieces are moved and alignment made by Meudon
Week #3, Monday 30th : continued, overturning, extra time just in case…
39
Road map
• Delay Line installation: Oct 06 -> spring 07
• Injection Modules: time has been asked on Keck
• Fiber Link beetween Gemini and CFHT: summer 07
• Beam Combiner installation: spring to summer 07
• Determination of length of the base: on going effort with IGN and OCA
• First light: when ready, fall 07?