08.21.2019 addendum no 1 - bid packages - huckabee

267
267

Upload: others

Post on 17-Jan-2022

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

267

Page 2: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 1A - GENERAL WORKS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 3: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 4: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 5: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82

Provide all labor, equipment, materials and incidentals to complete the following

scope of work as relates to the GENERAL WORKS requirements. Included within

this scope of work is all project plans, specifications, addendum, value engineering

and all uniform general & supplementary conditions.

Yes

83

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included.Yes

84

Provide all site layout and field engineering for the new addition, site utilities and

miscellaneous site appurtenances. Provide verification of building plumbness at all

exterior vertical columns and walls. Coordinate alignment of exterior walls and

openings with structural steel components and structures. Provide field verification

and quality control of location of building corners, foundations and ground structures

within building area.

Trade Specific Scope

Page 6: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

85Provide site security for new addition. Include three days week from 9 pm until 5 am.

Days will include Wednesday, Saturday and Sunday.

86

Provide one project sign, 4'x8', ground mounted on post in concrete footings. See

documents for complete requirements.

87

Provide temporary access and parking for project laydown area. Include site entry

and location on the west side of building. Include 6" of crushed concrete with a filter

fabric underlayment. Area to include 18,100 sqft. Include the loading and haul-off at

project completion. Include dress-up and grading of area after removal.

88

Provide temporary mats at perimeter of new addition for stabilized work area for

motorized lifts for materials placement, scaffolding and man lifts to access work.

Provide 66 each 8'x16' matts. Include the removal and haul-off. Include 4 months of

rental.

89

Provide temporary water for construction use. Include the service to the new building

area. Include 21 months of service.

90Provide temporary power and service for construction use. Include the service to the

new building area. Include 21 months of service.

91

Provide material handling of stored equipment as required for staging each phase of

the interior work. Include one operated skid steer and one helper for a 15 month

period of time. Include 20 hours per week.

92

Provide access control for entry and exit of existing building. Include one man to

manage the coordination of daily entry and exit of construction personnel, managing

the temporary partition(s) security and upkeep. Include 40 hours per week for a

period of 15 months.

93

Provide the installation of temporary construction fence panels at perimeter of work

area. Include surface mounted post and legs with sand bags for stability. Include

1,525 lnft of 6' high chain-link with vision screen. Include 3, 20' double gates and 3,

personnel gates. Remove and haul-off at project completion. Include 21 month

rental period.

94

Provide temporary tree protection fencing at perimeter of existing trees to remain.

Include 1,500 lnft of 6' chain-link fence panels with surface mounted post and legs

with sand bags for stability. No vision screen required. Include 10 month rental

period. Remove and haul-off at project completion.

95

Maintain existing grassed areas at perimeter of construction area and around job

trailer. Include 2 trips per month for maintaining for 21 months.

96Provide routine watering and maintenance of existing trees during construction.

Include 4 trips per month for 21 months of watering.

97Provide daily cleanup of project. Include one man for 8 hours per day. Include 40

hours per week for a duration of 10 months for the new addition. Include two men

for 8 hours per day for a duration of 15 months for the existing building.

98

Provide continuous clean-up of exterior site and paving areas during construction.

Include 40 hours per month for 21 months. Include sweeper and labor to manage the

cleanup of the entire site during each trip.

99

Provide final cleaning services for the new addition and the existing building. Include

clearing all new and existing furniture, walls, floors, glass openings, doors, frames and

all other typical items requiring cleaning. Include waxing of resilient floors per the

manufacturers recommendations. Include one rough clean prior to the final cleaning.

100 Provide cleaning of all new paving and sidewalks at project completion.

101

Provide street cleaning. Include adequate equipment and labor to accomplish a clean

public street and right of way. Include one cleaning per week for a period of 10

months.

102Provide restoration of existing grass areas at project completion. Include fine grading

and hydromulch seeding. Include an area of 101,350 sqft.

103

Provide a complete storm water pollution prevention system, including fencing, inlet

protection, storm water pollution plan, permits, sloped embankment protection at

detention pond, stabilized construction entry, concrete truck washout and

maintenance, filter damns, removal of all controls at project completion, cleaning of

storm system at project completion.

104

Stake and protect existing structures, facilities and miscellaneous items to remain

during construction. Allow one trip of layout and protection once per month for a

period of 21 months.

Page 7: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

105

Provide temporary partitions at existing building for security and separation of

students and faculty from the planned work areas. Provide a 6" metal stud wall

system with 5/8" type "x" fire rated material on each side, height of wall to be 12'.

Include 550 lnft of wall system with 5 each fire rated man doors. Location to be

determined. Include the demounting and haul-off of the system at project

completion.

106

Provide floor protection at areas within the existing building that have heavy overhead

equipment installation and access pathways to work area. Include 3/8" thick

masonite, taped at joints. Include purchasing of 25,600 sqft of masonite. Include

removal and disposal at project completion.

107

Provide scaffolding system underneath the clerestory construction area with

protective platform for protection of existing building and personnel below work area.

Include and area of 1,500 sqft at 4 each locations. Include a rental period of 15

months.

108

Provide the removal of all dirt spoils generated by the site utility, plumber and

concrete trades. Locate spoils as directed Superintendent. Load and haul-off as

directed by Superintendent. Include 521 cy for site utilities, 247 cy for plumbing and

428 cy for concrete. Total volume is 1,196 cy.

109Provide temporary dewatering of surface water after rain events. Allow 4 trips per

month for 8 months.

110

Maintain exterior site conditions at perimeter of building during construction for a

safe and usable site. Include grading and maintain a level working site. Include one

trip per week for 10 months.

111Provide temporary platforms and access way for new addition roof work. Include one

temporary stair tower for 3 months.

112Provide progress photos each month for the new addition. Include pictures of the

exterior of the building from 4 vantage points. Include 8 pictures of the interior and

two aerials. Include monthly progress photos for 10 months.

113

Provide saw-cutting and removal of existing sidewalks, curbs and paving at areas to

receive new paving, walks and curbs. Remove debris from site.

114

Provide all topsoil, grading, flexterra HP-FGM at detention pond. Water and maintain

until grass is established and accepted by owner. Include 3 months of watering and

maintenance for establishing growth.

115

116 Subtotal - Scope Revisions -$

117 Yes

118 Yes

119 Yes

120 Yes

121 Yes

122 Yes

123 Yes

124 Yes

125 Subtotal - Alternates -$

126 Yes

127 Yes

128 Yes

129 Subtotal - Value Engineering -$

130 Yes

131 Yes

132 Yes133 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 8: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 1B - FINAL CLEAN Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 9: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 10: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 11: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 GeneralProvide all FINAL CLEANING of the building at completion including but not limited

to the following:Yes

83General

Provide one initial rough clean and one final clean of the new addition including the

cleaning or the exterior glazing system and glass. Yes

84General

Provide one initial rough clean and one final clean of the existing building during the

Summer of 2020.Yes

85General

Provide one initial rough clean and one final clean of the existing building during the

Summer of 2021.Yes

86 General Provide final clean of all corridors during the 2019 Christmas Break Yes

87 General Provide final clean of all corridors during the 2020 Spring Break. Yes

88 General Provide waxing of all resilient floors. Yes

89 General Yes

90 Yes

91 Yes

Trade Specific Scope

Page 12: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92 Subtotal - Scope Revisions -$

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Subtotal - Alternates -$

102 Yes

103 Yes

104 Yes

105 Subtotal - Value Engineering -$

106 Yes

107 Yes

108 Yes109 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 13: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 2A - DEMOLITION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 14: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 15: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 16: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition Yes

83 02 4113.10 Removing Existing Pavement & Structures Yes

84 Yes

85 Yes

86

Provide a Complete Turnkey Scope of Work for DEMOLITION, including but not

limited to make safe, haul off, salvage, removal of complete system associated with

all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

87

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

88 Includes all tear down, hauling, and dump fees Yes

89

Provide roll off dumpsters for this scope of work. All material removal is at

subcontractors expense. S&P will not provide dumpsters for this scope of work.

Yes

Trade Specific Scope

Page 17: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

90

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

91 Protection of existing structures, finishes, and equipment that will remain in placeYes

92 Demolition and removal of all MEP equipment and ductwork as indicated Yes

93 Cut and make safe all utilities Yes

94 Demo of MEP pads as required Yes

95 Demo of Temporary classroom swing space Yes

96

All interior phased selective demolition indicated in Drawings and Notes. Includes but

not limited to making existing openings larger, walls, slab on grade, stairs and railings,

ceilings

Yes

97 Demo existing building as indicated, protect existing column to remain Yes

98 Saw cut and demo of concrete for structural work / repairs Yes

99

Provide all necessary temporary shoring, bracing, or supports as required to maintain

existing structural and building elements to remainYes

100 Demo debris to be removed daily Yes

101 All demo abutting existing to remain to be neat and clean cut Yes

102 All saw cutting as required for the performance of this work Yes

103 Dust control including temporary filters to protect HVAC system Yes

104

Provide all access required for the installation of this work including but not limited to

removal and repair/replacement of doors, walls, ceilings, MEP systems, protection of

existing to remain, etc.

Yes

105

Everything listed and shown on the following drawings: S0.1 thru S0.7, S1.2, AD1.1

thru AD1.7, PD1.01, EFD2.1 thru EFD2.6, MD1.00, ED1.00 and TSD2.1 thru TSD2.6.

Yes

106 The following items are to be included below but not limited to: Yes

107 Remove SOG at existing restroom areas Yes

108 Remove Metal Deck Yes

109 Remove Millwork and Countertop Yes

110 Remove Door and Hardware, Frame to Remain Yes

111 Remove Gates Yes

112 Remove Door Hardware Only - Salvage Yes

113 Remove Door, Hardware and Frame Yes

114 Remove Window, Hardware and Frame Yes

115 Remove Skylight - (Count 1 EA) Yes

116 Remove Skylight and Curb - (Count 4 EA) Yes

117 Remove Standing Seam Roof Down to Existing Deck Yes

118 Remove Roofing Assembly Down to Existing Deck Yes

119 Saw cut Roofing Yes

120 Remove Fascia Yes

121 Remove Roof Hatch Yes

122 Remove Drywall Yes

123 Cut Exterior Drywall Assembly for Opening Yes

124 Remove Gypsum Board from Drywall Yes

125 Remove Bulkhead - Furrdown Yes

126 Remove Ceiling and Grid - Gypsum Yes

127 Remove Ceiling and Grid - Lay In Yes

128 Remove Flooring with Base - Carpet Yes

129 Remove Flooring with Base - Tile Yes

130 Remove Flooring with Base - VCT Yes

131 Remove Wall Tiles Yes

132 Remove Vinyl Wall Covering - 10' H Assumed Yes

133 Remove Marker board/Tack board Yes

134 Remove Toilet Accessories Yes

135 Remove Toilet Partitions Yes

136 Remove Urinal Screen Yes

137 Remove Folding Partition - 10' 06" H Assumed Yes

138 Remove Active Board, Projector, Speakers Yes

139 Remove and Salvage Furniture and Shelving Yes

140 Yes

141 Subtotal - Scope Revisions -$

142 Yes

143 Yes

Project Alternates

Page 18: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

144 Yes

145 Yes

146 Yes

147 Yes

148 Yes

149 Yes

150 Subtotal - Alternates -$

151 Yes

152 Yes

153 Yes

154 Subtotal - Value Engineering -$

155 Yes

156 Yes

157 Yes158 Yes

Project Value Engineering

The following items are specifically EXCLUDED:

Page 19: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 3A - CONCRETE Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 20: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 21: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 22: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition Yes

83 02 41113.10 Removing Existing Pavement & Structures Yes

84 03 1000 Concrete Forming & Accessories Yes

85 03 2000 Concrete Reinforcing Yes

86 03 3000 Cast-In-Place Concrete Yes

87 32 1313.00 Concrete Paving Yes

88 32 1313.10 Concrete Pavement Curing Yes

89 32 1313.25 Concrete Sidewalks Yes

90 32 1373 Concrete Paving Joint Sealants Yes

91 32 1613 Curb & Gutter Yes

92 Yes

93 Yes

94 Yes

95 Yes

Trade Specific Scope

Page 23: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

96

Provide a Complete CONCRETE SYSTEM, including but not limited to all concrete

paving, sidewalks, curbs, construction joints, building concrete, foundations,

plinths, grade beams, SOG, joints, formwork, reinforcing steel, finishing, curing,

equipment to place, rubbing, patching, miscellaneous housekeeping equipment

pads, excavation, backfill and compaction that are associated with project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

97

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.Yes

98

Restroom Slabs on Grade replacement including but not limited to final grading,

moisture barrier, forming, reinforcing, pouring, finishing, and curingYes

99 Restroom Slab Saw Cut, demo, haul off and disposal of same Yes

100

Restroom Subgrade prep including excavate, haul off and dispose of same, import fill

and compact as indicatedYes

101 Pour Back of Concrete at Demo Restroom Slabs Yes

102 Drill piers, foundations and grade beams as indicated Yes

103 Installation of Pipe Bollards as indicated Yes

104 Housekeeping Pads and Curbs as indicated Yes

105

Provide all access required for the installation of this work including but not limited to

removal and repair/replacement of doors, walls, ceilings, MEP systems, protection of

existing to remain, etc.

Yes

106 All associated work (epoxy, dowels, etc.) as shown on the Structural drawings Yes

107 Spoils Removal and Haul Off Yes

108 Joint Sealants Yes

107 Shooting Shim Packs At Column Base Plates Yes

108 Yes

109 Subtotal - Scope Revisions -$

110 Yes

111 Yes

112 Yes

113 Yes

114 Yes

115 Yes

116 Yes

117 Yes

118 Subtotal - Alternates -$

119 Yes

120 Yes

121 Yes

122 Subtotal - Value Engineering -$

123 Yes

124 Yes

125 Yes126 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 24: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 3B - LIGHTWEIGHT CONCRETE ROOF INSULATION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 25: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 26: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 27: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 03 5216.16 Lightweight Concrete Roof Insulation Yes

83 Yes

84

Provide a Complete LIGHTWEIGHT CONCRETE ROOF INSULATION SYSTEM per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

Trade Specific Scope

Page 28: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

85

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.Yes

86 All equipment required for placing materials. Yes

86 Lightweight Insulating Concrete (R103/G3.1)

87 Provide metal roof decking for this system. Yes

88 Lightweight Insulating Concrete (R103/G3.1) Yes

88

Provide clean up associated with this scope of work, including sweeping and removal

of materials on floor slab at completion of work.Yes

89

Provide haul-off of cleaned up materials and debris associated with your scope of

work.Yes

90 Provide touch painting of deck welds as required. Yes

90 Yes

91 Subtotal - Scope Revisions -$

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Subtotal - Alternates -$

101 Yes

102 Yes

103 Yes

104 Subtotal - Value Engineering -$

105 Yes

106 Yes

107 Yes108 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 29: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 4A - MASONRY Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 30: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 31: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 32: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition Yes

83 04 0100 Maintenance Of Masonry Yes

84 04 0511 Mortar & Masonry Grout Yes

85 04 0513.19 Masonry Mortaring Restoration Yes

86 04 2000 Unit Masonry Yes

87 Yes

88 Yes

89

Provide a Complete MASONRY SYSTEM, including but not limited to unit masonry,

brick to match, grout, mortar, flashing, rigid insulation, crack repair, anchors,

hoisting and scaffolding, reinforcing steel, toothing and moisture control associated

with all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

Trade Specific Scope

Page 33: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

90

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

91

Furnish and install all masonry work as shown on the plans complete, including all but

no limited to, concrete masonry units (CMUs), face brick, mortar & grout, and cast

stone materials. Reuse of existing face brick removed from the existing building if

available may be required as necessary for the field conditions where the new work

ties into the existing building. Furnish matching brick as necessary

Yes

92

Remove from site all trash and spoils created from this scope of work during and after

all masonry work is complete to the satisfaction of the Construction Manager.Yes

93

Provide and install all masonry anchors as necessary, including all welded anchors and

welding equipment. Yes

94 All hoisting and scaffolding required for this work. Yes

95 All masonry reinforcing steel as required Yes

96

Masonry work terminating against the underside of the structure or metal deck shall

be wedged tight and the joints filled with mortar, compressible filler, or safing

insulation as required by Contract Documents.

Yes

97 Grouting door and window frames in masonry work Yes

98

Prep and tooth-in of masonry at existing to new. Areas included but not limited to

new window and door openings, patching of holes from louvers being removed, walls

removed, etc.

Yes

99 Library Masonry For Toothing In Skylight & Framing Yes

100 Façade Masonry Crack Repair Yes

95 Self Adhered Flashing With Mortar Dropping Collection System Yes

96 Temporary matts necessary for access of work areas. Yes

97 Temporary bracing and forms for permanent openings. Yes

98 Yes

99 Subtotal - Scope Revisions -$

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Yes

106 Yes

107 Yes

108 Subtotal - Alternates -$

109 Yes

110 Yes

111 Yes

112 Subtotal - Value Engineering -$

113 Yes

114 Yes

115 Yes116 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 34: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 5A - STRUCTURAL STEEL FABRICATION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 35: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 36: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68 Yes

69 Yes

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Div. & individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 37: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition Yes

83 05 1200 Structural Steel Framing Yes

84 05 2100 Steel Joist Framing Yes

85 05 3100 Steel Decking Yes

86 05 3123.13 Steel Roof Decking Remediation Yes

87 05 5000 Metal Fabrications Yes

88 Yes

89 Yes

90

Furnish all STRUCTURAL STEEL FABRICATION, included but not limited to structural

steel, miscellaneous steel, steel supports, steel bracing, anchor bolts, plates, shims,

joists, beams, metal decking and shop drawings associated with all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

91

This is a phased project. All deliveries required to meet the phasing plan are included.

Night and weekend work will be required.Yes

Trade Specific Scope

Page 38: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92 MEP Roof Top Unit Additional Steel Supports Yes

93 New Skylights Steel Supports Yes

94 Pinch Points Steel, Decking, and Rails Yes

95 New Folding Partition Supports Yes

96 Steel support framing at new slab and roof penetrations Yes

97 Furnish anchor bolts as required Yes

98 Furnish removable queing post and steel bollards as indicated Yes

99 Window and wall bracing Yes

100 Reinforcing of existing steel joists and beams as indicated Yes

101

Provide all field measurements of existing conditions for the development of shop

drawings, fabrication, and installationYes

102 Confirm operating weight of new equipment for development of shop drawingsYes

103 Yes

104 Yes

105 Subtotal - Scope Revisions -$

106 Yes

107 Yes

108 Yes

109 Yes

110 Yes

111 Yes

112 Yes

113 Yes

114 Subtotal - Alternates -$

115 Yes

116 Yes

117 Yes

118 Subtotal - Value Engineering -$

119 Erection and installation. Refer to Work Package 5B Steel Erection. Yes

120 Yes

121 Yes122 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 39: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 5A - STRUCTURAL STEEL FABRICATION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 40: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 41: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68 Yes

69 Yes

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Div. & individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 42: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition Yes

83 05 1200 Structural Steel Framing Yes

84 05 2100 Steel Joist Framing Yes

85 05 3100 Steel Decking Yes

86 05 3123.13 Steel Roof Decking Remediation Yes

87 05 5000 Metal Fabrications Yes

88 Yes

89 Yes

90

Provide all labor, equipment and incidentals necessary for ERECTION OF ALL

STRUCTURAL STEEL AND MISCELLANEOUS METALS per all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

91

This is a phased project. All deliveries required to meet the phasing plan are included.

Night and weekend work will be required.Yes

Trade Specific Scope

Page 43: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92

Erection to include but not limited to the following: structural steel, miscellaneous

steel, steel supports, steel bracing, plates, shims, joists, beams, metal decking per

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

93 MEP Roof Top Unit Additional Steel Support Erection Yes

94 New Skylights Steel Support Erection Yes

95 Pinch Points Steel, Decking, and Rail Erection Yes

96 New Folding Partition Support Erection Yes

97

Patch holes from penetrations in roof with new decking as indicated associated with

erection of miscellaneous metals.Yes

98 Erection of steel support framing at new slab and roof penetration Yes

99 Set removable queuing post and steel bollards as indicated Yes

100 Window and wall bracing erection Yes

101

Erection of all miscellaneous metals included in this scope of work and required to

complete this scope of work to its entiretyYes

102

Unloading and moving temporary matts necessary for your access to work and around

the site for crane and equipment. Matting material is provided by others.Yes

103 Yes

104 Yes

105 Yes

106 Subtotal - Scope Revisions -$

107 Yes

108 Yes

109 Yes

110 Yes

111 Yes

112 Yes

113 Yes

114 Yes

115 Subtotal - Alternates -$

116 Yes

117 Yes

118 Yes

119 Subtotal - Value Engineering -$

120 Yes

121 Yes

122 Yes123 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 44: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 6A - ROUGH CARPENTRY Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 45: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 46: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 47: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 06 1053 Miscellaneous Rough Carpentry Yes

84 06 2000 Finish Carpentry Yes

85 Yes

86 Yes

87 Yes

88

Provide a Complete Turnkey Scope of Work for ROUGH CARPENTRY per all project

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.Yes

90

framing lumber, misc. lumber, treated wood, fire-retardant-treated wood, plywood,

fasteners, anchors, nailers, blocking, etc. in accordance with the contract documents.

91 Provide all roof blocking in accordance with the contract documents. Yes

Trade Specific Scope

Page 48: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92

Provide all exterior window jamb/sill/header blocking in accordance with the contract

documents.Yes

93

Provide all exterior door jamb/header blocking in accordance with the contract

documents.Yes

94 Provide all exterior louver blocking in accordance with the contract documents. Yes

95

Provide all top of wall blocking associated with the service yard walls in accordance

with the contract documents.Yes

96

Provide all blocking & plywood underneath Cast Stone Sills in accordance with the

contract documents.Yes

97

Provide all blocking behind non-suspended plaster soffits in accordance with the

contract documents.Yes

98

Provide all interior window jamb/sill/header blocking in accordance with the contract

documents.Yes

99

Provide all interior door jamb/header blocking in accordance with the contract

documents.Yes

100

Provide all blocking located inside drywall partitions for toilet accessories and

partitions in accordance with the contract documents.Yes

101

Provide all butt-glazed glass system jamb/header/sill blocking in accordance with the

contract documents.Yes

102

Provide all blocking to support locker bases in accordance with the contract

documents.Yes

103 Provide all blocking behind lockers in accordance with the contract documents. Yes

104

Provide all blocking/strapping as required to support Plasma/LCD monitor mounting

brackets in accordance with the contract documents.Yes

105

Provide all blocking/strapping required for support of all non-welded hand/grab

railings only located in drywall partitions in accordance with the contract documents.Yes

106

Provide all blocking/strapping required to support casework/shelving, countertops, &

millwork in accordance with the contract documents.Yes

107

Provide all blocking/strapping as required to support marker boards & tack boards in

accordance with the contract documents.Yes

108

Provide all plywood sheathing in MDF and IDF rooms per the contract documents.

Coordinate location w/ CM.Yes

109 Yes

110 Yes

111 Subtotal - Scope Revisions -$

112 Yes

113 Yes

114 Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Yes

120 Subtotal - Alternates -$

121 Yes

122 Yes

123 Yes

124 Subtotal - Value Engineering -$

125 Yes

126 Yes

127 Yes128 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 49: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 7A - WATERPROOFING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 50: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 51: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 52: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 07 1326.13 Self-Adhering Sheet Through Wall Flashing Membrane Yes

83 07 2500 Weather Barriers Yes

84 07 9005 Joint Sealants Yes

85 Yes

86 Yes

87 Yes

88 Yes

89 Yes

90

Provide a Complete Turnkey Scope of Work for WATERPROOFING AND SEALANTS,

including but not limited to mockups, submittals, samples, testing, warranties,

barriers, membranes, moisture penetration and coatings associated with project

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

Trade Specific Scope

Page 53: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

91

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

####

Furnish and install all materials and accessories as necessary to provide complete

vertical and horizontal waterproofing at or below grade.Yes

96

Protect finished water-repellent from staining, marring and damages from work of

other trades. Correct damage to work of other trades caused by water-repellent

application, as approved by Architect.

Yes

97 Test for water repellency and graphically report test locations. Yes

98

Furnish and install all materials and accessories as necessary to provide complete

water repellents.Yes

99

Verify that required repairs are complete, cured, and dry before applying water

repellent.Yes

100

Furnish and install all materials and accessories as necessary to provide complete fluid

applied membrane air barrier system.Yes

101 Protect air barrier components from freezing, extreme heat, and exposure to sunlight. Yes

102

If evidence of moisture penetration is discovered, apply an additional coat of

approved fluid applied air and vapor barrier and/or transition strips to exterior

surface, repeating application and testing (at no additional cost to the Owner) until no

evidence of moisture penetration is found.

Yes

103 Protect air barrier system from damage during subsequent operations. Yes

104 Provide pH testing as required prior to application of membrane/coating materials.Yes

105

Provide and install all paving and sidewalk sealants as required. This includes but is

not limited to paving expansion joints, saw cut joints, paving/sidewalk to building

expansion joints and sidewalk to curb expansion joints. Redwood/protective strip

removal and sealants at vertical curbs are included.

Yes

106

Provide and install sealant including but not limited to all masonry control joints, H.M.

doors, parapets, cast stone, tilt walls, and walkway covers. Includes joints at metal

panels to masonry and to copings to masonry.

Yes

107 Provide and install joint sealants at all slab on grade saw cut control joints. Yes

108

Preparation of surfaces to receive waterproofing, water repellents, and joint sealants

is included.Yes

109 Furnish and install caulking and waterproofing at louvers. Yes

110

Provide and install all termination bars, backer rods, mastic, primers, tapes,

prefabricated drainage mats, hypalon strips, etc.Yes

111 Provide joint sealant between drywall and masonry joint. Yes

112 Yes

113 Yes

114 Subtotal - Scope Revisions -$

115 Yes

116 Yes

117 Yes

118 Yes

119 Yes

120 Yes

121 Yes

122 Yes

123 Subtotal - Alternates -$

124 Yes

125 Yes

126 Yes

127 Subtotal - Value Engineering -$

128 Yes

129 Yes

130 Yes131 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 54: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 7B - THERMAL INSULATION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 55: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 56: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 57: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 07 2100 Thermal Insulation Yes

83 Yes

84 Yes

85

Provide a Complete Turnkey Scope of Work for THERMAL INSULATION per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

86

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

87

Furnish and install all materials and accessories as necessary to provide complete

thermal insulation system per the contract documents.Yes

88 Provide batt insulation in framed walls per the contract documents. Yes

89 Provide cavity rigid wall insulation per the contract documents. Yes

90 Provide blanket insulation per the contract documents. Yes

91 Install insulation in miscellaneous voids per the contract documents. Yes

Trade Specific Scope

Page 58: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92 Provide all mockups, submittals, and samples as required. Yes

93 Provide all warranties and special warranties as required. Yes

94 Provide all testing as required by the contract documents and the manufacturer.Yes

95 Yes

96 Subtotal - Scope Revisions -$

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Subtotal - Alternates -$

106 Yes

107 Yes

108 Yes

109 Subtotal - Value Engineering -$

110 Yes

111 Yes

112 Yes113 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 59: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 7C - ROOFING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

A Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 60: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 61: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 62: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 06 1053 Miscellaneous Rough Carpentry Yes

84 07 2200 Roof & Deck Insulation Yes

85 07 5216 Styrene -Butadiene-Styrene Modified Bituminous Roofing Membrane Yes

86 07 6113 Sheet Metal Roofing Yes

87 07 6200 Sheet Metal Flashing & Trim Yes

88 07 7200 Roof Accessories Yes

89 07 7265 Non-Penetrating Portable Rooftop Supports Yes

90 Yes

91 Yes

92 Yes

Trade Specific Scope

Page 63: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

93

Provide and install a Complete Turnkey ROOFING SYSTEM, including but not limited

to demolition, roof curbs, rough blocking, plywood substrates, tapered insulation,

joints, sealants, warranties, testing, pipe support and penetrations, firestopping,

flashings, sheet metal, roof expansion joints and miscellaneous materials required

for a complete roofing system associated with all project plans, specifications,

addendum, value engineering and all uniform general & supplementary conditions.

Yes

94

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

95 Demo roof at all new equipment openings per the contract documents. Yes

96 Demo roof at all new skylight openings per the contract documents. Yes

97

Demo includes removing existing roofing materials for new curb and penetrations and

saw cutting metal deck.Yes

98

Installation of equipment curbs at new and existing locations provided by others this is

to include blocking per the contract documents.

99

Installation of flashing and roofing materials at equipment curbs, skylights, hot stacks,

pipe penetrations, hooded curbs, equipment support and pipe supports to maintain

manufacturer's warranty and per the contract documents.

Yes

100

All roof board insulation and accessories, including but not limited to roof insulation,

expansion joints, primers, board insulation, cover board, crickets, edges, composite

insulation, strapping, fasteners, screws, adhesives, cants, colors (top color, etc.),

temporary waterproofing, cold weather application, etc.

Yes

101

All flashing, sheet metal, and other miscellaneous materials required for a complete

roofing system as specified in the contract documents.Yes

102

All flashing and curbs for any drains, vents or other penetrations thru new or existing

roof.Yes

103 Yes

104 Yes

105 Subtotal - Scope Revisions -$

106 Yes

107 Yes

108 Yes

109 Yes

110 Yes

111 Yes

112 Yes

113 Yes

114 Subtotal - Alternates -$

115 Yes

116 Yes

117 Yes

118 Subtotal - Value Engineering -$

119 Yes

120 Yes

121 Yes122 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 64: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 7D - METAL WALL PANELS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis. Suggested

solutions or substitutions shall accompany the notification whenever possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on all

contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not intended

to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow Contractor

to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their schedule

commitments to the Contractor are the responsibility of the Subcontractor. It is also

understood that to meet certain project requirements it will be necessary to perform

some work tasks during nights, weekend, and holidays, off-hours, or make-up hours (i.e.

shift work, additional manpower, and/or acceleration). All premium costs associated

with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is responsible

for the implementation of their safety plan or program. This individual must have

authority to direct job site superintendents, foremen, and workers to comply with safety

directives and monitor the corrective responses until satisfactory completion. This

Subcontractor shall make available all history of accidents, workers compensation rates,

etc. as may be required in a timely manner.

Yes

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility of

Subcontractor.

Yes

Page 65: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence and

dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work including

any field measurements. It shall also be the responsibility of the Subcontractor to

maintain and preserve all stakes and other control established by Contractor or Owner.

If control or stakes are destroyed by Subcontractor, they will be replaced at their

expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is the

responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The primary

responsibility for safety resides with each subcontractor for its workers. Subcontractors

and their employees (workers) will be responsible for their health and safety

performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control, and

temporary partitions to protect all work adjacent or susceptible to damage by this scope

of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the primary

project boundaries as a part of your work is included in each subcontract unless

specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for review

at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to coordinate

all jobsite shipments with S&P Superintendent. All material will be palletized or bundled.

Any flagman as may be required for these deliveries is the responsibility of this

Subcontractor. In the event material is delivered to the job and the Subcontractor's

personnel are not available, the Contractor shall unload and charge for the costs of

unloading and storing unless agreed to in advance. However, The Contractor will not be

responsible for any loss or damage from any cause whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the preparation

of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by Owner,

due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

31 General Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract occurs.

Yes

Page 66: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

32 General

For this trade performing new and/or remodeling work on the premises of this project,

all required certificates and validations for each employee performing work are required

to be submitted as required by the Federal Environmental Protection Agency’s (EPA)

Renovation, Repair, and Painting Rule.  This trade is required to provide all required

certifications necessary outlined by the EPA and submit to the general contractor prior to

commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing the

following Building Information Modeling requirements: Where the contract documents

refer to shop drawings and coordination drawings, these documents are to be provided

in Revit Software or AutoCAD 3D. Attendance of coordination meetings as directed by

S&P. Provide all required documents and data necessary for the implementation and

completion of the closeout process, including the tagging of the components being

modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced twice

a week for duration of their on site time.Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 67: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to be

used to employ a worker that will be responsible for safety item maintenance, trash

removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each contractor

shall carry an amount for each day worked on the project to cover the cost of removal of

trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and Environmental

Assessment Information.Yes

76 GeneralAll Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of the

models provided by the subcontractors and designers. This includes coordination of all

trades, their models and the sharing of such models; conflict management and resolution

with the design consultants and subcontractors; integration and oversight of total model

completion, maintenance and closeout. This cost is to be included in the amount of 1%

of the total proposal amount.

Yes

78 GeneralThis Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs for

compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the fast

track nature of this project, Construction Documents may not be 100 Percent complete

and will develop as the project progresses. However the subcontractor shall perform all

work required or reasonably inferred under the best practices in the construction

industry for a complete, fully functional and operational system for the purpose

intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided by

others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure obtaining

the certificate of Occupancy in an expeditious manner.Yes

82 07 4213 Metal Wall Panels Yes

83 07 9005 Joint Sealants Yes

84

Provide and install a Complete Turnkey METAL WALL PANEL SYSTEM, including but not

limited to flashings, accessories, sealants, clips, trim and barriers associated with all

project plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

85

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

86

Furnish and install all materials and accessories as necessary to provide complete wall

panel system.Yes

87 Coordinate installation with all trades as required. Yes

88

Provide all flashing as required to prevent moisture penetration around all

doors, windows, wall bottoms, material transitions and penetrations.Yes

89

Provide sealants, clips, trim, flashing per the contract documents, manufacturer's

requirements and local building codes.Yes

90 Provide all mockups, submittals, and samples as required. Yes

91 Provide all warranties and special warranties as required. Yes

Trade Specific Scope

Page 68: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92 Protect air barrier system, do not install if damaged. Yes

93 Metal Soffit Panels and required support framing. Yes

94 Metal Wall Panel and required support framing. Yes

95 Yes

96 Subtotal - Scope Revisions -$

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Subtotal - Alternates -$

106 Yes

107 Yes

108 Yes

109 Subtotal - Value Engineering -$

110 Yes

111 Yes

112 Yes113 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 69: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 7E - EXPANSION JOINT ASSEMBLIES Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 70: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 71: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 72: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 07 9005 Joint Sealers Yes

83 07 9513 Expansion Joint Cover Assemblies

84

Provide a Complete Turnkey Scope of Work for EXPANSION JOINT COVER

ASSEMBLIES per all project plans, specifications, addendum, value engineering and

all uniform general & supplementary conditions.

Yes

Trade Specific Scope

Page 73: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

85

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

86

Furnish and install all materials and accessories as necessary to provide complete

Expansion Joint Cover Assembly packageYes

87 Coordinate installation with all trades as required. Yes

88

Provide Shop Drawings for all vertical and horizontal expansion air seal joints per plans

and specifications.Yes

89 Yes

90 Subtotal - Scope Revisions -$

91 Yes

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Subtotal - Alternates -$

100 Yes

101 Yes

102 Yes

103 Subtotal - Value Engineering -$

104 Yes

105 Yes

106 Yes107 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 74: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 7F - FIRESTOPPING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 75: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 76: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 77: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 07 8400 Firestopping Yes

83 Yes

84

Provide and install a Complete Turnkey Scope of Work for FIRESTOPPING per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

Trade Specific Scope

Page 78: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

85

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

86 Provide a complete turnkey firestopping scope of work including coordination of all

contract documents, field conditions, and impediments to ensure a complete

installation of the work of this subcontract in accordance with the Contract

Documents. Including but not limited to penetrations by mechanical, electrical and

pluming penetrations, safing and top of wall conditions and elevated floor to exterior

wall conditions.

Yes

86

Provide all required products, accessory products, design, calculations, finishes,

thicknesses, delivery, colors, finishes, thickness, material requirements, storage and

handling, product systems, quality assurance, safety, preparation, examination and

inspection, and application installation requirements in accordance with the contract

documents.

Yes

87

Provide all submittals and closeouts including, but not limited to: product data,

samples, schedules, certifications, manufacturer's installation instructions, test

reports, and warranties.

Yes

88 Minor preparation and cleaning of surfaces prior to installation of firestopping as

applies to scope of work.Yes

89 Verify that all materials are clean of debris prior to commencement of work Yes

90 Yes

91 Yes

92 Subtotal - Scope Revisions -$

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Subtotal - Alternates -$

102 Yes

103 Yes

104 Yes

105 Subtotal - Value Engineering -$

106 Yes

107 Yes

108 Yes109 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 79: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 8A - DOORS, FRAMES & HARDWARE Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 80: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 81: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 82: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 08 1113 Hollow Metal Doors and Frames Yes

83 08 1416 Flush Wood Doors Yes

84 08 3473 Sound Control Door Assemblies Yes

85 08 7100 Door Hardware Yes

86 08 3100 Access Doors & Frames Yes

87 Yes

88

Furnish all DOORS, FRAMES AND FINISH HARDWARE per all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

90

This subcontractor to comply and coordinate with related work including but not

limited to Masonry, Metal framing, Metal Fabrications, glazed systems, painting and

staining.

Yes

Trade Specific Scope

Page 83: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

91

Furnish all material, related to installation of all Hollow Metal Doors, Wood Doors,

Hardware, and Frames as per plans and specs or as per manufacturer's instructions

where applicable.

Yes

92

All doors and frames should be provided as per required fire protection ratings, sound

rating, color, gauge etc. Tagged as required.Yes

93 All hollow metal window frames per the contract drawings. Yes

94

Furnish all material related to all Laminate faced wood Doors as per plans and specs or

as per manufacturer's instructions where applicable. Tagged as required. Yes

95

All doors should be provided as per required fire protection ratings, sound rating,

color, gauge etc. Tagged as required.Yes

96

Coordination and delivery of the permanent cores per the contract documents.Yes

97 Furnish hardware for aluminum and glass doors provided by others. Yes

98

Coordination of hardware with aluminum and glass doors provided by others.Yes

99 Glazing stops provided for all doors and frames. Yes

100 Coordination of floor finishes with doors and frames. Yes

101 Furnish storage for all doors and hardware. Yes

102 Coordination with the security, fire alarm and electrical subcontractor. Yes

103 Provide all access doors and frames. Yes

104

Prep existing doors and frames as required to receive new hardware, patch any holes

resulting from prep and/or removal.Yes

105 Survey the existing doors prior to prep of doors for new hardware. Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Subtotal - Scope Revisions -$

111 Yes

112 Yes

113 Yes

114 Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Subtotal - Alternates -$

120 Yes

121 Yes

122 Yes

123 Subtotal - Value Engineering -$

124

Installation of doors, frames and finish hardware. See work package 8B for

installation.Yes

125 Yes

126 Yes127 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 84: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 8B - Doors & Hardware Installation Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 85: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 86: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 87: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 08 1113 Hollow Metal Doors and Frames Yes

83 08 1416 Flush Wood Doors Yes

84 08 3473 Sound Control Door Assemblies Yes

85 08 7100 Door Hardware Yes

86 Yes

87 Yes

88

Installation of all DOORS AND FINISH HARDWARE per all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

90

This subcontractor to comply and coordinate with related work including but not

limited to Masonry, Metal framing, Metal Fabrications, glazed systems, painting and

staining.

Yes

Trade Specific Scope

Page 88: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

91

Installation of all Hollow Metal Doors, Wood Doors and Hardware as per plans and

specs or as per manufacturer's instructions where applicable.Yes

92 Unload, inventory and place door and finish hardware materials. Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Subtotal - Scope Revisions -$

111 Yes

112 Yes

113 Yes

114 Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Subtotal - Alternates -$

120 Yes

121 Yes

122 Yes

123 Subtotal - Value Engineering -$

124Yes

125 Yes

126 Yes127 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 89: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 8C - GLAZING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 90: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 91: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 92: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 07 8400 Fire stopping Yes

83 07 9005 Joint Sealants Yes

84 08 4313 Aluminum Framed Storefronts Yes

85 08 5659 Service & Teller Window Units Yes

86 08 7100 Door Hardware Yes

87 08 8000 Glazing Yes

88 Yes

89 Yes

90 Yes

91

Provide and install a Complete GLAZING SYSTEM, included but not limited to

exterior and interior storefronts, exterior curtainwalls, clerestory windows,

hardware, frames, unframed mirrors, anchors, fasteners, flashings, sealants and

caulking associated with all project plans, specifications, addendum, value

engineering and all uniform general & supplementary conditions.

Yes

Trade Specific Scope

Page 93: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

92

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.Yes

93 Provide interior and exterior storefronts per the contract drawings. Yes

94 Provide all exterior and interior glazing per the contract drawings. Yes

95 Provide unframed mirrors per the contract documents. Yes

96 Provide all flashing per the contract drawings. Yes

97

Clip angles, support angles, inserts, aluminum break panels, anchors, shims,

connectors, overhead support steel, bent metal and/or break metal including sills,

snap in sealant stops, closures, trim, and drips required for a complete installation of

your work. All exposed components to match finish of curtain wall system as selected

by the Architect and Owner.

Yes

98

Provide engineered anchors and fasteners for connections at slab on grade and

precast architectural concrete panels.Yes

99

Coordination of all electrical and low voltage that is installed in curtainwalls and

storefronts.Yes

100

Internal and perimeter joint sealants, joint fillers, weeps, vents and gasketing systems

for your work.Yes

101 Sealants at the dry line of the window and cosmetic sealant as required. Yes

102

Provide joint sealants within glazed aluminum curtain wall system and where

materials provided by this Subcontractor abut a dissimilar material.Yes

103 Cap flashing, caulking, and sealants for your work. Yes

104

Miscellaneous interior glazing for hollow metal doors, wood doors, sidelites,

borrowed lites, mirrored glass, etc. including installation of glazing stops.

Yes

105

Swinging, balanced entrance doors and framing, sub frames, stripping and thresholds.

Coordinate installation of electric locks with the electrical, security and fire alarm

subcontractor.

Yes

106 Guarantees, warranties, and tests as required by the Contract Documents. Yes

107 Miscellaneous steel support as required for your frames. Yes

108 Interior sills, closure pieces and wall end caps to match frames as required. Yes

109

Provide temporary closure of openings from the time the frame installation begins

until glass is installed and caulkedYes

110 Provide and install all door hardware for this scope of work Yes

111 Removal of excess sealants and stickers. Yes

112 Final cleaning for this scope of work one week before punchlist development Yes

113

Installation Of 2" 4-1/2" Exterior Storefront With A Class I Clear Anodized Finish. -

Elevations: SF-A (20)Yes

114

Glazing Of Hollow Metal Window Frames & Door Vision Lites w/Glass Specified on

Elevations Pager A3.1Yes

115

Exterior Glazing of installed storefront system to be with Glass Specified on Elevations

Page A3.1Yes

116

Perimeter Caulking Sealing Of Storefront Framing System with two (2) beads of

sealant.Yes

117 Break Metal Sill Flashing underneath exterior storefront system. Yes

118 Engineering. Calculations, Shop Drawings, Samples & Submittals. Yes

119

Should any part of the system framing or glazing not be available for installation per

the CM's scheduled, subcontractor to provide temporary enclosure that provides a

weathertight system until permanent system is available.

Yes

120 Subtotal - Scope Revisions -$

121 Yes

122 Yes

123 Yes

124 Yes

125 Yes

126 Yes

127 Yes

128 Yes

129 Subtotal - Alternates -$

130 Yes

131 Yes

132 Yes

Project Alternates

Project Value Engineering

Page 94: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

133 Subtotal - Value Engineering -$

134 Yes

135 Yes

136 Yes137 Yes

The following items are specifically EXCLUDED:

Page 95: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 8D - SKYLIGHTS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 96: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 97: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 98: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 08 6300 Metal Framed Skylights Yes

83 Yes

84 Yes

85 Yes

86 Yes

87 Yes

88

Provide and install a Complete Turnkey Scope of Work for SKYLIGHTS per all project

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

90

Subcontractor is responsible for submitting and furnishing skylights and components

out of the materials and finishes noted in the contract documents.

Trade Specific Scope

Page 99: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

91

Subcontractor is responsible for providing skylight assemblies, with closure system;

structure; flashing; fasteners and accessories as required for a complete system.

92 Provide temporary enclosures as required to protect the interior of the school.

93 Provide blocking as indicated for complete installation per the contract documents.

94 Provide flashing per the contract documents.

95

Subcontractor is responsible for structural framing and support as indicated on the

drawings and required by the system manufacturer.

96

Subcontractor is responsible for demo of existing skylights and replacing as shown on

the contract documents.

97

Subcontractor is responsible for demo of roof where new skylights are to be installed

per the contract documents.

98 Protection of roof along pathway to and around skylights

99 Protection of all surrounding work.

100

101

102

103

104

105 Subtotal - Scope Revisions -$

106 Yes

107 Yes

108 Yes

109 Yes

110 Yes

111 Yes

112 Yes

113 Yes

114 Subtotal - Alternates -$

115 Yes

116 Yes

117 Yes

118 Subtotal - Value Engineering -$

119 Yes

120 Yes

121 Yes122 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 100: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 9A - DRYWALL Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 101: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 102: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 103: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 05 4000 Cold-Formed Steel Framing Yes

83 07 2100 Thermal Insulation Yes

84 07 8400 Firestopping Yes

85 07 9005 Joint Sealants Yes

86 09 2813 Cementitious Backing Board Yes

84 09 2982 Gypsum Board Yes

85 Yes

Trade Specific Scope

Page 104: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

86 Yes

87 Yes

88

Provide a Complete DRYWALL SYSTEM, including but not limited to exterior

sheathing, gypsum ceilings, gypsum soffits/furr downs, hat channels, supports,

matching of existing walls, clips, anchors, accessories, light gauge stud framing,

insulation, miscellaneous accessories, firestopping, weatherproofing, barriers,

sealants, caulking and fire rated items associated with all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

90 Provide Exterior Sheathing per the contract documents. Yes

91 Provide Gypsum Ceilings per the contract documents. Yes

92 Provide Gyp Soffit/Furr-Down @ all Upper Cabinets per the contract documents. Yes

93 Provide Furr-Down for Gyp Soffit per detail (12/A-121J). Yes

94 Provide Operable Partition Support (30/A-121J) per the contract documents. Yes

95 Provide Thick L2 Masonry Wall per the contract documents. Yes

96 SW4B - Gyp over Hat-Channel Yes

97 Patch to Match walls as required and per the contract documents. Yes

98 All cold formed metal stud framing as shown. Engineering as required. Yes

99 All light gauge stud faming, gypsum board and accessories. Yes

100 Complete insulation at all framed walls. Yes

101

All interior metal backing plates at all wall and ceiling hung accessories and

equipment. Provide and install plywood sheathing in MDF and IDF rooms.Yes

102

Store materials inside under cover and dry, and protect against damage from

weather, direct sunlight, etc.Yes

103 Neatly stack gypsum boards flat to prevent sagging. Yes

104 Firestopping at walls built under this scope of work. Yes

105 All caulking to seal walls. Yes

106 Furnish and installation of all drywall trim (Corner Beads, etc.) Yes

107 STC required ratings Yes

108 Rated Assemblies as detailed for columns and walls Yes

109 Fire rated sheetrock as required Yes

110 Framed opening in the MEP as required. Yes

111 Fire Rated Sealant Joint as required. Yes

112

Control joints and expansion joint covers - Coordinate expansion and control joints

with the joints in the building and/or ArchitectYes

113 Furr downs as required Yes

114 Gypsum Board Ceilings and grid systems where required. Yes

115 Moisture resistant boards as required Yes

116 Tape and float to specified level Yes

117 All scaffolding, lifts and lifting equipment as required Yes

118 Drywall related to the MEP trades. Yes

119 Drywall related to the Food Service trade. Yes

120

Studs at all framed openings. Coordinate with other trades where additional

miscellaneous steel bracing is required.Yes

121 Frame for access panels and sleeves as required Yes

122 AGB Sound Absorptive Gypsum Panel as required. Yes

123 Install Door Frames (Provided By others) at all Drywall Partitions. Yes

124 Sound Batt Insulation At Interior Drywall Partitions Yes

125 Tile Backer Board Yes

126 Backer Board On Wall Talker Areas for Moisture Protection Yes

127 Caulking at perimeter of openings within your system. Yes

128 Insulation in exterior walls. Yes

129 Install doors in frames within your walls. Yes

130 Yes

131 Subtotal - Scope Revisions -$

132 Yes

133 Yes

134 Yes

135 Yes

Project Alternates

Page 105: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

136 Yes

137 Yes

138 Yes

139 Yes

140 Subtotal - Alternates -$

141 Yes

142 Yes

143 Yes

144 Subtotal - Value Engineering -$

145 Furnishing of doors and frames. Yes

146 Yes

147 Yes148 Yes

Project Value Engineering

The following items are specifically EXCLUDED:

Page 106: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 9B - PLASTER Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 107: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 108: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 109: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 09 22 26 Suspension Systems Yes

09 22 36.23 Metal Lath Yes

09 24 00 Cement Plaster Yes

83 Yes

84 Yes

Trade Specific Scope

Page 110: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

85

Provide a Complete PLASTER SYSTEM, including but not limited to adhesive,

fasteners, board insulation, flashing, metal lath, channels, hangers, expansion

joints, wire, screeds, reinforcing fabrics, control joints, base and finish-coat systems

perforated trim, weeps, and accessories associated with all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

86

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

87 Provide drainage Barrier System Yes

88

Provide materials and plaster components standard with the manufacturer for the

product system.Yes

89 Provide tapes, sealers, and primers Yes

90 Provide drainage strips and materials Yes

91 Provide and install weather barrier as required Yes

92 Blocking and/or supplemental framing as required Yes

93 Joint sealant at plaster, and at dissimilar materials. Yes

94 Provide colors and textures as indicated or match existing Yes

95 Provide flashing at dissimilar materials Yes

96 Patch all interior/exterior plaster as required Yes

97 Patch/Touch up at all replaced soffit lights. Yes

98 Provide plaster soffit per the contract documents. Yes

99 Patch/Touch up plaster ceiling at structural column repairs Yes

100

Prepare demo edge to a neat clean edge to receive new plaster. Repair any framing

and supports damaged during demolition.Yes

101 Provide protection of surrounding existing elements to remain. Yes

102 New Addition: Exterior Plaster Soffits At Addition Soffits, Parapets, Etc.… Yes

103 Clean up and dispose of all debris Yes

104 Yes

105 Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Subtotal - Scope Revisions -$

111 Yes

112 Yes

113 Yes

114 Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Subtotal - Alternates -$

120 Yes

121 Yes

122 Yes

123 Subtotal - Value Engineering -$

124 Yes

125 Yes

126 Yes127 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 111: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 9C - ACOUSTICAL Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 112: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 113: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 114: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 09 2226 Suspension Systems Yes

83 09 5100 Acoustical Ceiling Panels Yes

84 09 8400 Acoustical Panels Yes

85 Yes

86

Provide a Complete Turnkey ACOUSTICAL SYSTEM, including but not limited to

acoustical panel ceilings complete, including reveals, trim, angles, T’s, molds,

hangar wire, tie wire, fasteners, insulation, hold down clips associated with all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

87

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

88 New wall molding to be attached 1/4" below existing to hide paint line Yes

89 Acoustical grid and ceiling panels Yes

90 Composite Wood Panel ceiling Yes

Trade Specific Scope

Page 115: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

91 Vinyl Faced ceiling Yes

92 Sound Absorptive Panels Yes

93

Remove and replace existing ceilings as required for installation of new steel supports.

Work to be done in a manner that keeps existing lighting, diffusers, fire alarm, audio

visual, etc. in operating condition

Yes

94 Lay - In Ceiling Metal Edge Trim Yes

95 Patch to Match Yes

96

Provide additional support wires at all new ceiling mounted grilles, registers and light

fixtures.Yes

97 Yes

98 Subtotal - Scope Revisions -$

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Yes

106 Yes

107 Subtotal - Alternates -$

108 Yes

109 Yes

110 Yes

111 Subtotal - Value Engineering -$

112 Yes

113 Yes

114 Yes115 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 116: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 9D - TILE Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 117: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 118: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 119: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 09 3000 Tiling Yes

83 Yes

Trade Specific Scope

Page 120: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

84

Provide Complete TILING SYSTEM, including but not limited to divider strips, control

joints, transitions, border strips, curing compound, cleaner, sealer, under bed,

isolation membrane, floor prep, anchoring devices and moisture testing associated

with all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

85

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

86

This Subcontractor is responsible for providing all labor, materials, tools, equipment,

and incidentals required and/or necessary to provide a complete, fully functional,

aesthetically pleasing, and compliant Tiling scope in accordance with the Contract

Documents.

Yes

87 Tile Base Yes

88 Thresholds Yes

89 Waterproofing Yes

90 Drain Slope Yes

91 Reno TK SS Yes

92 Quadec SS Yes

93 BSS Dilex HKS SS Yes

94 Dilex HKS Connector Yes

95 Dilex HKS Corners Yes

96 Dilex HKS End Cap Yes

97 Schienne SS Yes

98 Schluter SS Yes

99 Cleaning / Miscellaneous Yes

100 Caulking Yes

101 Schluter EHK SS Yes

102 Yes

103 Subtotal - Scope Revisions -$

104 Yes

105 Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Yes

111 Yes

112 Subtotal - Alternates -$

113 Yes

114 Yes

115 Yes

116 Subtotal - Value Engineering -$

117 Yes

118 Yes

119 Yes120 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 121: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Spring Woods HS Base -$

Scope Revision -$

Bid Package Scope 9E - RESILIENT & CARPETING FLOORING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 122: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 123: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 124: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 09 6500 Resilient Flooring Yes

83 09 6813 Tile Carpeting Yes

84 Yes

Trade Specific Scope

Page 125: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

85

Provide Complete RESILIENT & CARPET FLOORING SYSTEM, including but not

limited to resilient goods, carpet, shims, tack strips, attic stock, moisture protection,

substrate, warranties, submittals and all accessories associated with project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

86

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

87

Extra materials as required and shall be from same production run of material ordered

for installation. Yes

88 Moisture testing of concrete floors prior to installation. Yes

89 Inventory, storage, transportation and unloading of all materials to be installedYes

90 Mobilizations as required to complete this scope of work Yes

91

Samples of each type of Seam Tape, Edge Molding, and any other Accessories to

complete this scope of workYes

92

Preparation of floors in order for substrate to be at an acceptable condition to apply

floor finish, includes necessary floor preparation.Yes

93

Base at walls, columns, pilasters, casework, and other permanent fixtures in rooms or

areas where base is required.Yes

94

Subcontractor is to provide layout of LVT and Carpeting as specified in the contract

documents.Yes

95 Seaming drawings for carpet Yes

96 Transition strips at dissimilar flooring Yes

97 This Subcontractor will protect other trades work during installation of its workYes

98 Samples and mockups as required Yes

99 VCT01 - Vinyl Composition Tile Yes

100 LVT01 - Vinyl Tile (18" x 18") Yes

101 BR01 - Rubber Base Yes

102 BA - Aluminum Base Yes

103 Transition Strip EQ to Burke - Mercer Model #150 Tile/ Carpet Joiner Yes

104 CT01 to CT06 - Tile Carpeting (24" x 24") Yes

105 WT - Entrance Walk - Off Tile Carpeting Yes

106 Aluminum Transition Strip - Tile to Carpet Yes

107 Transition Strip EQ to Johnsonite SLT-XX-L - Carpet to Concrete Yes

108 Reducer Yes

109 High moisture type adhesive for all resilient flooring goods. Yes

110 Yes

111 Yes

112 Yes

113 Subtotal - Scope Revisions -$

114 Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Yes

120 Yes

121 Yes

122 Subtotal - Alternates -$

123 Yes

124 Yes

125 Yes

126 Subtotal - Value Engineering -$

127 Yes

128 Yes

129 Yes130 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 126: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 9I - PAINTING & VWC Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 127: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 128: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 129: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 07 9005 Joint Sealants Yes

83 09 7200 Wall Coverings Yes

84 09 7213 Markable Wall Surfacing Yes

85 09 9000 Painting & Coatings Yes

86 Yes

87 Yes

Trade Specific Scope

Page 130: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

88

Provide Complete PAINTING & WALL COVERING SYSTEM, including but not limited

to tape, bedding, tools, equipment, mock-ups, warranty, interior and exterior paint

and wall covering, prep work, epoxy coatings, chalkboard paint, tackable wall fabric

and all accessories associated with project plans, specifications, addendum, value

engineering and all uniform general & supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

90

This Subcontractor is responsible for providing all labor, materials, tools, equipment,

and incidentals required and/or necessary to provide a complete, fully functional,

aesthetically pleasing, and compliant Painting scope in accordance with the Contract

Documents.

Yes

91

This subcontractor responsible for providing the following complete per the contract

documents but not limited to: mock-up, warranty, interior painting, exterior painting,

prep work, epoxy coatings, etc.. for a complete scope.

Yes

92

Provide painting as required per contract documents at all previously painted areas as

described in the painting specification section. Yes

93 Provide all interior wall painter's caulking at painted and dissimilar materials.Yes

94 Provide chalkboard paint per the contract documents. Yes

95 Provide tackable wall fabric per the contract documents. Yes

96

This Subcontractor shall be responsible for touch-up of all wall surfaces prior to

Substantial Completion of the project and an additional touch-up of all wall surfaces

prior to punch list sign-off and Final Completion in accordance with the Contract

Documents.

Yes

97 Patch to Match Yes

98 Painting Of Fencing Yes

99 Painting Of Building Soffit For Roof Repair Yes

100

Display Case Staining At Existing Display Case Around the Library Area Along With

Tackable SurfacesYes

101 Yes

102 Yes

103 Subtotal - Scope Revisions -$

104 Yes

105 Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Yes

111 Yes

112 Subtotal - Alternates -$

113 Yes

114 Yes

115 Yes

116 Subtotal - Value Engineering -$

117 Yes

118 Yes

119 Yes120 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 131: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10A - Visual Display Boards Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 132: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 133: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 134: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 09 7800 Custom Digital Wall Covering Yes

85 10 1101 Visual Display Boards Yes

86 Yes

Trade Specific Scope

Page 135: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for VISUAL DISPLAY BOARDS

per all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

88

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

89

Provide markerboards, tackboards, tackstrips, display rails and all required accessories

for installation per the contract documentsYes

90 Yes

91 Yes

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Subtotal - Scope Revisions -$

103 Yes

104 Yes

105 Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Yes

111 Subtotal - Alternates -$

112 Yes

113 Yes

114 Yes

115 Subtotal - Value Engineering -$

116 Yes

117 Yes

118 Yes

119 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 136: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10B - Signage Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 137: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 138: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 139: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 1400 Signage Yes

85 Yes

Trade Specific Scope

Page 140: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

86

Provide and install a Complete Turnkey Scope of Work for SIGNAGE per all project

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

87 Provide Signage, Plaques & Site Parking Signage Yes

88

Provide coring of concrete and installation of foundation footings for ground mounted

signage.Yes

89 Yes

90 Yes

91 Yes

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Subtotal - Scope Revisions -$

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Yes

106 Yes

107 Subtotal - Alternates -$

108 Yes

109 Yes

110 Yes

111 Subtotal - Value Engineering -$

112 Yes

113 Yes

114 Yes

115 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 141: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10C - Toilet Compartments & Toilet Accessories Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 142: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 143: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 144: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 2113.19 Plastic Toilet Compartments Yes

85

Trade Specific Scope

Page 145: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

86

Provide and install a Complete Turnkey Scope of Work for PLASTIC TOILET

COMPARTMENTS and TOILET & BATH ACCESSORIES per all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

87

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

87 Provide Plastic Toilet Compartments Yes

88

Provide Toilet, Bath & Laundry Accessories and all necessary accessories for a

complete installation per the contract documents.Yes

88

89

90 Yes

91 Subtotal - Scope Revisions -$

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Subtotal - Alternates -$

101 Yes

102 Yes

103 Yes

104 Subtotal - Value Engineering -$

105 Yes

106 Yes

107 Yes

108 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 146: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10D - Folding Panel Partitions Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 147: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 148: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 149: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 2239 Folding Panel Partitions Yes

85

Trade Specific Scope

Page 150: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

86

Provide and install a Complete Turnkey Scope of Work for FOLDING PANEL

PARTITIONS per all project plans, specifications, addendum, value engineering and

all uniform general & supplementary conditions.

Yes

87

Provide operable folding partition with required accessories for a complete

installation per the contract documentsYes

88 Provide necessary support columns at jambs if required for support. Yes

89 Yes

90 Yes

91 Yes

92 Subtotal - Scope Revisions -$

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Subtotal - Alternates -$

102 Yes

103 Yes

104 Yes

105 Subtotal - Value Engineering -$

106 Yes

107 Yes

108 Yes

109 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 151: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10E - Wall & Corner Guards Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 152: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 153: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 154: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 2601 Wall & Corner Guards Yes

85

Trade Specific Scope

Page 155: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

86

Provide and install a Complete Turnkey Scope of Work for WALL & CORNER

GUARDS per all project plans, specifications, addendum, value engineering and all

uniform general & supplementary conditions.

Yes

87 Provide metal corner guards and required accessories per the contract documentsYes

88 Yes

89 Yes

90 Subtotal - Scope Revisions -$

91 Yes

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Subtotal - Alternates -$

100 Yes

101 Yes

102 Yes

103 Subtotal - Value Engineering -$

104 Yes

105 Yes

106 Yes

107 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 156: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10F - Fire Protection Specialties Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 157: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 158: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 159: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 4400 Fire Protection Specialties Yes

85

86

Trade Specific Scope

Page 160: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for FIRE PROTECTION per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

88

Provide Fire extinguishers, extinguisher brackets and all necessary accessories for a

complete installation per the contract documents.Yes

89 Yes

90 Yes

91 Yes

92 Subtotal - Scope Revisions -$

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Subtotal - Alternates -$

102 Yes

103 Yes

104 Yes

105 Subtotal - Value Engineering -$

106 Yes

107 Yes

108 Yes

109 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 161: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10G - Metal Storage Shelving Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 162: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 163: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 164: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 5613 Metal Storage Shelving Yes

85

Provide and install a Complete Turnkey Scope of Work for METAL STORAGE

SHELVING per all project plans, specifications, addendum, value engineering and all

uniform general & supplementary conditions.

Yes

Trade Specific Scope

Page 165: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

86

Provide Four post metal storage shelving and accessories necessary for a complete

installation per the contract documents.Yes

87 Yes

88 Yes

89 Yes

90 Yes

91 Subtotal - Scope Revisions -$

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Subtotal - Alternates -$

101 Yes

102 Yes

103 Yes

104 Subtotal - Value Engineering -$

105 Yes

106 Yes

107 Yes

108 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 166: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10H - Protective Covers Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 167: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 168: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 169: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 10 7300 Protective Covers

85 Yes

86 Yes

Trade Specific Scope

Page 170: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for PROTECTIVE COVERS per

all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

88

Provide Protective Covers and all necessary accessories for a complete installation per

the contract documentsYes

89 Provide all miscellaneous in-wall support brackets, steel and mounting accessories. Yes

90 Subtotal - Scope Revisions -$

91 Yes

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Subtotal - Alternates -$

100 Yes

101 Yes

102 Yes

103 Subtotal - Value Engineering -$

104 Yes

105 Yes

106 Yes

107 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 171: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 10I - Digital Wall Covers Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 172: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 173: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 174: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 09 7800 Custom Digital Wall Covering Yes

85

86

Trade Specific Scope

Page 175: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for DIGITAL WALL COVERING

per all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

88 Provide Graphic Digital Wall Coverings Yes

89 Yes

90 Subtotal - Scope Revisions -$

91 Yes

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Subtotal - Alternates -$

100 Yes

101 Yes

102 Yes

103 Subtotal - Value Engineering -$

104 Yes

105 Yes

106 Yes

107 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 176: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 11A - RESIDENTIAL APPLIANCES Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 177: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 178: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 179: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 07 9005 Joint Sealers Yes

84 11 3100 Residential Appliances Yes

85 Yes

86 Yes

Trade Specific Scope

Page 180: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for RESIDENTIAL

APPLIANCES per all project plans, specifications, addendum, value engineering and

all uniform general & supplementary conditions.

Yes

88

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

89 Provide Residential Appliances. Yes

90 Science Room Refrigerator Yes

91 Dishwasher Yes

92 Microwave Yes

93 Off-load and set in place for final connection by others. Yes

94 Subtotal - Scope Revisions -$

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Subtotal - Alternates -$

104 Yes

105 Yes

106 Yes

107 Subtotal - Value Engineering -$

108 Yes

109 Yes

110 Yes

111 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 181: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 12A - WINDOW TREATMENTS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 182: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 183: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 184: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 12 2100 Window Blinds Yes

84 12 2400 Window Shades Yes

85 Yes

86 Yes

Trade Specific Scope

Page 185: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for WINDOW TREATMENTS

per all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

88

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

89 Yes

90 Yes

91 Subtotal - Scope Revisions -$

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Subtotal - Alternates -$

101 Yes

102 Yes

103 Yes

104 Subtotal - Value Engineering -$

105 Yes

106 Yes

107 Yes

108 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 186: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 12B - CASEWORK Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 187: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 188: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 189: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 06 1000 Rough Carpentry Yes

83 06 4119 Manufactured Plastic - Laminate - Clad Casework Yes

84 06 6500 Solid Polymer Fabrications Yes

85 11 5300 Laboratory Equipment Yes

86

Provide and install a Complete Turnkey Scope of Work for CASEWORK per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

87

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

88 Provide all plastic laminate casework, solid polymer tops and laboratory equipment.Yes

88 Provide wood casings, moldings and trim. Yes

89 Provide all countertops, backsplashes, cabinet hardware and accessories. Yes

90 Provide window sills and stools. Yes

Trade Specific Scope

Page 190: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

90

Provide all service fixtures including but not limited to sinks, faucets, electrical items

and accessories for installation by others.Yes

91

Provide protective covering over cabinets at completion for protection from other

trades.Yes

92 Provide all epoxy resin tops at lab equipment as specified. Yes

92 Provide all wood grounds at wall mounted equipment. Yes

93 Provide flammable liquid storage cabinets, and drench shower tester.

94

94 Yes

95 Subtotal - Scope Revisions -$

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Subtotal - Alternates -$

105 Yes

106 Yes

107 Yes

108 Subtotal - Value Engineering -$

109 Yes

110 Yes

111 Yes

112 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 191: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 12D - FURNITURE Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 192: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 193: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 194: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 12 50 00 Furniture Yes

83 Yes

84 Yes

85 Yes

86 Yes

Trade Specific Scope

Page 195: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide and install a Complete Turnkey Scope of Work for FURNITURE per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

88

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

89

Provide Furniture for all areas of the project including furniture located within the new

addition and the existing building.Yes

89 Provide all unloading, assembly and setting furniture in it's final location. Yes

90 Yes

91 Yes

91 Subtotal - Scope Revisions -$

92 Yes

93 Yes

94 Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Yes

100 Subtotal - Alternates -$

101 Yes

102 Yes

103 Yes

104 Subtotal - Value Engineering -$

105 Yes

106 Yes

107 Yes

108 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 196: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 21A - FIRE SUPPRESSION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 197: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 198: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule. This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 199: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 21 1100 Wet-Pipe Fire Suppression Sprinklers Yes

83 Yes

84 Yes

85 Yes

86 Yes

Trade Specific Scope

Page 200: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

87

Provide a Complete Turnkey Scope of Work for FIRE SUPPRESSION SYSTEM

including but not limited to valve assemblies, knox box, working pressure, welding

certificates, escutcheons, heads, pendants, upright brass, sealants, fittings, piping

and accessories associated with all project plans, specifications, addendum, value

engineering and all uniform general & supplementary conditions.

Yes

88

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required

Yes

89

Fire Sprinkler subcontractor to immediately notify the Project Superintendent if

anything in the contract documents conflicts with applicable codes.

Yes

90 System to be isolated by floor with Floor Control Valve Assemblies. Yes

91 New Fire Department Connection including Knox Box. Yes

92 Required working pressure. Yes

93 Welding certificates for applicable pipefitters. Yes

94 Scope of work begins 1' AFF. Yes

95 Semi-Recessed Chrome escutcheons in finished areas. Yes

96 All heads and trim as specified. Yes

97

Provide system drains where required by contract documents and/or applicable

codes.Yes

98 Clean, test & flush system per the specifications and code Yes

99 Provide clay plugs around utilities before they go under the building footprint.Yes

100 Provide all signage, markings, and labeling required for this scope of work. Yes

101 Provide all sealants associated with this scope of work. Yes

102

Sprinkler heads are to be installed at the center of ceiling tiles, or as directed for

proper alignment.Yes

103 Coordination with the Fire Alarm System. Yes

104

In addition to the requirements of the contract documents, Subcontractor is required

to participate and lead in the final checkout of the Fire Suppression System to assure

Substantial Completion per the project schedule.

Yes

105 Provide all sleeves & firestopping as required. Yes

106 Coordinate with location of Kiln to prevent accidental system action. Yes

107

Protect all work from incidental damage upon completion (cover with cardboard,

etc.).Yes

108

Licenses, permits, tests, fees, inspections, and warranties required by the Contract

Documents and applicable codes.Yes

109

Provide all necessary engineering & deferred submittals (if required by local code

authority).Yes

110

Provide all necessary equipment and personnel to perform all tests & inspections

required.Yes

111

Subcontractor shall provide all information and documentation required for BIM

coordination and as-builts.Yes

112 Attic stock requirements Yes

113

Complete sets of special tools & equipment necessary to perform routine

maintenance on the sprinkler system.Yes

114 Access doors Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Subtotal - Scope Revisions -$

120 Yes

121 Yes

122 Yes

123 Yes

124 Yes

125 Yes

126 Yes

127 Yes

128 Subtotal - Alternates -$

Project Alternates

Page 201: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

129 Yes

130 Yes

131 Yes

132 Subtotal - Value Engineering -$

133 Site fire line. Yes

134 Yes

135 Yes

136 Yes

Project Value Engineering

The following items are specifically EXCLUDED:

Page 202: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 22A - PLUMBING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 203: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 204: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 205: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 22 0500 Common Work Results For Plumbing Yes

83 22 0516 Expansion Fittings & Loops For Plumbing Piping Yes

84 22 0529 Plumbing Hangers & Support Yes

85 22 0553 Identification For Plumbing Piping & Equipment Yes

86 22 1116 Domestic water Piping Yes

87 22 1316 Sanitary Waste Yes

88 22 1413 Storm Drainage Piping Yes

89 22 1426.13 Retrofit Roof Drain Backflow Mechanical Seal Yes

Trade Specific Scope

Page 206: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

90 22 3000 Plumbing Equipment Yes

91 22 4000 Plumbing Fixtures Yes

92 Yes

93 Yes

94

Provide a Complete PLUMBING SYSTEM included but not limited salvaged material,

fixtures, trim, gas system, domestic water, sanitary waste and vent system, storm

drainage system, equipment, supplies, finishes, demolition, concrete, sealants,

penetrations, layout drawings, submittals, sleeves and accessories associated with

all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

95

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

96

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

97 Protection of existing structures, finishes, and equipment that will remain in placeYes

98 Demolition and removal of all plumbing equipment as indicated. Yes

99 Cut and make safe all utilities Yes

100

Furnish all access doors as required by your work. Access doors in drywall to be

installed by others.Yes

101 Firestopping of all penetrations in fire rated assemblies resulting from your work.Yes

102 Seal all penetrations resulting from your work as required. Yes

103 Cutting of concrete and core drilling required to install your work. Yes

104

Will provide layout drawings for all housekeeping pads provided by others for your

scope of work.Yes

105 Furnish, layout, and install sleeves and blockouts for your work. Yes

106

This Subcontractor shall provide layout drawings of all framed openings through the

structure required for the work of this Subcontract.Yes

107 All supports, valves, hangers, connections and testing. Yes

108 Replace all ceiling tiles if removed to perform your scope of work. Yes

109 Patch any fireproofing removed by this Subcontractor. Yes

110

All roof mounted equipment shall be mounted on prefabricated curbs and/or

equipment rails furnished and installed by this Subcontractor. Subcontractor is

responsible for blocking required. All roof mounted piping and duct shall include the

appropriate supports, roof pads, and attachment devices for the duct and pipe they

support. Subcontractor is responsible for coordinating all openings for scope of work

Yes

111 Grouting of the equipment and equipment bases. Yes

112

Provide bedding, vaults and thrust anchors for underground piping as required and

per the contract documents.Yes

113

All notes, keynotes, and details on all contract documents related to this

subcontractors work are included within this agreement.Yes

114

Owner demonstration and training of all equipment and systems as designated by the

Contract Documents.Yes

115 All non formed concrete work associated with mechanical work. Yes

116

Equipment curbs, pitch pans, penetrating assemblies required on roof as applies to

the mechanical scope.Yes

117 Final connections to equipment supplied by others. Yes

118 Provide all gas systems and connections as shown on the contract documents.Yes

119

Provide valves on gas systems to allow system to be brought up per the phased

schedule.Yes

120 Provide trap primer and hose bib in all mechanical rooms per the contract documents.Yes

121

All new and existing sanitary 3'' or above shall be inspected by camera prior to

Substantial Completion.Yes

122 Guarantees, warranties, and tests as required by the Contract Documents. Yes

123 Yes

124 Yes

125 Yes

Page 207: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

126 Yes

127 Yes

128 Subtotal - Scope Revisions -$

129 Yes

130 Yes

131 Yes

132 Yes

133 Yes

134 Yes

135 Yes

136 Yes

137 Subtotal - Alternates -$

138 Yes139 Yes

140 Yes

141 Subtotal - Value Engineering -$

142 Yes

143 Yes

144 Yes145 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 208: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 23A - HVAC Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in

writing with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or

any other Specification Section, or shown on the plans. All notes, keynotes, and

details on all contract documents related to this subcontractors work are included

within this agreement. This subcontractor acknowledges all project specifications, all

project drawings, and all related contractual provisions. The items listed below are

not intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-

up hours (i.e. shift work, additional manpower, and/or acceleration). All premium

costs associated with the aforementioned are included in this Subcontract

Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for

their work, as required by any authorized agency or applicable code. Arrangements

for the inspection of any area, system, equipment, etc., needed testing or inspection

prior to being covered up must be made by the subcontractor in sufficient time to

allow for inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

Page 209: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will

be replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by

this scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-

built drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

31 General

Exploratory measures and associated costs required for determining the existence

and location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

Page 210: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 211: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for

each day that the subcontractor will be working on the project. This dedicated

amount is to be used to employ a worker that will be responsible for safety item

maintenance, trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor

shall perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 23 0500 Common Work Results For HVAC Yes

83 23 0513 Common Motor Requirements For HVAC Equipment Yes

84 23 0517 Sleeves & Sleeve Seals for HVAC Piping Yes

85 23 0518 Escutcheons For HVAC Piping Yes

86 23 0519 Meters & Gages For HVAC Piping Yes

87 23 0523 General Duty Valves For HVAC Piping Yes

88 23 0529 Hangers & Supports For HVAC Piping & Equipment Yes

89 23 0548 Vibration Controls For HVAC Yes

90 23 0553 Identification For HVAC Piping & Equipment Yes

91 23 0593 Testing Adjusting & Balancing For HVAC Yes

92 23 0713 Duct Insulation Yes

93 23 0716 HVAC Equipment Insulation Yes

94 23 0719 HVAC Piping Insulation Yes

95 23 0800 Commissioning Of HVAC Yes

96 23 0900 Instrumentation & Control For HVAC Yes

97 23 1123 Natural Gas Piping Yes

98 23 2113 Hydronic Piping Yes

99 23 2116 Hydronic Piping Specialties Yes

100 23 2123 Hydronic Pumps Yes

101 23 2300 Refrigerant Piping Yes

102 23 2513 Water Treatment For Closed Loop Hydronic Systems Yes

Trade Specific Scope

Page 212: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

103 23 2923 Variable Frequency Motor Drives Yes

104 23 3113 Metal Ducts Yes

105 23 3300 Air Duct Accessories Yes

106 23 3423 HVAC Power Ventilators Yes

107 23 3600 Air Terminal Units Yes

108 23 3713 Diffusers, Registers & Grilles Yes

109 23 5216 Condensing Boilers Yes

110 23 6423 Scroll Water Chillers Yes

111 23 7313 Modular Central-Station Air-Handling Units Yes

112 23 7433 Dedicated Outdoor Air Units Yes

113 23 8123 Computer-Room Air - Conditioners Yes

114 Yes

115 Yes

116 Yes

117 Yes

118 Yes

119 Yes

120 Yes

121

Provide and install a Complete Turnkey Scope of Work for HVAC SYSTEMS included

but not limited to, penetrations, chillers, boilers, supports, piping, insulation,

ductwork, AHU's, VAV's, Fans and Boxes, Hydronic Pumps, Relief Fans, louvers,

heaters, air separators and accessories associated with all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

122

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

123

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

124 Protection of existing structures, finishes, and equipment that will remain in placeYes

125 Curbs/Pitch Pans for roof penetrations & roof pipe supports. Yes

126 Provide Equipment as scheduled, including but not limited to: Yes

127 Air Cooled Chillers Yes

128 Air Handling Units Yes

129 Ductless Split-System Units Yes

130 Single Duct VAV's Yes

131 Hydronic Pumps Yes

132 Exhaust Fans Yes

133 Relief Fans Yes

134 Louvers, including bird screens Yes

135 Gravity Ventilators Yes

136 Heating Hot Water Boiler Yes

137 Electric Unit Heaters Yes

138 Air Separators Yes

139 Provide all starters integral & external. Yes

140 Provide crawlspace ventilation duct per the contract documents. Yes

141 All HVAC work in new building and renovated Family Services area. Yes

142 Preparation for and coordination & cooperation with SBISD's Test & Balance firm.Yes

143 CHS/R piping, insulation & jacketing as called for in the contract documents.Yes

144 Provide all sleeves & firestopping as required. Yes

145 Provide all signage, markings, and labeling required for this scope of work. Yes

146 Provide all sealants associated with this scope of work. Yes

147 Provide all sleeves and/or core drilling required for this scope of work. Yes

148 Provide all concrete cutting, sawing and removal as required by your scope of work.Yes

149 Access doors for scope of work. Yes

150 Duct lining where called for in the contract documents. Yes

151 Replace all ceiling tiles if removed to perform your scope of work. Yes

152 Provide flashing per the contract drawings as required for this scope of work.Yes

153 Blank off unused portions of louvers connected to your ductwork. Yes

154

All duct openings shall be kept sealed at all times during construction until the AHUs

are started up. Yes

Page 213: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

155 Provide all grouting of the equipment and equipment bases. Yes

156

Provide all bedding, vaults, and thrust anchors for underground piping as required

and per the contract documents.Yes

157 Provide final cleaning of all units. Yes

158 Provide all non formed concrete work associated with mechanical work. Yes

159 Provide all final connections to equipment supplied by others. Yes

160

In addition to the requirements of the Contract Documents, this Subcontractor will

participate and lead in the final checkout of all HVAC systems with S&P to assure

substantial completion of the mechanical systems.

Yes

161

Clean, flush, sterilize & sanitize systems as called for by the contract documents &

applicable codes.Yes

162 Provide all sleeves & firestopping as required. Yes

163 Provide clay plugs around utilities before they go under the building footprint.Yes

164

Protect all work from incidental damage upon completion (cover with cardboard,

etc.).Yes

165

Licenses, permits, tests, fees, inspections, and warranties required by the Contract

Documents and applicable codes.Yes

166

Provide all necessary engineering & deferred submittals (if required by local code

authority).Yes

167

Provide all necessary equipment and personnel to perform all tests & inspections

required.Yes

168 All coordination of the contract documents required to perform this scope of work. Yes

169

Provide all layout drawings of all framed openings through the structure required for

the work of this Subcontract.Yes

170

This Subcontractor is responsible for providing all coordination drawings, as required

by the Contract Documents.Yes

171

Subcontractor shall provide all information and documentation required for BIM

coordination and as-builts.Yes

172 Submittals are due within four (4) weeks after receipt of this agreement. Yes

173 Provide Owner Training as called for in the contract documents. Yes

174

Warranty per specifications on all equipment and systems provided in this scope of

work.Yes

175

All existing HVAC systems are to remain functional during normal school hours.

Critical work that requires the existing systems to be off line will be coordinated with

the superintendent and will have to take place during after hours, weekends and

holidays. If temporary HVAC is required to sustain normal operation conditions

during school hours, this trade is to include such within the proposal amount.

Yes

176 Yes

177 Yes

178 Yes

179 Yes

180 Yes

181 Subtotal - Scope Revisions -$

182 Yes

183 Yes

184 Yes

185 Yes

186 Yes

187 Yes

188 Yes

189 Yes

190 Subtotal - Alternates -$

191 Yes192 Yes193 Yes

194 Subtotal - Value Engineering -$

195 Yes

196 Yes

197 Yes198 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 214: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 25A - HVAC CONTROLS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 215: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 216: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 217: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 23 0500 Common Work Results For HVAC Yes

83 23 0513 Common Motor Requirements For HVAC Equipment Yes

84 23 0900 Instrumentation & Control For HVAC Yes

85 Yes

86 Yes

87 Yes

Trade Specific Scope

Page 218: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

88

Provide and install a Complete Turnkey Scope of Work for HVAC CONTROLS per all

project plans, specifications, addendum, value engineering and all uniform general

& supplementary conditions.

Yes

89

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

90

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

91 Protection of existing structures, finishes, and equipment that will remain in placeYes

92 Preparation for and coordination & cooperation with SBISD's Test & Balance firm.Yes

93

Direct Digital Controls furnished & installed by approved controls contractor, once

complete to be remotely accessed by SBISD's existing district-wide Energy

Management Control System.

Yes

94

Warranty per specifications on all equipment and systems provided in this scope of

work.Yes

95 Yes

96 Yes

97 Yes

98 Yes

99 Subtotal - Scope Revisions -$

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Yes

106 Yes

107 Yes

108 Subtotal - Alternates -$

109 Yes110 Yes

111 Yes

112 Subtotal - Value Engineering -$

113 Yes

114 Yes

115 Yes116 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 219: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Spring Woods HS Base -$

Scope Revision -$

Bid Package Scope 26A - ELECTRICAL & SYSTEMS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 220: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 221: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 222: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition - As Applies to your scope of work Yes

83 03 3000 Cast-In-Place Concrete - As applies to your scope of work Yes

84 07 2100 Thermal Insulation - As applies to your scope of work Yes

85 07 8400 Firestopping - As applies to your scope of work Yes

86 07 9005 Joint Sealants - As applies to your scope of work Yes

87 08 3100 Access Doors and Frames - As applies to your scope of work Yes

88 26 00 10 Electrical General Provisions Yes

Trade Specific Scope

Page 223: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

89 26 00 11 Submittals Yes

90 26 00 12 Operation & Maintenance Manuals Yes

91 26 00 30 Special Testing Yes

92 26 05 19 Low-Voltage Electrical Power Conductors & Cables Yes

93 26 05 26 Grounding & Bonding For Electrical Systems Yes

94 26 05 29 Hangers & Supports For Electrical Systems Yes

95 26 05 33 Raceways & Boxes For Electrical Systems Yes

96 26 05 53 Identification For Electrical Systems Yes

97 26 08 00 Commissioning Of Electrical Systems Yes

98 26 22 00 Low-Voltage Transformers Yes

99 26 24 16 Panelboards Yes

100 26 27 26 Wiring Devices Yes

101 26 28 16 Enclosed Switches & Circuit Breakers Yes

102 26 43 13 Surge Protection For Low-Voltage Electrical Power Circuits Yes

103 26 51 19 LED Interior Lighting Yes

104

105

106

Provide a Complete ELECTRICAL SYSTEM including but not limited to salvaged items

and materials, equipment, supplies, finishes, lighting, electrical gear, utilities,

penetrations, fire rated assemblies, sealants, fire stopping, concrete cutting and

patching, warranties, layout drawings, submittals and accessories associated with

all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

107

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

108

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

109 Protection of existing structures, finishes, and equipment that will remain in placeYes

110 Demolition and removal of all electrical systems per the contract documents.Yes

111 Cut and make safe all electrical systems. Yes

112

Furnish all access doors as required by your work. Access doors in drywall to be

installed by others.Yes

113 Cutting of concrete and core drilling required to install your work. Yes

114

Will provide layout drawings for all housekeeping pads provided by others for your

scope of work.Yes

115 Furnish, layout, and install sleeves and blockouts for your work. Yes

116 Trace and label all existing panels with correct circuit locations. Yes

117 Provide temporary power to the S&P trailer complex. Yes

118

Provide temporary power and lighting to the building, must be sufficient to keep all

operations on going.Yes

119

Provide underground electrical, trenching, backfilling, bedding and compaction per

the contract documents.Yes

120 All Div. 27 & 28 systems are to remain operational during construction. Yes

121 Replace existing exterior lights per drawings Yes

122

Provide all switch gear, MCC, panels, combo starters and disconnects per the contract

documents.Yes

123

Provide and install light poles, light fixtures and lighting controls per the contract

documents.Yes

124 Install lighting fixtures with the required wire hangers per the contract documents.Yes

125

Provide all power for mechanical equipment per the contract documents. Coordinate

with the mechanical subcontractor for power requirements.Yes

126

Provide all power for plumbing equipment per the contract documents. Coordinate

with the plumbing subcontractor for power requirements.Yes

127

All notes, keynotes, and details on all contract documents related to this

subcontractors work are included within this agreement.Yes

128

Provide conduit and cable tray per the contract documents and as needed for all

systems.Yes

129 Replace all burned out lamps prior to final acceptance by the owner. Yes

Page 224: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

130

Provide all power and disconnects for miscellaneous equipment as shown on the

contract documents, including but not limited to: marquee signs, laundry systems,

photo lab equipment, residential appliances, food service, shop equipment, theatrical

equipment, stage lighting, gym equipment, scoreboards, tennis equipment, soccer

equipment, baseball and softball equipment, folding partitions, shades, door

hardware etc.. Coordinate with subcontractors for power requirements.

Yes

131

Equipment curbs, pitch pans, roof pads, penetrating assemblies required on roof as

applies to this scope of work. Yes

132

Provide all access required for the installation of this work including but not limited to

removal and repair/replacement of doors, walls, ceilings, MEP systems, protection of

existing to remain, etc that is not indicated in the documents to be removed.

Yes

133 Provide cutting and patching of site work as required for this work Yes

134

All existing systems powered by electricity are to remain functional during normal

school hours. Critical work that requires the existing systems to be off line will be

coordinated with the superintendent and will have to take place during after hours,

weekends and holidays.

Yes

135 Yes

136 Yes

137 Yes

138 Yes

139 Yes

140 Yes

141 Subtotal - Scope Revisions -$

142 Yes

143 Yes

144 Yes

145 Yes

146 Yes

147 Yes

148 Yes

149 Yes

150 Subtotal - Alternates -$

151 Yes

152 Yes

153 Yes

154 Subtotal - Value Engineering -$

155 Yes

156 Yes

157 Yes158 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 225: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Spring Woods HS Base -$

Scope Revision -$

Bid Package Scope 27A - COMMUNICATIONS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 226: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 227: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 228: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition - As Applies to your scope of work Yes

83 27 00 00 Basic Materials & Methods Yes

84 27 02 01 Coordination Drawings Yes

85 27 03 00 Communications Demolition For Remodeling Yes

86 27 10 00 Category 6A Structure Cabling System (SCS) Yes

87 27 41 16 Integrated Audio Video Systems & Equipment Yes

88 27 51 23 Intercom Communications Systems Yes

Trade Specific Scope

Page 229: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

89

90

91

Provide a Complete COMMUNICATION SYSTEM per all project plans, specifications,

addendum, value engineering and all uniform general & supplementary conditions.

Yes

92

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

93

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

94 Protection of existing structures, finishes, and equipment that will remain in placeYes

95

Demolition and removal of all electrical, technology and special systems per the

contract documents.Yes

96 All Structured Cabling complete and in place where specified in the documents.Yes

97

All Communications scope shall be done by a Registered Communications Distribution

Designer.Yes

98

Includes all labeling, color coding, testing, certification, etc. of the system per the

contract documents.Yes

99 All fiber & copper backbone cabling between existing MDF & new IDF's. Yes

100 Build-Out of new IDF Rooms including overhead ladder tray, wall mounted cabinet, grounding, fire-treated plywood & all other item per the contract documents.Yes

101 Plenum-rated cable where called for and per code. Yes

102 Replace all ceiling tiles if removed to perform your scope of work. Yes

103 Provide all sleeves & firestopping as required. Yes

104

Protect all work from incidental damage upon completion (cover with cardboard,

etc.).Yes

105

Protect all work from incidental damage upon completion (cover with cardboard,

etc.).Yes

106

Licenses, permits, tests, fees, inspections, and warranties required by the Contract

Documents and applicable codes.Yes

107

Provide all necessary engineering & deferred submittals (if required by local code

authority).Yes

108

Provide all necessary equipment and personnel to perform all tests & inspections

required.Yes

109 All coordination of the contract documents required to perform this scope of work. Yes

110

This Subcontractor is responsible for providing all coordination drawings, as required

by the Contract Documents.Yes

111

Subcontractor shall provide all information and documentation required for BIM

coordination and as-builts.Yes

112 Submittals are due within four (4) weeks after receipt of this agreement. Yes

113 Provide Owner Training as called for in the contract documents. Yes

114

Pretest existing system to determine if system is fully functioning or not. Document

test results prior to beginning any work.Yes

115

All existing systems are to remain functional during normal school hours. Critical work

that requires the existing systems to be off line will be coordinated with the

superintendent and will have to take place during after hours, weekends and holidays.

Yes

116 Yes

117 Yes

118 Yes

119 Yes

120 Yes

121 Yes

122 Yes

123 Subtotal - Scope Revisions -$

124 Yes

125 Yes

126 Yes

127 Yes

128 Yes

Project Alternates

Page 230: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

129 Yes

130 Yes

131 Yes

132 Subtotal - Alternates -$

133 Yes

134 Yes

135 Yes

136 Subtotal - Value Engineering -$

137 Yes

138 Yes

139 Yes140 Yes

Project Value Engineering

The following items are specifically EXCLUDED:

Page 231: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Spring Woods HS Base -$

Scope Revision -$

Bid Package Scope 28A - SAFETY & SECURITY SYSTEMS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 232: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 233: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 234: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition - As Applies to your scope of work Yes

83 27 00 00 Basic Materials & Methods Yes

84 27 02 01 Coordination Drawings Yes

85 27 03 00 Communications Demolition For Remodeling Yes

86 27 10 00 Category 6A Structure Cabling System (SCS) Yes

87 27 41 16 Integrated Audio Video Systems & Equipment Yes

88 27 51 23 Intercom Communications Systems Yes

Trade Specific Scope

Page 235: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

89

90

91

Provide a Complete SAFETY & SECURITY SYSTEM per all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

92

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

93

Coordination with contractor for removal of all owner salvaged material, equipment,

and suppliesYes

94 Protection of existing structures, finishes, and equipment that will remain in placeYes

95

Demolition and removal of all electrical, technology and special systems per the

contract documents.Yes

96 Plenum-rated cable where called for and per code. Yes

97 Access Control System Yes

98 Access Control software to be used with District's existing centralized server.Yes

99

Provide the following items per the contract documents, including but not limited to

Access Control Software, control panels, card readers, signal extenders, device power

supplies, system cabling, cabling support, cable color coding & labeling.

Yes

100 Coordination with door hardware supplier & glazier. Yes

101 Access cards, blanks & security hierarchy per the contract documents. Yes

102 Provide battery chargers & battery back-up per the contract documents. Yes

103 Intrusion Detection System Yes

104

Provide the following items per the contract documents, including but not limited to

Intrusion Detection control panels, expansion modules, relay boards, keypads,

network communication modules, motion sensors, glass break detectors, duress

alarms, siren & speaker horns, strobes, device power supplies, cabling & cabling

support.

Yes

105 Coordination with door hardware supplier & glazer. Yes

106 Provide battery chargers & battery back-up per the contract documents. Yes

107 Video Surveillance System Yes

108

Provide the following items per the contract documents, including but not limited to

Video Surveillance software, racks, cameras, uninterruptible power supplies, surge

protection, cabling, cabling support and grounding/bonding.

Yes

109 Provide ONSSI Software Upgrade Plan (1-Year) for Ocularis CS platform. Yes

110 Install a new two-post rack in existing MDF room with a double-sided steel shelf.Yes

111

Includes all labeling, color coding, testing, certification, etc. of the system per the

contract documents.Yes

112 Replace all ceiling tiles if removed to perform your scope of work. Yes

113 Provide all sleeves & firestopping as required. Yes

114

Protect all work from incidental damage upon completion (cover with cardboard,

etc.).Yes

115

Protect all work from incidental damage upon completion (cover with cardboard,

etc.).Yes

116

Licenses, permits, tests, fees, inspections, and warranties required by the Contract

Documents and applicable codes.Yes

117

Provide all necessary engineering & deferred submittals (if required by local code

authority).Yes

118

Provide all necessary equipment and personnel to perform all tests & inspections

required.Yes

119 All coordination of the contract documents required to perform this scope of work. Yes

120

This Subcontractor is responsible for providing all coordination drawings, as required

by the Contract Documents.Yes

121

Subcontractor shall provide all information and documentation required for BIM

coordination and as-builts.Yes

122 Submittals are due within four (4) weeks after receipt of this agreement. Yes

123 Provide Owner Training as called for in the contract documents. Yes

Page 236: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

124

Pretest existing system to determine if system is fully functioning or not. Document

test results prior to beginning any work.Yes

125

All existing systems are to remain functional during normal school hours. Critical work

that requires the existing systems to be off line will be coordinated with the

superintendent and will have to take place during after hours, weekends and holidays.

Yes

126 Subtotal - Scope Revisions -$

127 Yes

128 Yes

129 Yes

130 Yes

131 Yes

132 Yes

133 Yes

134 Yes

135 Subtotal - Alternates -$

136 Yes

137 Yes

138 Yes

139 Subtotal - Value Engineering -$

140 Yes

141 Yes

142 Yes143 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 237: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 31A - EARTHWORK & SITE DEMOLITION Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 238: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 239: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 240: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 02 4100 Demolition Yes

83 02 41 13.10 Site - Misc. Demo of paving & walks Yes

84 31 00 00 Site Earthwork Yes

85 31 06 20.15 Cement Stabilized Sand Yes

86 31 11 00 Clearing & Grubbing Yes

87 31 22 00 Site Grading Yes

88 31 23 10 Building Excavation & Fill Yes

89 32 11 13.13 Lime-Treated Subgrades Yes

90 32 91 13.13 Topsoil Placement & Grading Yes

91 Yes

92

Provide a Complete Turnkey Scope of Work for EARTHWORK per all project plans,

specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

Trade Specific Scope

Page 241: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

93

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

94

Provide a turnkey site demolition, earthwork and asphalt paving package per the

contract documents.Yes

95 Site Demolition Yes

96

Removal & disposal of the trees, communications vault (empty), power pole (de-

energized), concrete curb & pavingYes

97

Removal & disposal of the temporary buildings, sidewalks & ramps for t-buildings,

communications vault, asphalt paving & base materials, existing & temporary fencing,

concrete paving & curbs, base material and signage

Yes

98 Sawcutting of existing for proper future tie-in. Yes

99 Earthwork Yes

100 Clear & grub site with offsite disposal of vegetation. Yes

101 Strip & stockpile existing topsoil. If not used or redistributed as fill, haul-off excess.Yes

102 Cut & fill site to subgrades per the contract documents. Yes

Provide specified fill under building as required to meet final sub-grade elevation.

103

Subgrade preparation for concrete paving & walks. Provide stabilization of sub-grade

for paving as specified.Yes

104 Haul-off balance of site, if required. Yes

105 Shaping of channel for Off-Site Drainage Improvements Yes

106 Protection of existing transmission tower base and structure in channel. Yes

107 Detention Pond Excavation and Haul Off Yes

108 All site demolition work done but not limited to on sheets: C001 thru C702 Yes

109 Site Demo to include but not limited to: Yes

110 Full Depth Saw Cut Yes

111 Remove - Asphalt Walkway Yes

112 Remove - Bench Yes

113 Remove - Brickwall with Gate Yes

114 Remove - Temporary Classroom Buildings Yes

115 Remove - Concrete Pavement Yes

116 Remove - Curb Yes

117 Remove - Light Pole Yes

118 Remove - Sidewalk Yes

119 Remove - Striping Yes

120 Remove - Tree Yes

121 Provide all layout and grades for this scope. Yes

122 Yes

123 Yes

124 Yes

125 Yes

126 Yes

127 Yes

128 Yes

129 Yes

130 Yes

131 Yes

132 Yes

133 Subtotal - Scope Revisions -$

134 Yes

135 Yes

136 Yes

137 Yes

138 Yes

139 Yes

140 Yes

141 Yes

142 Subtotal - Alternates -$

143 Yes

144 Yes

Project Alternates

Project Value Engineering

Page 242: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

145 Yes

146 Subtotal - Value Engineering -$

147 Underground detention system. Refer to work package 33A for scope. Yes

148 Yes

149 Yes150 Yes

The following items are specifically EXCLUDED:

Page 243: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 31B - TERMITE TREATMENT Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 244: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 245: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 246: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 31 3116 Termite Control Yes

83 Yes

84 Yes

85

Provide and install a Complete Turnkey Scope of Work for TERMITE TREATMENT

per all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

86

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.Yes

87 Termite Control For New Addition Yes

88 Yes

89 Yes

90 Yes

91 Yes

92 Yes

93 Yes

Trade Specific Scope

Page 247: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

94 Yes

95 Yes

96 Subtotal - Scope Revisions -$

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Subtotal - Alternates -$

106 Yes

107 Yes

108 Yes

109 Subtotal - Value Engineering -$

110 Yes

111 Yes

112 Yes113 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 248: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 32A - FENCING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 249: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 250: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 251: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 32 31 11 Gate Operators Yes

83 32 31 13 Chain Link Fences & Gates Yes

84 32 31 19 Decorative Metal Fences & Gates Yes

85 Yes

86 Yes

87 Yes

88 Yes

Trade Specific Scope

Page 252: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

89

Provide and install a Complete Turnkey Scope of Work for FENCING per all project

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions. Including but not limited to ornamental fencing, all

gates and openings, hardware and accessories.

Yes

90

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

91 Ornamental Fencing Yes

92 Decorative Metal Fence Yes

93 Decorative Metal Gate Yes

94 Yes

95 Subtotal - Scope Revisions -$

96 Yes

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Subtotal - Alternates -$

105 Yes

106 Yes

107 Yes

108 Subtotal - Value Engineering -$

109 Yes

110 Yes

111 Yes112 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 253: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 32B - PAVEMENT MARKINGS Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 254: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 255: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 256: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 32 1723 Pavement Markings Yes

83 Yes

84 Yes

85

Provide and install a Complete Turnkey Scope of Work for PAVEMENT MARKINGS

per all project plans, specifications, addendum, value engineering and all uniform

general & supplementary conditions.

Yes

86

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

87 Yes

88 Wheel Stops Yes

89

Place parking bumpers at each ADA parking space and other locations as shown on

the drawings.Yes

90

Includes epoxy coated dowels (core drill holes into concrete), epoxy adhesives &

grout where called for per the contract documents.Yes

Trade Specific Scope

Page 257: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

91 Striping Yes

92 Provide pavement markings where shown on the drawings including the Fire Lane.Yes

93 Colors shall be per the contract documents and/or applicable codes. Yes

94

Prep areas prior to striping per the specifications and/or manufacturer's

recommendations. Include power washing or other means of cleaning acceptable

to your scope of work.

Yes

95 Barricade and/or protect striping until it has completely cured. Yes

96 Traffic Signage Yes

97 Signage Specifications Per Civil Drawings Yes

98 Fire Lane signage per applicable local code. Yes

99 Place all traffic signage where shown on the drawings & where required by code.Yes

100 Provide core drilling of concrete at areas of signed post located within concrete.Yes

101 Subtotal - Scope Revisions -$

102 Yes

103 Yes

104 Yes

105 Yes

106 Yes

107 Yes

108 Yes

109 Yes

110 Subtotal - Alternates -$

111 Yes

112 Yes

113 Yes

114 Subtotal - Value Engineering -$

115 Yes

116 Yes

117 Yes118 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 258: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 32D - PLAYGROUND EQUIPMENT & SURFACING Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 259: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 260: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 261: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 11 6813 Playground Equipment Yes

83 32 1816.13 Playground Protective Surfaces Yes

84 Yes

85 Yes

86 Yes

87 Yes

88 Yes

89

Provide a Complete Turnkey Scope of Work for PLAYGROUND EQUIPMENT &

SURFACING per all project plans, specifications, addendum, value engineering and

all uniform general & supplementary conditions.

Yes

90

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

91 Yes

92 Playground Yes

Trade Specific Scope

Page 262: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

93 Out Door Fall Protection For Playground Surfacing Yes

94 Remove, Store & Re-install Playground Equipment over New Surfacing Yes

95 Yes

96 Subtotal - Scope Revisions -$

97 Yes

98 Yes

99 Yes

100 Yes

101 Yes

102 Yes

103 Yes

104 Yes

105 Subtotal - Alternates -$

106 Yes

107 Yes

108 Yes

109 Subtotal - Value Engineering -$

110 Yes

111 Yes

112 Yes113 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED:

Page 263: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

Project SBISD - Cedar Brook E.S. Base -$

Scope Revision -$

Bid Package Scope 33A - UTILITIES Alternates -$

VE -$

Job No./Phase

Contract No.

Total Contract -$

Company name

Mailing Address

Contact Phone:

Email

Co. Designation

Reference Scope Item Included

1 General

All deviations from or discrepancies to the plan, specifications, schedule or submittal

requirements must be brought to the immediate attention of the Contractor in writing

with sufficient details reference and explanations to permit proper analysis.

Suggested solutions or substitutions shall accompany the notification whenever

possible.

Yes

2 General

In addition to the foregoing, it is further understood and agreed that this Subcontract

Agreement also includes, but is not limited to, the following conditions and items,

regardless of whether or not they are in the below listed Specification Sections, or any

other Specification Section, or shown on the plans. All notes, keynotes, and details on

all contract documents related to this subcontractors work are included within this

agreement. This subcontractor acknowledges all project specifications, all project

drawings, and all related contractual provisions. The items listed below are not

intended to represent each and every item necessary to perform the Work.

Yes

3 General

Subcontractor is responsible for notifying all utility companies and having them locate

their existing utilities prior to starting work and advising the Contractor of required

street, sidewalk, utility or other system tie-ins or shutdowns in time to allow

Contractor to properly coordinate the Work.

Yes

4 General

All work and deliveries are to be coordinated and performed in accordance with the

overall project requirements and schedule, including sequence. All required move-

ins/mobilizations to meet project schedule, requirements, equipment and manpower

requirements and coordination and cooperation with other subcontractors. It is

understood that any overtime cost incurred by the Subcontractor to meet their

schedule commitments to the Contractor are the responsibility of the Subcontractor.

It is also understood that to meet certain project requirements it will be necessary to

perform some work tasks during nights, weekend, and holidays, off-hours, or make-up

hours (i.e. shift work, additional manpower, and/or acceleration). All premium costs

associated with the aforementioned are included in this Subcontract Agreement.

Yes

5 General

The Subcontractor shall set up, arrange, coordinate and obtain all inspections for their

work, as required by any authorized agency or applicable code. Arrangements for the

inspection of any area, system, equipment, etc., needed testing or inspection prior to

being covered up must be made by the subcontractor in sufficient time to allow for

inspections so as not to impact the project schedule.

Yes

6 General

Subcontractor must identify the competent person (English speaking)who is

responsible for the implementation of their safety plan or program. This individual

must have authority to direct job site superintendents, foremen, and workers to

comply with safety directives and monitor the corrective responses until satisfactory

completion. This Subcontractor shall make available all history of accidents, workers

compensation rates, etc. as may be required in a timely manner.

Yes

Page 264: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

7 General

Temporary power for construction is limited. Generators required for work of this

subcontract shall be the responsibility of this Subcontractor. All specific power and

lighting, including task lighting, required for Subcontractor's work is the responsibility

of Subcontractor.

Yes

8 GeneralProvide S&P with 3 week look ahead schedules conforming to the overall sequence

and dates established by the projects CPM Schedule.Yes

9 General

Subcontractor is responsible for layout required to perform their scope of work

including any field measurements. It shall also be the responsibility of the

Subcontractor to maintain and preserve all stakes and other control established by

Contractor or Owner. If control or stakes are destroyed by Subcontractor, they will be

replaced at their expense.

Yes

10 General

The Subcontractor shall perform all cutting, core drilling, access, clean-up, patching,

repair, filling, disposal etc. as required to install your scope of work. Any fire

extinguishers, multiple flash screens, fire protection blankets, and fire watchman is

the responsibility of this Subcontractor as required by this scope of work.

Yes

11 General

The Subcontractor is responsible to meet or exceed the OSHA regulations. The

primary responsibility for safety resides with each subcontractor for its workers.

Subcontractors and their employees (workers) will be responsible for their health and

safety performance.

Yes

12 General Subcontractor is responsible for his or her drinking water. Yes

13 General SWPPP/Erosion control - As applies Yes

14 GeneralAll subcontractor vehicles exiting the site are required to clean vehicles at the site exit

wash area. Yes

15 GeneralProvide S&P weekly safety meeting minutes, daily pretask planning (JSA), and daily

reportsYes

16 General

Attendance at S&P weekly subcontractor meetings (Will attend Pre-Construction

Meeting, Coordination Meetings and other meetings as the need arises) Yes

17 General Daily sweeping and removal of construction debris. Yes

18 General

Subcontractor will cooperate in carrying out Contractor's quality assurance program

including, but not limited to, furnishing necessary documentation and facilitating

inspections, testing, etc.

Yes

19 General

Subcontractor shall provide temporary protection and support, shoring, dust control,

and temporary partitions to protect all work adjacent or susceptible to damage by this

scope of work.

Yes

20 General

Complete protection and restoration of the disturbed conditions outside of the

primary project boundaries as a part of your work is included in each subcontract

unless specifically excluded.

Yes

21 General All punch lists to be complete in accordance with Contractor's schedule. Yes

22 General

Subcontractor shall maintain up-to-date asbuilts drawings on site at all times. As-built

drawings shall be updated weekly at a minimum and shall be made available for

review at all times by Contractor.

Yes

23 General Traffic control and dust control for your work - As applies Yes

24 General Parking for your employees is offsite if no onsite parking is available. Yes

25 General

The Subcontractor will unload, store and protect all material required for his work as

delivered to the jobsite. It shall be the responsibility of the Subcontractor to

coordinate all jobsite shipments with S&P Superintendent. All material will be

palletized or bundled. Any flagman as may be required for these deliveries is the

responsibility of this Subcontractor. In the event material is delivered to the job and

the Subcontractor's personnel are not available, the Contractor shall unload and

charge for the costs of unloading and storing unless agreed to in advance. However,

The Contractor will not be responsible for any loss or damage from any cause

whatsoever to the material.

Yes

26 GeneralSubcontractor is responsible for obtaining field dimensions required for the

preparation of shop drawings, submittals, and final fabrication.Yes

27 GeneralSubcontractor will transmit certified payroll on a monthly basis or as required by

Owner, due with monthly pay requisition. Yes

28 General Receipt of Job Information Packet (JIP) Manual. Yes

29 GeneralCloseout documents required for review 2 months prior to scheduled substantial

completion.Yes

30 General Asbuilts will be provided digitally as well as hard copies Yes

Page 265: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

31 General

Exploratory measures and associated costs required for determining the existence and

location of underground utilities or lines in areas where work of this subcontract

occurs.

Yes

32 General

For this trade performing new and/or remodeling work on the premises of this

project, all required certificates and validations for each employee performing work

are required to be submitted as required by the Federal Environmental Protection

Agency’s (EPA) Renovation, Repair, and Painting Rule.  This trade is required to

provide all required certifications necessary outlined by the EPA and submit to the

general contractor prior to commencement of any work.

Yes

Specifications

331

Contract between Project Owner and Satterfield & Pontikes Construction, Inc.Yes

Division 00 Procurement and Contracting Requirements

34 00 0115 List of Drawing Sheets Yes

35 00 2116 Instructions To Proposers Yes

36 00 3126 Existing Hazardous Material Information Yes

37 00 3132 Geotechnical Data Yes

38 00 7200 General Conditions - A201 - 2017 Yes

39 00 7300 Supplementary Conditions Yes

40 00 7343 Wage Rate Requirements Yes

41 Yes

Division 01 General Requirements

42 01 1100 Summary Of Work Yes

43 01 1400 Work Restrictions Yes

44 01 2100 Allowances Yes

45 01 2200 Unit Prices Yes

46 01 2300 Alternates Yes

47 01 3000 Administrative Requirements Yes

48 01 3216 Construction Progress Schedule Yes

49 01 3223 Survey & Layout Data Yes

50 01 4000 Quality Requirements Yes

51 01 4100 Regulatory Requirements Yes

52 01 4516 Contractor's Quality Control Yes

53 01 4533 Code-Required Quality Control Yes

54 01 5000 Temporary Facilities & Controls Yes

55 01 5513.10 Stabilized Construction Entrance Yes

56 01 5526 Traffic Control Yes

57 01 5710 TPDES Requirements Yes

58 01 5719.00 Indoor Air Quality Controls Yes

59 01 5719.10 Control Of Ground & Surface Water Yes

60 01 5723 Temporary Storm Water Pollution Control Yes

61 01 6000 Product Requirements Yes

62 01 6210 Schedule Of Materials & Colors Yes

63 01 7000 Execution & Closeout Requirements Yes

64 01 7416 Site Maintenance Yes

65 01 7419 Construction Waste Management Disposal Yes

66 01 7800 Closeout Submittals Yes

67 01 7900 Demonstration & Training Yes

68

69

70 General

BIM Requirements as specified. Subcontractors are to include the cost for providing

the following Building Information Modeling requirements: Where the contract

documents refer to shop drawings and coordination drawings, these documents are

to be provided in Revit Software or AutoCAD 3D. Attendance of coordination

meetings as directed by S&P. Provide all required documents and data necessary for

the implementation and completion of the closeout process, including the tagging of

the components being modeled and the nomenclature required by S&P.

Yes

All CSI Divisions and individual Specifications Sections listed below are a part of this Subcontract Agreement:

This Subcontractor shall be responsible for providing all labor, materials, tools, equipment and incidentals for performing all work included in the

Specification Sections listed below.

All Subcontractors

CM General Requirements

Page 266: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

71 GeneralSubcontractor will provide temporary toilets (1 for every 5 workers) to be serviced

twice a week for duration of their on site time.Yes

72 General

This subcontractor shall provide in their contract amount a daily cleaning sum for each

day that the subcontractor will be working on the project. This dedicated amount is to

be used to employ a worker that will be responsible for safety item maintenance,

trash removal from the building and maintaining a safe environment.

Yes

73 General

This subcontractor shall be responsible for trash removal from the site. Each

contractor shall carry an amount for each day worked on the project to cover the cost

of removal of trash from the site.

Yes

74 General All mobilizations required to complete this scope of work. Yes

75 GeneralThis subcontractor acknowledges the Existing Asbestos Information and

Environmental Assessment Information.Yes

76 General

All Subcontractors will include the cost for the CM managed Subcontractor

Security/Bond Program. This cost is to be included in the amount of 2.5% of the total

proposal amount and is to be included in all future changes that result in a change

order.

Yes

77 General

All Subcontractors will include the cost for BIM for CM's management and analysis of

the models provided by the subcontractors and designers. This includes coordination

of all trades, their models and the sharing of such models; conflict management and

resolution with the design consultants and subcontractors; integration and oversight

of total model completion, maintenance and closeout. This cost is to be included in

the amount of 1% of the total proposal amount.

Yes

78 General

This Project falls under the requirements of Senate Bill 9, and subsequent Texas

Education Association (TEA) rulings as it relates to criminal background checks and

fingerprinting. It will be the responsibility of the Subcontractor, and any lowered tier

subcontractors, to abide by the requirements of this legislation and assume all costs

for compliance. Badges will be required of all workers for this project.

Yes

79 General

It is the intent of this scope of work to convey to this subcontractor the total

responsibility for this work package. This subcontractor understands that due to the

fast track nature of this project, Construction Documents may not be 100 Percent

complete and will develop as the project progresses. However the subcontractor shall

perform all work required or reasonably inferred under the best practices in the

construction industry for a complete, fully functional and operational system for the

purpose intended.

Yes

80 General

Subcontractor shall inspect and survey all building areas and substrates in advance of

fabrication or installation of any work. The Subcontractor shall advise the CM of any

conditions which are inconsistent with the contract documents or will hinder proper

installation of the subcontractors work. Start of the work by the subcontractor will

indicate acceptability of substrates, openings and support bracing systems provided

by others.

Yes

81 GeneralSubcontractor will cooperate fully with the CM and other key trades to ensure

obtaining the certificate of Occupancy in an expeditious manner.Yes

82 31 06 20.17 Utility Backfill Materials Yes

83 31 23 16.14 Trench Safety System Yes

84 31 23 33 Excavation & Backfill For Utilities Yes

85 33 05 16.16 Concrete For Utility Construction Yes

86 33 10 00 Water Distribution Yes

87 33 06 10.14 Polyvinyl Chloride (PVC) Pipe Yes

88 33 06 10.15 Ductile Iron Pipes & Fittings Yes

89 33 06 40.10 HDPE Solid & Profile Wall Pipe Yes

90 33 20 00 Sanitary Sewer Yes

91 33 05 13.00 Manholes & Structures Yes

92 33 05 13.13 Manhole Grade Adjustment Yes

93 33 05 16.13 Precast Concrete Utility Structures Yes

94 33 06 40.11 Reinforced Concrete Pipe Yes

95 33 30 00 Storm Sewer Yes

96 33 41 00 Storm Utility Drainage Piping Yes

97 33 49 13 Storm Drainage Manholes Frames & Covers Yes

Trade Specific Scope

Page 267: 08.21.2019 Addendum No 1 - Bid Packages - Huckabee

98 Yes

99 Yes

100

Provide a Complete Site Utility and Underground Detention System per all project

plans, specifications, addendum, value engineering and all uniform general &

supplementary conditions.

Yes

101

This is a phased project. All mobilizations and demobilizations required to meet the

phasing plan are included. Night and weekend work will be required.

Yes

102

Provide all site water, fire water, storm and sanitary systems including but not limited

to drainage structures, inlets, grates, trench drains, junction boxes, valves, boxes,

manholes, meters and accessories, adjustment of existing structures to meet new

elevations, layout and grade.

Yes

103

Includes all coordination with local authorities having jurisdiction over the project,

schedule all tests & inspections as required.Yes

104 Trenching, bedding and backfill per contract documents. Yes

105

Responsible to protect all open trenches or any other hazards that arise from your

scope of work.Yes

106

Includes dust control, street cleaning & traffic control necessary to complete the

scope of work.Yes

107 Trench & excavation safety as required. Yes

108

Verify accuracy of existing utilities as shown on the drawings and immediately notify

the Project Superintendent of any discrepancies.Yes

109

Verify and coordinate tie-in elevations of existing systems PRIOR to beginning work.

Confirm existing elevations are correct and consistent with the contract documents.

Yes

110

Provide all site utility demo as required and shown within the contract documents,

including but not limited to sawcutting, cut & plug, removal, and haul-off.

Yes

111

Provide a complete detention system including but not limited to excavation, bedding,

backfill, haul-off of excess spoils, detention structure, fittings, manholes and

accessories.

Yes

112 Tie-In Canopy Downspouts Yes

113 Yes

112 Yes

113 Yes

114 Yes

115 Subtotal - Scope Revisions -$

116 Yes

117 Yes

118 Yes

119 Yes

120 Yes

121 Yes

122 Yes

123 Yes

124 Subtotal - Alternates -$

125 Yes

126 Yes

127 Yes

128 Subtotal - Value Engineering -$

129 Yes

130 Yes

131 Yes132 Yes

Project Alternates

Project Value Engineering

The following items are specifically EXCLUDED: