05 shuttering.doc2
DESCRIPTION
05 Shuttering.doc2TRANSCRIPT
LARSEN & TOUBRO LIMITED
LARSEN & TOUBRO LIMITED:: ECC DIVISIONBUILDINGS AND FACTORIES OPERATING COMPANY
Ref: IM 08 D Rev 00
Date:01.11.08SAFE WORK METHOD FOR SHUTTERING ACTIVITYDocument No
: SHUTTERING / F/05Name of the Job Site: ICICI BANK PROJECT, HyderabadRisk Level
: LowSafe Work Method:
SHUTTERING
Shuttering shall be done as per the drawing given and under supervision.
Before it is cleared for concrete pouring the carpentry foreman shall inspect for the reliability of the shutters.
While pouring the concrete, persons shall be assigned to keep a watch on the shutters & its supports esp. during major pours; for reliability.
Employees should be briefed the proper handling of the shuttering materials.
Shuttering oil should be applied gently over the shuttering plates. Overdose may make the floor form more slippery. Instruction should be given for NO SMOKING and care for no fire/ hot work occurs nearby.
Vessel containing shuttering oil should be covered and kept in a safe place to avoid any ignition source come and contact with the shuttering oil.
Dismantling of shutters is done as per the instruction and supervision of the foreman.
Tools & nails are to be kept in a toolbox.
No materials shall be left scattered on the ground. The foreman shall ensure good housekeeping.
Residual risk( if any):LowAction By
: ___________________
PM/CM / Section Head HSEO