Page 1: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

1

MID TERM REVIEW MEETINGRESA PROJECT

PROJECT MANAGEMENT

1ST APRIL 2009

UDAI S. MEHTA, CUTS INTERNATIONAL

Page 2: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

2

Project management and communication

Key actors

Challenges encountered

PRESENTATION OUTLINE

Page 3: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

3

PROJECT MANAGEMENT AND COMMUNICATION

Page 4: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

4

UNNAYAN SHAMANNAYBangladesh

CUTS CARTRajasthan

CUTS CRCWest Bengal

SAWTEENepal

CUTS C-CIER

Project advisory committee (PAC)

Reference groups (RG):

Overall advice on the project

Coordination of project activities

Guidance at the territorial level

Execution at territorial level

PROJECT MANAGEMENT AND COMMUNICATION

Local CSOs and other stakeholders Support at Grassroots Level

UNNAYAN SHAMANNAYBangladesh

CUTS CARTRajasthan

CUTS CRCWest Bengal

SAWTEENepal

CUTS C-CIER

Project advisory committee (PAC)

Reference groups (RG):

Overall advice on the project

Execution at territorial level

Local CSOs and other stakeholders Support at Grassroots Level

Guidance at the territorial level

UNNAYAN SHAMANNAYBangladesh

CUTS CARTRajasthan

CUTS CRCWest Bengal

SAWTEENepal

CUTS C-CIER

Project advisory committee (PAC)

Reference groups (RG):

Overall advice on the project

Execution at territorial level

Local CSOs and other stakeholders Support at Grassroots Level

Coordination of project activities

Guidance at the territorial level

UNNAYAN SHAMANNAYBangladesh

CUTS CARTRajasthan

CUTS CRCWest Bengal

SAWTEENepal

CUTS C-CIER

Project advisory committee (PAC)

Reference groups (RG):

Overall advice on the project

Execution at territorial level

Local CSOs and other stakeholders Support at Grassroots Level

Page 5: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

5

KEY ACTORS

Page 6: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

6

PROJECT ADVISORY COMMITTEE

Comprising persons from various fields including former/present regulators, policy makers, practioners, CSOs, development partners, etc

Responsibilities• Advice at the regional level• Comment on few of the key project outcomes/outputs• Act as Ambassadors of the project

CUTS is expected to:• Keep the PAC members abreast with project activities• Send event reports/newsletters/update regularly• Seek advise on specific project issues at the regional /national level

Page 7: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

7

REFERENCE GROUP (RG)

Comprising persons from various fields including former/present regulators, policy makers, practioners, CSOs, development partners, etc

Responsibilities• Advice at the territorial level• Comment on the project outcomes/outputs• Review the progress from time to time• Participated as resource persons during TT

Partners are expected to:• Keep the RG members abreast with project activities• Send event reports/newsletters/update regularly• Seek advise on specific project issues at the territorial level

Page 8: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

8

CUTS C-CIER CUTS Centre for Competition, Investment & Economic Regulation (CCIER)

Implementing institution

Involvement of key project staff• Project Coordinator

Project Management• Financial management: co-ordination with partners and donor• Institutional management: Web page, reports, e-newsletter, etc

Liaising with media

Page 9: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

9

C-CIER AND PROJECT PARTNERS

Preparation of OSN, TOR and Methodology note for conducting perception survey

Draft outline and providing feedback on key outputs• TBP, TTM, event reports, etc• Prepared draft questionnaires for conducting perception survey• Analysed data and shared findings with partners

Facilitated participation of Nodal persons (Nepal and West Bengal): Perception Survey in Rajasthan

Participated in RG meetings & Territorial meetings: get hands-on information from national stakeholders

Page 10: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

10

CHALLENGES ENCOUNTERED AND HOW THEY WERE TACKLED

Page 11: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

11

CHALLENGES

Communication gaps or non-communication between the project team & country partners

• Telephone service was used intensively with frequent visits to project countries

Confusion between inter-related terminologies

• Examples were provided to clear the confusion • Confusions were clarified during the interactions between the

project team and partners

Information not easily available • Baseline consumer survey helped in generating first-hand

information

Page 12: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

12

CHALLENGES

Analytical capability of partners • Project team guided drafting of various key documents • Documents received positive comments from NRG/PAC members

Delay in implementation of project• Two months delay in signing of the contract • Taking suitable action to overcome the delay

Page 13: 1 MID TERM REVIEW MEETING RESA PROJECT PROJECT MANAGEMENT 1 ST APRIL 2009 UDAI S. MEHTA, CUTS INTERNATIONAL

13

Thank You

[email protected]