Primavera Risk Analysis Tips & Tricks 01-13 Objectives: To demonstrate one of the correct methods of importing or converting Primavera project files to Oracle Primavera Risk Analysis (OPRA). To teach the new Risk Analyst how to align the OPRA schedule to the original P6 schedule and ensure an accurate Schedule Quantitative Risk Assessment. To save time and optimize effort. ABSTRACT Many risk professionals have experienced much difficulties using PertMaster (now known as OPRA) in processing their sample deterministic schedule for quantification and analysis. The persistent issues encountered, especially by new would be risk analyst is the discrepancy of the risk plan file and the original multi-calendar Primavera schedule after import. If the flawed translation is not properly addressed, reference and original deterministic dates of affected activities will stay misaligned, producing erroneous results. This short write up will attempt to present the secret key to the proper use of the tool and prevent loss of data quality, hence, an accurate risk assessment! REV: 25-May-15

Upload: rufran-frago-p-eng-pmp-ccp-rmp-author

Post on 12-Jan-2017

4.482 views

Category:

Business


0 download

TRANSCRIPT

Primavera Risk Analysis Tips & Tricks 01-13

Objectives:

To demonstrate one of the correct methods of importing or converting Primavera project files to Oracle Primavera Risk Analysis (OPRA). To teach the new Risk Analyst how to align the OPRA schedule to the original P6 schedule and ensure an accurate Schedule Quantitative Risk Assessment. To save time and optimize effort.

ABSTRACT

Many risk professionals have experienced much difficulties using PertMaster (now known as OPRA) in processing their sample deterministic schedule for quantification and analysis.

The persistent issues encountered, especially by new would be risk analyst is the discrepancy of the risk plan file and the original multi-calendar Primavera schedule after import. If the flawed translation is not properly addressed, reference and original deterministic dates of affected activities will stay misaligned, producing erroneous results.

This short write up will attempt to present the secret key to the proper use of the tool and prevent loss of data quality, hence, an accurate risk assessment!

REV: 25-May-15

052815-Rufran's Primavera Risk Analysis Tips Tricks 01-13 Page 1 of 35

Author: Rufran C. Frago, P. Eng., PMP, CCP, PMI-RMP

Sorry, the article you are looking was removed.

You will find a more detailed discussion about the subject and many other related topics in the paperback edition of the book "Risk-based Management in the World of Threats and Opportunities: A Project Controls Perspective." It is also available in Amazon’s Kindle edition.

Please follow the hyperlink below or copy and paste the URL on your browser to check. You can now grab a copy. Check it out!

• http://www.amazon.com/RUFRAN-C.-FRAGO-PMI-RMP/e/B01055MPYI

• http://www.amazon.com/dp/B0104OFUDI/ref=rdr_kindle_ext_tmb

• https://www.linkedin.com/pulse/risk-based-management-world-threats-opportunities-rufran?trk=prof-post

Cheers,

Rufran C. Frago

Author

Owner
Text Box
Sorry, the article you were looking for was removed.

052815-Rufran's Primavera Risk Analysis Tips Tricks 01-13 Page 2 of 35

Author: Rufran C. Frago, P. Eng., PMP, CCP, PMI-RMP

TABLE OF CONTENTS

1. SITUATION/PROBLEM ............................................................................................................................................ 4

2. RELATED ELATED TOOLS ...................................................................................................................................... 4

3. DEFINITION .................................................................................................................................................................. 4

4. PROBLEM ANALYSIS (PA) ...................................................................................................................................... 5

5. EXPLANATION/SOLUTION ................................................................................................................................. 11

6. REFERENCES ............................................................................................................................................................ 32

7. INDEX ........................................................................................................................................................................... 33

052815-Rufran's Primavera Risk Analysis Tips Tricks 01-13 Page 3 of 35

Author: Rufran C. Frago, P. Eng., PMP, CCP, PMI-RMP

TABLE OF FIGURES

Figure 1 - Project A Activity View ..................................................................................................... 6 Figure 2 – Project A Activity View showing Durations & Duration Ranges ..................... 7 Figure 3 – OPRA Import Settings Window .................................................................................... 8 Figure 4 – OPRA Import Log Dialogue Box ................................................................................... 8 Figure 5 – OPRA Import Warning Log (Notepad text) ............................................................. 9 Figure 6 – Result of Import Check ................................................................................................. 10 Figure 7 – OPRA Activity View showing the Translated Min, ML & Max Duration .... 10 Figure 8 – Project A Showing the Translated Min, ML, & Max Duration in Hours ...... 12 Figure 9 – OPRA Import Setting\General Tab Using Hour as the Planning Unit ........ 13 Figure 10 – OPRA Import Setting\Tasks Tab-Using Hour as the unit of Entry ........... 14 Figure 11 – OPRA Import Warning Report Log........................................................................ 15 Figure 12 – Check/Correct Proper date Setting ....................................................................... 16 Figure 13 – Project-A Import Check of a correctly imported schedule .......................... 17 Figure 14 – Risk Analysis Dialogue Box ...................................................................................... 18 Figure 15 – OPRA Risk Analysis Options-Risk Data Tab Dialogue Box ........................... 18 Figure 16 – OPRA Risk Options\Analysis Tab Dialogue Bo ................................................. 19 Figure 17 – OPRA Risk Analysis Options-Warnings Tab Dialogue Box .......................... 20 Figure 18 – Example of Risk Errors and Warnings ................................................................. 21 Figure 19 – Example of Risk Errors and Warnings ................................................................. 21 Figure 20 – Example of Risk Errors and Warnings ................................................................. 22 Figure 21 – Calculation Status Box ................................................................................................ 22 Figure 22 – Cross-check OPRA Ranges to Confirm Translation is Correct .................... 23 Figure 23 – Planning Unit Window ............................................................................................... 23 Figure 24 – Example Distribution Chart ..................................................................................... 24 Figure 25 – Example Distribution Chart ..................................................................................... 25 Figure 26 – Example Distribution Chart ..................................................................................... 26 Figure 27 – Example Distribution Analyzer .............................................................................. 27 Figure 27 – Plan Options-Time Tab Dialogue Box .................................................................. 28 Figure 29 – Schedule Options\Scheduling Tab (OPRA) ........................................................ 30 Figure 30 – Schedule Option\General (P6) ............................................................................... 31