1, 3 & 4 school model options april 9, 2013 restructuring of keene elementary schools

73
1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Upload: silvester-paul

Post on 15-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

1, 3 & 4 School Model Options

April 9, 2013

Restructuring of Keene Elementary Schools

Page 2: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Over the winter, the Board of Education decided to move toward a 4-school, wide grade span model, with Daniels housing the Preschool program

Following this, we received a Board request to provide a more detailed evaluation of several variations of 1, 3 and 4-school models

Today, we will be answering those questions

04/21/23 2KES restructuring – Marinace Architects

Where We Are Now

Page 3: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Provide cost analysis of creating 3 EQUALLY-sized K-5 schools, including Fuller & Symonds, with long-term expandability

Provide breakout cost of Preschool in that option Provide cost to close Daniels, Franklin, OR

Wheelock in the 4-school, wide grade span model Provide cost of building one large elementary

school and closing all existing schools

04/21/23 3KES restructuring – Marinace Architects

School Board Questions

Page 4: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Option 1A: 1-School, 1,200 student option Options 3A & 3B: 3-School, wide grade span options Options 4A, 4B, 4C, 4D: 4-School, wide grade span

options, each with a different combination of closed and expanded schools

04/21/23 4KES restructuring – Marinace Architects

Scope of This Presentation

Page 5: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Location of Keene Elementary Schools

04/21/23 5KES restructuring – Marinace Architects

Page 6: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Construct a new 1,200 student, 198,000 square foot P-5 school at the Daniels site

Existing Daniels school demolished Other 4 existing schools closed and sold

04/21/23 6KES restructuring – Marinace Architects

Option 1A

Page 7: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 7KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 11 11 11 11 9 9 62 + P

Franklin 0 0 0 0 0 0 0

Fuller 0 0 0 0 0 0 0

Symonds 0 0 0 0 0 0 0

Wheelock 0 0 0 0 0 0 0

Total 11 11 11 11 9 9 62

Class distribution – Total Capacity: 1,188 Students

Option 1A

Page 8: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 8KES Restructuring - Marinace Architects

Option 1A – Daniels Floor Plan

Page 9: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 9KES restructuring – Marinace Architects

Option 1A – Site Plan

Page 10: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 10KES restructuring – Marinace Architects

Option 1A – Summary

Page 11: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Significant operating cost savings, but a large capital investment is required

New, state-of-the-art space for all students High performance building heated from wood chip plant,

with low long-term maintenance costs Neighborhood schools replaced by one large school Maple Street site maxed out with 2,200 students on site,

creates traffic and access issues, congestion Another site needed for possible long-term expansion

04/21/23 11KES restructuring – Marinace Architects

Option 1A – Pros & Cons

Page 12: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Fuller & Symonds expanded from 3-section to 4/3-section schools. Capacity of each rises from 324 to 426 students

Daniels expanded from a 2-section to 3-section school. Capacity rises from 216 to 324 students

Preschool moves to Daniels Franklin & Wheelock closed and sold Total district capacity of 1,188 students K-5

04/21/23 12KES restructuring – Marinace Architects

Option 3A

Page 13: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 13KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 3 3 3 3 3 3 18 + P

Franklin 0 0 0 0 0 0 0

Fuller 4 4 4 4 3 3 22

Symonds 4 4 4 4 3 3 22

Wheelock 0 0 0 0 0 0 0

Total 11 11 11 11 9 9 62

Class distribution – Total Capacity: 1,188 Students

Option 3A

Page 14: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 14KES Restructuring - Marinace Architects

Option 3A – Daniels Floor Plan

Page 15: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 15KES Restructuring - Marinace Architects

Option 3A – Daniels Site Plan

Page 16: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 16KES Restructuring - Marinace Architects

Option 3A – Fuller Floor Plan

Page 17: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 17KES Restructuring - Marinace Architects

Option 3A – Symonds Floor Plan

Page 18: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 18KES Restructuring - Marinace Architects

Option 3A – Summary

Page 19: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Significant staff operating cost savings, but a large capital investment is required

Avoid CIP, maintenance and utility costs by closing two schools

Offers long-term expansion potential Neighborhood school model diminished More pressure placed on larger school cores

04/21/23 19KES restructuring – Marinace Architects

Option 3A – Pros & Cons

Page 20: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Same as Option 3A except Preschool is eliminated from Daniels School

Since Preschool is not accounted for elsewhere in this option, the difference in cost between Option 3A and Option 3B can be seen as a breakout cost for the preschool program

04/21/23 20KES restructuring – Marinace Architects

Option 3B

Page 21: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 21KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 3 3 3 3 3 3 18 + P

Franklin 0 0 0 0 0 0 0

Fuller 4 4 4 4 3 3 22

Symonds 4 4 4 4 3 3 22

Wheelock 0 0 0 0 0 0 0

Total 11 11 11 11 9 9 62

Class distribution – Total Capacity: 1,188 Students

Option 3B

Page 22: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 22KES Restructuring - Marinace Architects

Option 3B – Daniels Floor Plan

Page 23: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 23KES Restructuring - Marinace Architects

Option 3B – Summary

Page 24: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

This is the 4-school, wide grade span option favored up to this point Fuller & Symonds remain 3-section, 324 student schools, and receive small

additions Franklin expanded from a 2-section to 3-section school. Capacity rises from

216 to 324 students Preschool only at Daniels Wheelock remains a 2-section school Total district capacity of 1,188 students K-5

04/21/23 24KES restructuring – Marinace Architects

Option 4A

Page 25: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 25KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 0 0 0 0 0 0 Preschool

Franklin 3 3 3 3 3 3 18

Fuller 3 3 3 3 3 3 18

Symonds 3 3 3 3 3 3 18

Wheelock 2 2 2 2 2 2 12

Total 11 11 11 11 9 9 66

Class distribution – Total Capacity: 1,188 Students

Option 4A

Page 26: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 26KES Restructuring - Marinace Architects

Option 4A – Daniels Floor Plan

Page 27: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 27KES Restructuring - Marinace Architects

Option 4A – Fuller Floor Plan

Page 28: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 28KES Restructuring - Marinace Architects

Option 4A – Symonds Floor Plan

Page 29: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 29KES Restructuring - Marinace Architects

Option 4A – Franklin Floor Plan

Page 30: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 30KES Restructuring - Marinace Architects

Option 4A – Wheelock Floor Plan

Page 31: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 31KES Restructuring - Marinace Architects

Option 4A – Summary

Page 32: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Similar to Option 4A, except Wheelock closed instead of Daniels

Fuller & Symonds remain 3-section, 324 student schools, and receive small additions

Franklin remains a 2-section, 216 student school Daniels expanded from a 2-section to a 3-section,

324 student school, and receives a large addition. Preschool moves from Wheelock to Daniels

Total district capacity of 1,188 students K-5

04/21/23 32KES restructuring – Marinace Architects

Option 4B

Page 33: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 33KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 3 3 3 3 3 3 18 + P

Franklin 2 2 2 2 2 2 12

Fuller 3 3 3 3 3 3 18

Symonds 3 3 3 3 3 3 18

Wheelock 0 0 0 0 0 0 0

Total 11 11 11 11 9 9 66

Class distribution – Total Capacity: 1,188 Students

Option 4B

Page 34: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 34KES Restructuring - Marinace Architects

Option 4B – Daniels Floor Plan

Page 35: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 35KES Restructuring - Marinace Architects

Option 4B – Fuller Floor Plan

Page 36: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 36KES Restructuring - Marinace Architects

Option 4B – Symonds Floor Plan

Page 37: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 37KES Restructuring - Marinace Architects

Option 4B – Franklin Floor Plan

Page 38: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 38KES Restructuring - Marinace Architects

Option 4B – Summary

Page 39: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Similar to Option 4A, except Franklin closed instead of Daniels

Fuller & Symonds remain 3-section, 324 student schools, and receive small additions

Wheelock remains a 2-section, 216 student school Daniels expanded from a 2-section to a 3-section, 324

student school, and receives a large addition. Preschool moves from Wheelock to Daniels, and collaborative programs move from Franklin to Daniels

Total district capacity of 1,188 students K-5

04/21/23 39KES restructuring – Marinace Architects

Option 4C

Page 40: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 40KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 3 3 3 3 3 3 18 + P

Franklin 2 2 2 2 2 2 12

Fuller 3 3 3 3 3 3 18

Symonds 3 3 3 3 3 3 18

Wheelock 0 0 0 0 0 0 0

Total 11 11 11 11 9 9 66

Class distribution – Total Capacity: 1,188 Students

Option 4C

Page 41: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 41KES Restructuring - Marinace Architects

Option 4C – Daniels Floor Plan

Page 42: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 42KES Restructuring - Marinace Architects

Option 4C – Fuller Floor Plan

Page 43: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 43KES Restructuring - Marinace Architects

Option 4C – Symonds Floor Plan

Page 44: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 44KES Restructuring - Marinace Architects

Option 4C – Wheelock Floor Plan

Page 45: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 45KES Restructuring - Marinace Architects

Option 4C – Summary

Page 46: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Similar to Option 4B, except Franklin is expanded to a 3-section school instead of Daniels

Fuller & Symonds remain 3-section, 324 student schools, and receive small additions

Wheelock Closed Preschool moves from Wheelock to Daniels, and

Daniels received a medium-sized addition Total district capacity of 1,188 students K-5

04/21/23 46KES restructuring – Marinace Architects

Option 4D

Page 47: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 47KES restructuring – Marinace Architects

SchoolTypical no. of sections per gradeK 1 2 3 4 5

Total sections / school

Daniels 2 2 2 2 2 2 12 + P

Franklin 3 3 3 3 3 3 18

Fuller 3 3 3 3 3 3 18

Symonds 3 3 3 3 3 3 18

Wheelock 0 0 0 0 0 0 0

Total 11 11 11 11 9 9 66

Class distribution – Total Capacity: 1,188 Students

Option 4D

Page 48: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 48KES Restructuring - Marinace Architects

Option 4D – Daniels Floor Plan

Page 49: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 49KES Restructuring - Marinace Architects

Option 4D – Fuller Floor Plan

Page 50: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 50KES Restructuring - Marinace Architects

Option 4D – Symonds Floor Plan

Page 51: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 51KES Restructuring - Marinace Architects

Option 4D – Franklin Floor Plan

Page 52: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 52KES Restructuring - Marinace Architects

Option 4D – Summary

Page 53: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Analysis of staffing requirements for each option. Increases in staffing efficiencies are the most important factor in overall savings

CIP Tabulation for each option Budget for each option broken down by Additions,

Renovation, CIP and Operational costs

04/21/23 53KES restructuring – Marinace Architects

Cost Analysis

Page 54: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 54KES restructuring – Marinace Architects

1-School Staffing Tabulation

Page 55: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 55KES restructuring – Marinace Architects

3-School Staffing Tabulation (3A Shown)

Page 56: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 56KES restructuring – Marinace Architects

4-School Staffing Tabulation (4A Shown)

Page 57: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 57KES restructuring – Marinace Architects

5-School Staffing Tabulation (Existing)

Page 58: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

Include three categories: 1. (Shown in red) Items required by building code +

building heat conversion from steam to hot water included in the project budgets

2. (Shown in blue) Long-term CIP items that will need to be done in the next 10-20 years to maintain the buildings, not included in the project budgets

3. (Shown in black) Items the school district will complete outside of the building program not included in the project budgets

04/21/23 58KES restructuring – Marinace Architects

CIP Budgets

Page 59: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 59KES restructuring – Marinace Architects

CIP - Daniels

Page 60: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 60KES restructuring – Marinace Architects

CIP - Fuller

Page 61: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 61KES restructuring – Marinace Architects

CIP - Wheelock

Page 62: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 62KES restructuring – Marinace Architects

CIP - Franklin

Page 63: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 63KES restructuring – Marinace Architects

Overall Project Budgets

Page 64: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

CIP heat conversion is included, at a cost of $3,386,000 to the budget of 3 and 4-school options, and reduces the annual savings by up to $267,000

1 and 3-school options assume that unused buildings will be sold at a price of $750,000 each

Staffing figures and salaries have been updated. Preschool staffing has increased in all new configurations by $121,000 (1 teacher, 1 para)

04/21/23 64KES restructuring – Marinace Architects

Budgets Notes

Page 65: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 65KES Restructuring - Marinace Architects

Option 1A - Budget

Page 66: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 66KES Restructuring - Marinace Architects

Option 3A - Budget

Page 67: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 67KES Restructuring - Marinace Architects

Option 3B - Budget

Page 68: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 68KES Restructuring - Marinace Architects

Option 4A - Budget

Page 69: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 69KES Restructuring - Marinace Architects

Option 4B - Budget

Page 70: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 70KES Restructuring - Marinace Architects

Option 4C - Budget

Page 71: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 71KES Restructuring - Marinace Architects

Option 4D - Budget

Page 72: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

04/21/23 72KES Restructuring - Marinace Architects

Budget Summary

Page 73: 1, 3 & 4 School Model Options April 9, 2013 Restructuring of Keene Elementary Schools

For a copy of this presentation visit

www.KeeneSchoolSolutions.org

04/21/23 73KES restructuring – Marinace Architects