1 BROOKHAVEN SCIENCE ASSOCIATES
Ring Building Construction Status
Michael P. BromfieldConstruction Engineer
NSLS II Conventional Facilities Advisory Committee Review November 9-10, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline
• Introduction • Technical Progress• Cost Overview
– Budgeted value, – Contract value, – Approved changes to date– Estimate of Potential Changes – EAC
• Schedule Status• Issues & Risks• Look Ahead• Conclusions
3 BROOKHAVEN SCIENCE ASSOCIATES
Introduction
Construction Inspection Team (CIT) - Responsible to:
• Inspect work of the contractor to verify conformance of installed work with contract plans and specifications.
• Coordinate work of BNL support groups with contractor to assure that all required permits are in place prior to commencement of work.
• Assure that contractors perform work in accordance with applicable work controls requirements.
• Coordinate with the NSLS-II CSEs to assure that work progresses in accordance with the contract ESH requirements.
• Review contractor payment requests to verify completed quantities.
• Confirm testing proceeds with contract plans and specifications.
• Timely Response to Contractor(s) Requests• Follow-up on Compliance Notices to Ensure Matter Satisfactorily Resolved.
4 BROOKHAVEN SCIENCE ASSOCIATES
Overview
• Scope (WBS 1.05.03.02)• Construction of the Ring Building, Service Buildings• Installation of Utility Mains to Ring Building, including
– Primary Electric– Connection to Central Chilled Water & Compressed Air Mains– Installation of Water Loop
• On Site Infrastructure Improvements – Roads, Parking, Storm & Sanitary Systems
• Cost• Contract amount = $172.6M
• Initial Baseline = $167M (CD- 3)
• Pre-bid estimate = $194M (Sept 08)
5 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Project Site at January ’09
6 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Project Site at October ‘09
7 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Concrete Phasing Plan
8 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
– Baseline Critical Path – Construction Activities thru’ November ‘09
9 BROOKHAVEN SCIENCE ASSOCIATES
Project Site at October ‘09
Technical Progress
Ratchet Wall #25B (Col Ln. 3)
Ratchet Wall 27A (Col Ln. 3)
Ratchet Wall #22A (Col Ln. 103 )
Ratchet Wall #21A (Col Ln. 103 )
10 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Project Site at October ‘09
Vehicle Tunnel
Column Footing B-78
11 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Project Site at October ‘09
Curbs & Sidewalk in
Progress
12 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Underground Utilities
Domestic Water Main Installation
Electrical Ductbank Installation
13 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Some Challenges Faced
Geo-Thermal ExperimentWater Main Relocation for New Steam Line
14 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
15 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
Ring Building Project: CF Inspection Responsibility Matrix
DIVISION 2 - SITE WORKSPEC.
SECTIONTORCON S/C BNL BNL VENDOR BNL PROCEDURE
SITE EXCAVATION AND ROUGH GRADING INSPECTION 02210 LT-CF-05-001
COMPACTION DENSITY TEST 02210 MT GROUP LT-CF-05-002
MOISTURE DENSITY TEST 02221 MT GROUP LT-CF-05-002
TOP SOIL FINISHED GRADING INSPECTION 02260 LT-CF-05-001
EXFILTRATION TEST ON STORM DRAINAGE SYSTEM 02463 VOLLERS LT-CF-05-001
TESTING OF HIGH PRESSURE STEAM SYSTEM 02490 SIMS LT-CF-05-001
DENSITY TESTS ON PAVING SUB GRADE 02513 VOLLERS LT-CF-05-001
TEST COMPLETED WATER MAINS FOR LEAKAGE 02665 VOLLERS LT-CF-05-001
INSPECT U/G CHILLED WATER SYSTEM BEFORE BACKFILLING 02676 SIMS LT-CF-05-001
PRESSURE TESTING OF EXTERIOR COMPRESSED AIR SYSTEM 02678 SIMS LT-CF-05-001
LEAKAGE TEST OF SANITARY SEWERS 02732 VOLLERS LT-CF-05-001
16 BROOKHAVEN SCIENCE ASSOCIATES
Technical Progress
9/9/09
Meeting with. Testing Agency to Review Concrete Sampling & Testing
procedures
4000 psi
17 BROOKHAVEN SCIENCE ASSOCIATES
Schedule Status
Concrete Cylinder Break Test Results
18 BROOKHAVEN SCIENCE ASSOCIATES
Schedule Status
• Overall Project Status– 16% complete (per cost basis)– Concrete Work on Schedule, recovered rain impacts in June &
September– Underground Utility Work lagging due to Coordination Effort
(required to resolve interferences See Drawing)– Fabrication of Structural Steel slightly behind early finish
projections, but ahead of baseline.
19 BROOKHAVEN SCIENCE ASSOCIATES
Schedule Status
Underground Utility Plan C – 600• Substantial Utility Installation• Extensive coordination
20 BROOKHAVEN SCIENCE ASSOCIATES
Schedule Status
Intermediate Project Milestones thru’ March 2010
21 BROOKHAVEN SCIENCE ASSOCIATES
Schedule Status
Mandatory Project Milestone Report
22 BROOKHAVEN SCIENCE ASSOCIATES
Issues & Risks
• Potential Problems• Winter Concrete Work
– Winter Mix Design, Placement & Protection Plan
• Utility Installation in Inner Courtyard– Resolve Interferences (all resolved to date)– Coordination / Staging of Trades for Utility Work
• Potential for Construction Outpacing Design by ASD & XFD Groups
– Could necessitate revision to installed work
• Coordination between LOB & Ring Building Contractors
23 BROOKHAVEN SCIENCE ASSOCIATES
Look Ahead
• Place Storage Ring Tunnel Floor Slab at Utility & Vehicle Tunnels
– Allows backfill & continuity of Ring Storage Tunnel construction
• Construction of Underground Electric ductbanks• Installation of Steam Main to Project Site• Construct Selected Roadways & Parking Areas
– Control site drainage,– Facilitates better soil erosion control
24 BROOKHAVEN SCIENCE ASSOCIATES
Conclusion
• Continue to encourage pace of construction• At a safe rate
• Continue diligence of Inspections• Advance Construction Operations with an eye to Minimizing
Risks and Mitigating delays