1 contract change clause the change order process annual program of the claims avoidance and...

50
1 Contract Change Clause Contract Change Clause The Change Order Process The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11, 2010 – Los Angeles

Upload: bruce-biby

Post on 29-Mar-2015

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

1

Contract Change ClauseContract Change Clause The Change Order Process The Change Order Process

Annual Program of theClaims Avoidance and Resolution Committee

of the Construction InstituteMarch 11, 2010 – Los Angeles

Page 2: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Prepared by Changes Clause Prepared by Changes Clause SubcommitteeSubcommittee

• Dan Becker – Chair

• Michael Radbill

• Hal McKittrick

• Joe Ramaglia

2

Page 3: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Changes are a Natural Part Changes are a Natural Part of Constructionof Construction

3

• Changes may have both cost and schedule impacts.

• Dealing with changes promptly will have the least amount of impact on the budget and schedule.

• Delaying resolution can increase costs, jobsite friction, delay the completion of the project and result in a dispute.

Page 4: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Reasons for ChangesReasons for Changes

• Differing site conditions.

• Regulatory changes.

• Owner changes.

– Scope added/deleted during construction – field changes.

– Late design changes.

– Changes in Owner-provide equipment.

– Start-up changes

• Information missing from the CD’s; errors and omissions

• Schedule delays and revisions.

• Adverse weather and other force majeure events.4

Page 5: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Owner’s Perceptions of Change OrdersOwner’s Perceptions of Change Orders

5

Original Contract

Page 6: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Contract Changes Presentation Contract Changes Presentation GoalsGoals• Define a change order process

• Provide recommended provisions to include in your contracts

6

Page 7: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Contract Changes PresentationContract Changes Presentation

• Process Elements

• Notifications

• Preparing Change Proposals

• Overhead Costs

• Change Management Process/System

Construction InstituteClaims Avoidance and Resolution

Committee

7

Page 8: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Change Process ElementsChange Process Elements

• Define the Process

• Change Proposal Submittal

– Scope

– Timing

– Pricing the Change Order Request

– Time and Materials Work

– Schedule Impacts

8

Page 9: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

EJCDCEJCDC• Many of the terms and processes included in

this presentation are based on the Engineers Joint Contract Documents Committee Standard (EJCDC) General Conditions.

• Issued and Published by:– American Society of Civil Engineers– American Council of Engineering Companies– National Society of Professional Engineers

9

Disclaimer: Terms used here may vary depending on the Owner, process, and/or contract used.

Page 10: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Change Order ClausesChange Order Clauses

• Most construction contracts state “… the Owner has the right to issue changes without invalidating the Contract.”

• EJCDC – Article 10.01 (Work Change Directive or Change Order)

• AIA A201 – Section 7.3.1 (Construction Change Directive)

• FAR Contracts – Section 52.24310

Page 11: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Defining the ElementsDefining the Elements• Work Change Directive (WCD) – A statement to the Contractor

from the Owner (design team, Owner’s Rep, CM, etc.) requesting an addition, deletion, or change to the work.

• Field Directive (FD) – Written directive from the Owner directing a minor change to the work that will not impact the contract price or time.

– If the Contractor feels the WCD or FD impacts the budget or schedule, it is required to notify the Owner.

• Change Request (CR) – Notification from the Contractor to the Owner of a change to the Contract time and/or schedule

11

Page 12: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Defining the ElementsDefining the Elements

• Change Order (CO) – Document that incorporates changes to the scope, price and/or time into the Agreement/Contract.

– Bilateral Change Order – Change Order whereby both the Owner and Contractor agree to adjustment to the price and time.

– Unilateral Change Order – Change Order issued by the Owner when the Owner and Contractor cannot come to an agreement on the price and time.

• Claims – A demand or assertion by the Contractor (or Owner) for an adjustment to the contract time or price.

12

Page 13: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Owner Directed Owner Directed Change ProcessChange Process

Yes

Yes

Prepare WCD or FD

Reach Agreement

Send WCD/FD to Contractor

Prepare Engineer’s

Estimate of Time and Cost Impact

Withdraw WCD / FD

Contractor Prepares Cost & Time Estimate

Negotiate cost and schedule Impacts with Contractor

Owner Review Contractor's

Submittal

Contractor Determine if cost/

schedule impact

Contractor Notify the Owner that

cost or schedule will be impacted

YesContractor perform the work No

Execute Change Order

Issue Unilateral Change

No

No

13

The General Conditions of the Contract define the process to follow.

Page 14: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Contractor Change Request ProcessContractor Change Request Process

• Most Contracts do not spell out a “Contractor Change Request” process.

• If the Contractor wants to submit a change request it needs to follow the “claims” process defined in the contract to request a change.

CR Accepted

Yes

CR Accepted

Reach Agreement

Contractor Identifies a Change

Prepare Engineer’s

Estimate of Time and Cost Impact

Withdraw WCD / FD

Contractor Prepares Cost & Time Estimate

Negotiate Cost and ScheduleImpacts with Contractor

Owner Review Contractor's

Submittal

Owner’s Review

Execute Change Order

Issue Unilateral Change

No

No

Contractor Notifies the Owner with

Change Request

Contractor Prepares Claim

Contractor Withdraws Request

CR RejectedOptions

14

Page 15: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Notification RequirementsNotification Requirements

• EJCDC Contract states that the Contractor must notify the Owner within 30 days of notification of the change by way of the Claims clause. (Section 10)

• The AIA document has no requirement for submittal of Change Proposal.

• FAR General Conditions state that the contractor must assert its rights for added costs and/or time within 30 days of notice of change. (Section 53-243-4) 15

Page 16: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

• Include a requirement in the Contract’s General or Special Conditions or Division 1 such as:

“The Contractor has 10 days to provide the Owner with their cost and schedule impacts resulting from this Work Change Directive.”

• If the Contractor is “allowed” to extend the submittal date, don’t let the proposal submittal extend indefinitely.

• Benefits: – Receive the information early enough to make a decision on

whether to move forward with this change or an alternative.

– Resolve issue while fresh in everyone’s mind.

– Reduces ability to claim at the end of construction. 16

Recommended Practice Notification RequirementsRecommended Practice Notification Requirements

Page 17: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Sample Sample Change FormChange Form

Change Request

Title: No.:

Request Date:

Project:

Contractor:

Contract No.: WO Contract No.:

Initiated by: Owner Engineer Contractor CM Other:

Change Request The following change is proposed for the project. Please provide us with your proposed cost and schedule changes for this request as described below (use additional pages if necessary):

This work shall be constructed in accordance with the terms and conditions of the Contract Documents. The Contractor shall provide it’s proposal for this work by _____________________________.

Contractors Proposal: Increase Decrease $

Increase Decrease Days

Recommendation: Amount $

Comments

Accept Reject Accept Reject

HDR Engineering, Inc. Date Otak Date

Local Programs: Accepted Rejected By: Date:

Utility Provider: (if required)

Accepted

Rejected

By:

Date:

City:

Accepted Rejected By: Date:

17

Include a proposal return

date

Page 18: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Work Change DirectiveWork Change DirectiveProposal Submittal RequirementsProposal Submittal Requirements

• Pricing Changes– Forward pricing changes (direct and indirect costs)– Time and Material pricing– Define the basis for costs

• Labor rates• Equipment• Materials

– Define mark-ups– Define mark-up distribution 18

Page 19: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Forward Pricing ChangesForward Pricing Changes

• Agree on the change order price before the Contractor begins the added work

• Risk shifts from Owner to Contractor

• Need to address how to price or agree to the price for “potential” inefficiencies in forward pricing

19

Page 20: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

20

Advantages of Forward Pricing Advantages of Forward Pricing ChangesChanges

• Owner – Certainty of the cost and schedule impacts before changed work starts

• Contractor – Payment for the changed work when changed work is performed

Page 21: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

• Owner – They may feel they are paying more than the change is worth.

• Contractor – Changed work may cost more and/or take longer to complete than the agreed amount.

21

Risks of Forward Pricing ChangesRisks of Forward Pricing Changes

Page 22: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Final Thoughts on Forward Final Thoughts on Forward Pricing Changes Pricing Changes

• Lump Sum Proposal supported with cost breakdown.

• Some contracts define how changes should be priced in the changes clause. (AIA Section 7.3.6, NYC Contract Article 26)

• Others default to other clauses such as force account or accounting clauses. (EJCDC directs to Section 11.01, Section 15.4 of the FAR)

22

Page 23: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

• Define how the Contractor should price labor, materials, equipment, construction equipment and tools in the Contract.

If you cannot include this in the contract, then…

• Agree on how you plan to price labor, materials and equipment at the start of the project, before the first change is issued. 23

Recommended Practice

Forward Pricing Changes

Recommended Practice

Forward Pricing Changes

Page 24: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Defining Basis for CostsDefining Basis for Costs

• Determine how labor productivity will be defined: actual, projected, or industry defined production rates.

• Labor wage rates

– Davis Bacon

– Prevailing Wage Rates

– Contractor’s actual payroll

• Actual labor costs or blended rates.24

Page 25: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Forward Pricing ChangesForward Pricing Changes

• Material prices based on:– Invoices– Quotes– Audited costs

• Construction Equipment prices based on:– Invoices – Quotes– Contractor’s accounting records– AGC/Blue Book/Green Book

25

Page 26: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Change Order Mark-upsChange Order Mark-ups

• Some contracts define mark-ups.

• Typical mark-ups:– Labor 10% to 30%– Materials 10% to 20%– Equipment 10% to 20%– Subcontractor work 5% to 20%

.26

Page 27: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

EJCDC Mark-upsEJCDC Mark-ups

• EJCDC Contract Mark-ups.– Labor 15%– Materials & Equipment 15%– Construction Equipment 15%– Subcontractor work 5%

27

Page 28: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

AIA Document Addresses AIA Document Addresses Mark-upsMark-ups

• “…cost plus a reasonable sum for Overhead and Profit.”

.

28

Page 29: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

29

NYC Contract Mark-upsNYC Contract Mark-ups

• NYC Contract Mark-ups.– Overhead

• Labor 8% to 10%• Materials & Equipment 8% to 10%• Construction Equipment 8% to 10%

– Profit 10%

Page 30: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Florida DOT Florida DOT

• Labor 17.5%• Materials & Equipment 17.5%• Construction Equipment 17.5%• Subcontractor work 10% for first $50,000,

5% for amounts > $50k

+ Bond Costs

30

Page 31: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

CaltransCaltrans

– Labor 33%– Materials 15%– Equipment 15%– Subcontractor work 5%

31

Page 32: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

State of California State of California Depart of General Services Depart of General Services

• Allowable Contractor Mark-ups– Labor 21 %– Materials and Equipment 16 %– Subcontract Work 6 % – These costs include bond costs

• Allowable Subcontractor Mark-ups– Labor 20 %– Materials and Equipment 15 %– All Subcontract tiers shall not exceed 20 % for labor and

15 % for materials and equipment32

Page 33: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

ConsensusDOCSConsensusDOCS

33

“…costs calculated on a basis agreed upon by the Owner and Contractor plus ___% Overhead and ___% profit; or

… “…if there is a net increase in the Contract Price, the

Contractor’s Overhead and profit shall be adjusted accordingly.”

In case of a net decrease in the Contract Price, the Contractor’s Overhead and profit shall not be adjusted unless ten percent (10%) or more of the Project is deleted.

Page 34: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Time & Materials/Time & Materials/Force AccountForce Account

• When Owner and Contractor cannot agree on the costs, Owner issues the change directive to be performed on a time and materials basis.

• Risk is on Owner vs Contractor

• Payment based on actual costs plus agreed on mark-ups.

• Daily T&M sheets are completed and signed by the Contractor and Owner.

• Payment is made after incorporated into the Contract by Change Order.

• The contract should state what support activities and costs will be included in a time and materials change.

34

Page 35: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Advantages/Disadvantages Advantages/Disadvantages to T&Mto T&M• Advantages

– Owner – Work starts on change when directed; reduces potential for schedule impacts

– Contractor – Certainty of costs after the work is completed

• Disadvantages

– Owner – Uncertainty of costs when the change work begins

– Contractor – Loses ability to make more money on efficiencies

35

Page 36: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Change Order Mark-upsChange Order Mark-ups

• Define mark-ups in the Contract.

• Mark-ups should be reasonable and consistent with area practices.

• If you can’t put them in the Contract, then negotiate the rates at the start of the project as a first order of business.

36

Recommended PracticeRecommended Practice

Page 37: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Time & Materials WorkTime & Materials Work

• Issue a Not-to-Exceed amount for the changed work.

• Mark-ups (profit) for Time & Materials should be reduced due to reduced risk.

• If you can’t put them in the Contract, then negotiate the rates at the start of the project.

37

Recommended PracticeRecommended Practice

Page 38: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

• Field office – Identify facilities, office equipment, etc.• Field staff – Project Manager, Superintendent, Field

Engineers, administrative support, etc.• Home office – Office expenses, officers, legal, accounting, etc.• Insurance• Bonds• Profit/Fee • State whether OH included in the mark-ups is applied to any

contract time extensions38

Identify what the mark-ups cover Identify what the mark-ups cover Identify what the mark-ups cover Identify what the mark-ups cover

Recommended PracticeRecommended Practice

Page 39: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Proposal Submittal RequirementsProposal Submittal Requirements

• Schedule Impacts– Include schedule impacts in all changes to avoid schedule

impact claims at the end of the project.

– Require a preliminary Time Impact Analysis (TIA) with any schedule extension request and a TIA 30 days after the event is complete.

– Negotiate extended overhead and/or acceleration issue NOW – otherwise constructive acceleration.

– Agree on new project end date. 39

Recommended PracticeRecommended Practice

Page 40: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Cost of Extended OverheadCost of Extended Overhead

• Agree to extended overhead amount when you agree to the new contract completion date.

• Costs for extended overhead based on:– “Modified” Eichleay – Negotiated Amount/Rate– Time related overhead

40

NOTE: Some States have regulations prohibiting “No damages for delay clauses.”

Page 41: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Time Related Overhead (TRO)Time Related Overhead (TRO)

• California Department of Transportation (Caltrans) uses TRO on some Unit Price contracts– Bid Item either:

• Lump sum (divided by the number of contract days)• Daily Rate

– Contract states that the rate will be used for any schedule extension up to 180 days beyond original contract completion date.

41

Page 42: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Calculating Time-Related-OverheadCalculating Time-Related-Overhead

Lump Sum Overhead Amount $1,534,500.00

Contract Days (working days) 620

Daily Rate $ 2,475.00/day

Days Added by Change Order 12 days

Extended Overhead Amount to be included in Change Order $ 29,700.00

42

Page 43: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

• Define what is included in the extended overhead:– Construction support equipment (cranes, forklifts,

etc.)– Field office – Identify facilities, office equipment, etc.– Field staff - Project Manager, Superintendent, Field

Engineers, administrative support, etc.– Home office – Office expenses, officers, legal,

accounting, etc.

43

Recommended PracticeRecommended Practice

Identify How to Calculate Extended OHIdentify How to Calculate Extended OHIdentify How to Calculate Extended OHIdentify How to Calculate Extended OH

Page 44: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Managing the CO ProcessManaging the CO Process

• Develop a system for tracking changes

• Track status/disposition of the change

• Meeting regularly with the Contractor to resolve changes

• Meeting regularly with the Owner to resolve changes

44

Page 45: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Sample Two Step ProcessSample Two Step Process

• Step 1: Work Change Directives– Initiates the process– Resolves distinct issues

• Step 2: Change Orders– Needed to incorporate changes into contract– Accumulates Change Requests into single CO; thereby

reducing the approvals by the client’s board

Construction InstituteClaims Avoidance and Resolution

Committee

45

Page 46: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

46

Page 47: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Column HeadingsColumn Headings• Initiating InformationInitiating Information

– Number– Date Initiated– Description (Brief) – Status– Change Type

(FA, UP or LS)– Initiated by– Engineer’s Estimate– Date Sent to Contractor

• Funding Entities InformedFunding Entities Informed– Client– WSDOT (State DOT)– Utilities

• Contractor’s ProposalContractor’s Proposal– Date Received – Amount Proposed

Construction InstituteClaims Avoidance and Resolution

Committee

47

Page 48: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Column HeadingsColumn Headings• Resolution ApprovalsResolution Approvals

– Client (City)

– WSDOT

– Utilities• Additional Funding Partners

• Payment MethodPayment Method– Change Order #

– Payment Item (if applicable)

– Change Order Amount

• CommentsComments – Why, why not, what else

48

Page 49: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Managing the CO ProcessManaging the CO Process

• Dealing with changes promptly will have the least amount of impact on the budget and schedule.

• Failing to resolve changes promptly will increase their costs

• Failing to pay for changes in timely manner can result in violating prompt payment regulations

49

Page 50: 1 Contract Change Clause The Change Order Process Annual Program of the Claims Avoidance and Resolution Committee of the Construction Institute March 11,

Questions?

50