04.00 calculo de movilizacion y transporte de material

Upload: cm-wil

Post on 03-Apr-2018

230 views

Category:

Documents


2 download

TRANSCRIPT

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    1/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo: Puente Montalvo - Puente Camiara.

    COSTO DE HORA - HOMBRE

    VIGENTE AL 01.06.06

    DESCRIPCION OPERARIO OFICIAL PEON

    REMUNERACION BASICA VIGENTE (RB) (*) 35.09 31.36 28.03

    BONIFICACION UNIFICADA DE CONSTRUCCION (BUC) 11.23 9.41 8.41

    BONIFICACION POR MOVILIDAD ACUMULADA 7.20 7.20 7.20

    OVEROL 0.40 0.40 0.40

    TOTAL LEYES SOCIALES SOBRE BONIFICACION BASICA (113.28%) 39.75 35.52 31.75

    TOTAL LEYES SOCIALES SOBRE BUC (12.00%) 1.35 1.13 1.01

    TOTAL POR DIA DE 8 HORAS (SOLES) 95.02 85.02 76.80

    COSTO DE HORA HOMBRE (SOLES) 11.88 10.63 9.60

    CAPATAZ " A " (SOLES) = 1.30 x 11.88 = 15.44

    CAPATAZ " B " (SOLES) = 1.20 x 11.88 = 14.26

    CAPATAZ " C " (SOLES) = 1.10 x 11.88 = 13.07

    Elaborado con base en la Resolucin Directoral N 090-2003-DRTPSL-DPSC

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    2/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo: Puente Montalvo - Puente Camiara.

    DISTANCIAS VIRTUALES

    CENTROS DE ABASTECIMIENTOLIMA: (CEMENTO ASFALTICO MODIFICADO Y OTROS MATERIALES)CONCHN: (CEMENTO ASFALTICO NORMAL, ASFALTOS DILUIDOS Y OTROS MATERIALES)MOQUEGUA: (TUBOS Y OTROS MATERIALES)MOLLENDO: (PETROLEO DIESEL)AREQUIPA: (CEMENTO PORTLAND, ACERO Y OTROS MATERIALES)

    CUADRO DE DISTANCIAS VIRTUALES

    RUTAS DISTANCIA VIRTUALDE A ( KM )

    LIMA OBRA 1,224.10

    CONCHN OBRA 1,197.30

    MOLLENDO OBRA 110.50

    MOQUEGUA OBRA 45.30

    AREQUIPA OBRA 265.00

    TACNA OBRA 208.00

    Para el clculo de los fletes se empleo la ltima Resolucin CRTT que aprueba la FijacinTarifaria del Servicio Pblico de Transporte de Carga en Camiones en la Ruta del SistemaNacional de Carreteras R.C.D. N 027-91-TC/CRTT-T de Junio de 1991. (Artculo 3o. y 10o. )

    RUTAS DIST. FACTOR DISTANCIA VIRTUAL

    DE A REAL ( KM )

    LIMA - OBRA:

    Lima (Km 0+000) Pte Montalvo (Km 1139+700) 1,139.70 1.04 1,185.30

    Pte Montalvo (Km 1139+700) Obra (c.g. Tramo) Km 36.63 1.06 38.80

    TOTAL ----->. 1,224.10

    CONCHN - OBRA:

    Conchn (Km25+750) Pte Montalvo (Km 1139+700) 1,113.95 1.04 1,158.50

    Pte Montalvo (Km 1139+700) Obra (c.g. Tramo) 36.63 1.06 38.80

    TOTAL ----->. 1,197.30

    MOQUEGUA - OBRA:

    MOQUEGUA (Km 1146+580) Dv. Moquegua (Km 1140+000) 6.58 1.04 6.80

    Dv. Moquegua (Km 1140+000) Obra (c.g. Tramo) 36.33 1.06 38.50

    TOTAL ----->. 45.30

    MOLLENDO - OBRA: Mollendo (Km 1051+000) Dv. Mollendo 69.25 1.04 72.00

    Dv. Mollendo Pte Montalvo (Km 1139+700) 157.95 1.40 221.10

    Pte Montalvo (Km 1139+700) Obra (c.g. Tramo) 36.33 1.06 38.50

    TOTAL ----->. 110.50

    AREQUIPA - OBRA:

    Arequipa (Km 1008+900) Dv Mollendo (Km 981+750) 56 87 1 04 59 10

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    3/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo: Puente Montalvo - Puente Camiara.

    CALCULO DE FLETE :

    VEHICULO TIPO = C4, 8 x 4CAPACIDAD DE CARGA = 20,000 KG

    CICLO = NORMAL + FRV

    COSTO APLICADO = SEGN DISTANCIA 0.18648

    DISTANCIAVIRTUAL

    ( KM )

    PESO( KG )

    COSTONORMAL( SOLES )

    COSTO FRV( SOLES )

    COSTO TOTAL( SOLES )

    COSTO( SOLES / KG )

    FACTOR DEACTUALIZACION

    COSTOACTUAL

    ( SOLES / KG )1 ) LIMA - OBRA 1,224.10 20,000 3,699.30 1,479.10 5,178.40 0.259 1.100 0.2852 ) CONCHAN - OBRA 1,197.30 20,000 3,617.90 1,447.30 5,065.20 0.253 1.100 0.2783 ) MOLLENDO - OBRA 110.50 20,000 721.74 0.00 721.74 0.036 1.100 0.040

    4 ) AREQUIPA - OBRA 265.00 20,000 1,034.76 413.90 1,448.66 0.072 1.100 0.0795 ) MOQUEGUA - OBRA 45.30 20,000 591.06 0.00 591.06 0.030 1.100 0.0336 ) TACNA - OBRA 208.00 20,000 919.28 367.71 1,286.99 0.064 1.100 0.070

    ACTUALIZACION A JULIO DEL 2006:

    Iu (32) Julio.05 382.01K = ----------------- = ----------------- = 1.200

    Iu (32) Nov.02 318.23 1.100 MAYOR DEL RANGO DEL 10% ADOPTAR 1.1

    RUTA

    Debido a que el D.S. N 049-2002-MTC (30.12.02) contempla el Costo del Flete a Noviembre.02 y que a Julio.04 no han habido nuevas publicaciones, hemos Actualizadoestos valores teniendo presente lo indicado en D.S. N 021-2003-MTC (14.05.03)

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    4/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo: Puente Montalvo - Puente Camiara.

    COSTO DE HORARIO DE EQUIPO MECANICO

    FECHA: Julio 2006

    TIPO DE CAMBIO: 3.244

    COSTO DE COSTO DE COSTO

    EQUIPO MECANICO POT. CAPACIDAD PESO POSESION OPERACION HORARIO

    HP KG S/. S/. S/.

    BARREDORA MECANICA 10-20 7 long. 1000 10.38 31.73 42.11

    CAMION BARANDA 3,000 kg 3000 19.93 32.51 52.44

    CAMION CISTERNA (4X2) AGUA 145-165 2,000 gl 13000 45.41 71.22 116.63

    CAMION IMPRIMADOR 6x2 178-210 1,800 gl 16475 46.33 116.25 162.58

    CAMIONETA PICK UP 4x2 107 1,000 kg 2450 9.3 46.82 56.12CAMION VOLQUETE 330 15 m3 26000 47.86 142.32 190.18

    CARGADOR RETROEXCAVADOR 62 1 yd3 8000 42.4 59.88 102.28

    CARGADOR SOBRE LLANTAS 100-115 2.00-2.25 yd3 10308 44.76 74.78 119.54

    CARGADOR SOBRE LLANTAS 160-195 3.5 yd3 18585 90.57 127.38 217.95

    CHANCADORA PRIM/SECUND. (3) ME 75 46-70 ton/h 39000 118.18 75.89 194.07

    FAJA TRANSPORTADORA 18"X5 (3) ME 3 150 ton/h 4000 10.19 4.56 14.75

    COCINA DE ASFALTO 320 gl 2100 1.91 38.68 40.59

    COMPACT.VIB.TIPO PLANCHA 7 160 2.8 19.28 22.08

    COMPRESORA NEUMATICA 87 250-330 PCM 2000 16.12 59.27 75.39

    CORTADORA DE ASFALTO 14.22

    EQUIPO DE SOLDAR 260 AMP 90 10.00EQUIPO MEZCLADOR CEMENTO MODIFICADO 65.00

    ESPARCIDOR DE AGREGADOS 12000 150.00

    FRESADORA 565 421 KW 30000 541.55 460.88 1002.43

    GRUPO ELECTROGENO (2) 230 150 Kw. 2000 8.85 100.08 108.93

    GRUPO ELECTROGENO (2) 116 75 Kw. 1500 5.94 52.36 58.30

    MAQUINA PINTAR PAVIM. 135 57.93

    MEZ. CONCRETO T.TAMBOR (2) 18 11 p3 2200 14.03 9.89 23.92

    MOTOBOMBA (2) 7-10 4" 135 2.56 2.56

    MOTONIVELADORA 125 11515 56.46 73.19 129.65

    MOTONIVELADORA 145-150 13540 69.05 94.57 163.62

    PAVIMENTADORA SOBRE ORUGA 69 10' 12000 50.47 60.34 110.81

    PLANTA ASFALTO EN CALIENTE (*) ME 50 60-115 ton/h 38400 473.57

    RETROEXCAVADORA S/LL 58 1.0 yd3 9000 42.38 58.78 101.16

    RODILLO LISO VIB.AUTOP 101-135 HP 10-12 ton 11100 56.77 85.84 142.61

    RODILLO LISO VIB.MANUAL 10.8 0.8-1.1 ton 800 7.33 14.57 21.90

    RODILLO NEUMATICO AUTOPR. 81-100 5.5-20.0 Tn. 5500 68.43 81.74 150.17

    RODILLO TANDEM ESTATICO 58-70 8.0-10.0 Tn. 8800 83.55 118.32 201.87

    RUTEADORA DE GOLPE 88.50

    SELLADOR (FUNDIDOR/APLICADOR) 153.40

    TRACTOR SOBRE ORUGAS 140-160 HP 14900 170.73 170.17 340.90

    TRACTOR SOBRE ORUGAS 190-240 HP 20520 191.81 193.93 385.74

    TRACTOR DE TIRO 80 HP 4320 14.25 48.82 63.07

    VIBRADOR DE CONCRETO (1) 4 1.5 plg 1.89 1.52 3.41

    ZARANDA VIBRATORIA 4"x6"x14" (3) ME 15 7000 12.4 21.75 34.15

    (1) No incluyen operador

    (2) No incluyen combustibles, lubricantes, filtros ni operador

    (3) No considera la fuente de poder que acciona la unidad.

    (*) Incluye Planta de asfalto, una amasadora, un secador de aridos y dos calentadores de aceites.

    La tarifa horaria incluye los siguientes conceptos:

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    5/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo: Puente Montalvo - Puente Camiara.

    COSTO DE MATERIALES PUESTOS EN OBRA

    FECHA: Julio 2006

    TIPO DE CAMBIO: 3.244

    ADQUISICIONES ADICIONALES O RECARGOS PRECIO

    DESCRIPCION LUGAR UND. PESO/Und P. UNIT. FLETE ALMAC. MERMAS VIAT. TOTAL

    KG S/. S/. 2.00% 5.00% 2.00% S/.

    ACERO CORRUGADO FY=4200 kg/cm2 AREQUIPA kg 1.00 2.13 0.08 0.04 2.25

    ADITIVO MEJORADOR DE ADHERENCIA LIMA kg 1.00 15.75 0.29 0.32 0.79 17.15

    ALAMBRE NEGRO # 8 AREQUIPA kg 1.00 3.28 0.08 0.07 3.43

    ALAMBRE NEGRO # 16 AREQUIPA kg 1.00 3.28 0.08 0.07 3.43

    ASFALTO LIQUIDO MC-30 CONCHAN gl 3.87 6.36 1.07 0.13 0.32 7.88

    ASFALTO SOLIDO PEN 60/70 CONCHAN gl 3.87 4.53 1.07 0.09 0.23 5.92

    BUNKER MOLLENDO gl 4.92 3.53 0.20 0.07 0.18 3.98CAPTAFARO DE GUARDAVA LIMA und 0.30 9.10 0.09 0.18 9.37

    CEMENTO ASFALTICO MODIFICADO CON POLIMERO PARA SAMI(1) LIMA kg 1.00 4.96 0.29 0.10 0.25 5.60

    CEMENTO ASFALTICO MODIFICADO CON POLIMEROS(1)

    LIMA kg 1.00 2.83 0.29 0.06 0.14 3.31

    CEMENTO PORTLAND TIPO I (42.5 kg) AREQUIPA bol 42.50 14.62 3.36 0.29 0.73 19.00

    CLAVOS AREQUIPA kg 1.00 3.28 0.08 0.07 3.43

    AGUA MOQUEGUA m3 1,000.00 3.00 33.00 0.06 36.06

    DETERGENTE MOQUEGUA kg 1.00 5.00 0.03 0.10 0.25 5.38

    DISOLVENTE XL LIMA gl 5.07 31.35 1.44 0.63 1.57 34.99

    EMULSION ASFLTICA CRS-2 LIMA gl 3.79 6.65 1.08 0.13 0.33 8.19

    EMULSION ASFLTICA CSS-1h LIMA gl 3.79 6.65 1.08 0.13 0.33 8.19EMULSION ASFLTICA MODIF.CRS-2P LIMA gl 3.79 7.26 1.08 0.15 0.36 8.85

    FIBRA DE VIDRIO DE 4 mm ACABADO LIMA m2 1.00 153.73 0.29 3.07 157.09

    CAL HIDRATADA AREQUIPA kg 1.00 0.40 0.08 0.01 0.02 0.51

    GAVION TIPO CAJA LIMA m3 1.00 69.52 0.29 1.39 71.20

    GUARDAVIAS LIMA m 11.15 63.02 3.18 1.26 67.46

    LAMINA REFLECTIVA A.I. AMARILLA (24") LIMA p2 0.25 13.05 0.07 0.26 13.38

    LAMINA REFLECTIVA A.I. BLANCA (24") LIMA p2 0.25 13.05 0.07 0.26 13.38

    LAMINA REFLECTIVA A.I. VERDE (24") LIMA p2 0.25 13.05 0.07 0.26 13.38

    LAMINA REFLECTIVA ALTA INTENSIDAD LIMA p2 0.25 13.05 0.07 0.26 13.38

    LIJA LIMA hja 0.05 1.43 0.01 0.03 0.07 1.54

    MADERA TORNILLO LIMA p2 2.12 2.84 0.60 0.06 3.50

    MICROESFERAS DE VIDRIO LIMA kg 1.00 4.50 0.29 0.09 0.23 5.11

    PEGAMENTO EPOXICO (A + B) LIMA gl 5.07 224.25 1.44 4.49 11.21 241.39

    PERNOS 5/8" X 14 " C/T+2A MOQUEGUA und 0.80 7.90 0.03 0.16 8.09

    PERNOS DE 5/16" x 3" CON TUERCA Y ARANDELA MOQUEGUA jgo 0.20 0.90 0.01 0.02 0.93

    PERNOS DE 5/16" x 6" CON TUERCA Y ARANDELA MOQUEGUA jgo 0.35 1.35 0.01 0.03 1.39

    PERNOS PARA GUARDAVIA LIMA jgo 1.30 27.63 0.37 0.55 28.55

    PETROLEO DIESEL MOLLENDO gl 5.07 8.57 0.20 0.17 0.43 9.37

    PINTURA DE TRAFICO LIMA gl 5.07 49.00 1.44 0.98 2.45 53.87

    PINTURA ESMALTE SINTETICO LIMA gl 5.07 26.48 1.44 0.53 1.32 29.77

    PINTURA ESMALTE SINTETICO GRIS LIMA gl 5.07 26.48 1.44 0.53 1.32 29.77

    PINTURA ESMALTE ANTICORROSIVA LIMA gl 5.07 32.37 1.44 0.65 1.62 36.08

    PINTURA IMPRIMANTE LIMA gl 5.07 13.89 1.44 0.28 0.69 16.30

    PLANCHA DE ACERO E=3/8" LIMA kg 1.00 3.78 0.29 0.08 4.15

    PLANCHA DE ACERO E=5/8"x8"X8" LIMA und 5.11 17.05 1.46 0.34 18.85

    PLANCHA DE ACERO E=3/16" LIMA m2 37.15 110.18 10.59 2.20 122.97

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    6/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo Puente Montalvo Puente Camiara

    DISTANCIA MEDIA DE TRANSPORTE

    PARA SU USO EN MATERIALES GRANULARES Y CONCRETOS

    INFLUENCIA C.G.

    UBICACINACCESO

    (Km)DESDE HASTA LONG. KM M-K

    1139 + 795 0.10 1139 + 795 1139 + 795 0.100

    1139 + 795 1176 + 398 36602.50 18.401 673522.60

    1213 + 000 0.10 1176 + 398 1213 + 000 36602.50 18.401 673522.60

    1213 + 000 1213 + 050 50.00 0.125 6.25

    TOTALES 73255.00 1347051.46

    18.39

    DISTANCIA MEDIA DE TRANSPORTE 18.40

    PARA SU USO EN MEZLAS CON EMULSIONES

    700.A 700.BUnd Metrado 1 Km

    Agua en base estabilizada(1)

    m3 96.69 96.69 3592.36

    38.15

    DISTANCIA MEDIA DE TRANSPORTE 38.20

    (1) SE CONSIDERO ESTA ACTIVIDAD POR SER LA MAS INFLUYENTE EN LA DUSTANCIA. EL METRADO ES FUNCION AL VOLUMEN UTILIZADO

    2% DEL VOL. DE LA MEZCLA

    3689.05

    CALCULO DE DISTANCIA MEDIA DE TRANSPORTE DE AGUA

    FUENTE DE AGUA

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    7/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo Puente Montalvo Puente Camiara

    DISTANCIA MEDIA DE TRANSPORTE

    INFLUENCIA

    UBICACIN ACCESO DESDE HASTA LONG.

    1140 + 000 4.00 1139 + 795 1140 + 000 205.00

    1140 + 000 1170 + 749 30749.25

    1201 + 500 2.50 1170 + 749 1201 + 500 30750.75

    1201 + 500 1213 + 050 11550.00

    TOTALES 73255.00

    AGREGADOS PARA CONCRETOS Y RELLENOS

    INFLUENCIA C.G.

    UBICACIN ACCESODESDE HASTA LONG. KM M-K

    1140 + 000 4.00 1139 + 795 1140 + 000 205.00 4.103 841.12

    1140 + 000 1170 + 749 30749.25 19.375 595766.72

    1201 + 500 2.50 1170 + 749 1201 + 500 30750.75 17.875 549669.66

    1201 + 500 1213 + 050 11550.00 8.275 95576.25

    TOTALES 73255.00 1241853.74

    DISTANCIA MEDIA DE TRANSPORTE 16.95

    BASE GRANULAR PARA PARCHADOS

    DESCRIPCION Vol

    (m3) 1 Km

    CANTERA

    ZONA DE INFLUENCIA DE AGREGADOS PARA

    BASES GRANULARES, CONCRETO DE CEMENTO PORTLAND,

    TRATAMIENTO SUPERFICIALES, RELLENOS

    C.G.

    TRANSPORTE

    CANTERA

    CALCULO DE DISTANCIA MEDIA DE TRANSPORTE DE

    8.275

    KM

    4.103

    19.375

    17.875

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    8/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo Puente Montalvo - Puente Camiara

    DISTRIBUCION DE MEZCLA DE LA PLANTA DE ASFALTO

    INFLUENCIA

    UBICACIN ACCESO DESDE HASTA LONG.

    1201 + 500 2.50 1139 + 795 1201 + 500 61705.00

    1201 + 500 1213 + 050 11550.00

    LONGITUD DEL TRAMO (m) 73255.00

    DESCRIPCION Vol

    (m3) 1 Km

    PARCHADO PROFUNDO(1)

    10.00 10.00 413.25

    PARCHADO SUPERFICIAL(2)

    324.2868 324.2868 10753.74

    334.2868

    34.41

    DIST MEDIA 34.50(1),(2) Ver sustento de metrados de pavimentos

    DISTANCIA MEDIA DE TRANSPORTE

    CANTERA

    TRANSPORTE

    11501.2768

    CALCULO DE DISTANCIA MEDIA DE TRANSPORTE DE MEZCLA ASFALTICA PARA PARCHADOS

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    9/11

    stu io e initivo para e antenimiento erio ico e a arretera anamericana urramo uente onta vo - uente amiara

    DISTANCIA MEDIA DE TRANSPORTE

    CALCULO DE DISTANCIA MEDIA DE TRANSPORTE DE PIEDRA MEDIANA Y GRANDEPARA CONCRETO CICLOPEOS

    INFLUENCIA C.G.UBICACIN ACCESO DESDE HASTA LONG. KM M-K

    1139 + 795(1)

    0.10 1139 + 795 1139 + 795 0.00 0.100 0.00

    1139 + 795 1170 + 649 30853.70 15.527 479065.40

    1201 + 500 2.50 1170 + 649 1201 + 500 30851.30 17.926 553040.40

    1201 + 500 1207 + 249 5748.80 5.374 30894.05

    1213 + 000(2)

    0.10 1207 + 249 1213 + 000 5751.20 2.976 17115.57

    1213 + 000 1213 + 050 50.00 0.125 6.25

    TOTALES 73255.00 1080121.68

    DISTANCIA MEDIA DE TRANSPORTE 14.74(1) La fuente de agregados proviene del rio Moquegua

    (2) La fuente de agregados proviene del rio Locumba

    CALCULO DE DISTANCIA MEDIA DE TRANSPORTE DE PIEDRA MEDIANAPARA GAVIONES

    DESCRIPCION Vol

    (m3) 1 KmPROTECCION EROSION DE BERMAS

    (3)80 80 774

    80 854

    DIST MEDIA 10.68(3) Ver sustento de metrados . La fuente de agregados proviene del rio Moquegua

    FUENTE DE AGREGADOS

    TRANSPORTE

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    10/11

    stu io e initivo para e antenimiento erio ico e a arretera anamericana urramo uente onta vo - uente amiara

    DISTANCIA MEDIA DE TRANSPORTE

    CALCULO DE DISTANCIA MEDIA DE ELIMINACION A BOTADERO

    INFLUENCIA C.G.

    UBICACINACCESO

    (Km)DESDE HASTA

    LONG.(M)

    KMM-K

    1159 + 500 0.05 1139 + 795 1159 + 500 19705.00 9.903 195138.62

    1159 + 500 1160 + 250 750.00 0.425 318.75

    1161 + 000 0.05 1160 + 250 1161 + 000 750.00 0.425 318.75

    1161 + 000 1162 + 250 1250.00 0.675 843.75

    1163 + 500 0.05 1162 + 250 1163 + 500 1250.00 0.675 843.75

    1163 + 500 1164 + 400 900.00 0.500 450.00

    1165 + 300 0.05 1164 + 400 1165 + 300 900.00 0.500 450.00

    1165 + 300 1166 + 350 1050.00 0.575 603.75

    1167 + 400 0.05 1166 + 350 1167 + 400 1050.00 0.575 603.75

    1167 + 400 1213 + 050 45650.00 22.875 1044243.75

    TOTALES 73255.00 1243814.865

    16.98

    DISTANCIA MEDIA DE TRANSPORTE 17.00

    BOTADERO

  • 7/28/2019 04.00 Calculo de Movilizacion y Transporte de Material

    11/11

    Estudio Definitivo para el Mantenimiento Periodico de la Carretera Panamericana Sur

    Tramo Puente Montalvo - Puente Camiara

    RENDIMIENTOS DE TRANSPORTE

    MATERIAL Y MATERIAL Y TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE TRANSPORTE

    BASES DE CALCULO UND ELIMINACION ELIMINACION AGUA/OBRA AGUA/OBRA INTERNO MEZCLA.ASFAL. MEZCLA.ASF AL . MEZCLA.ASFAL. AGREG.PARA PIEDRA MEDIANA

    (AGUA INSUMO (EN CANTERA) P/PARCHADO

    HASTA 1 KM DESPUES 1 KM P/EMULSIONES) HASTA 1 KM DESPUES 1 KM (P/GAVIONES) (P/CONC.CICLO.)

    DISTANCIA MEDIA PONDERADA Km. 1.00 1.00 18.40 38.20 0.20 1.00 1.00 34.50 16.60 10.68 14.74 17.00

    VELOCIDAD CARGADO Km/Hr. 30 35 30 30 20 30 40 35 35 35 35 35

    VELOCIDAD DESCARGADO Km/Hr. 40 50 50 50 30 40 50 45 45 45 45 45

    TIEMPO CARGA Y DESCARGA Min. 6.79 30 30 6.79 20 20 6.79 6.79 6.79 6.79

    TIEMPO RECORRIDO CARGADO Form. 60 d / 30 60 d / 35 60 d / 30 60 d / 30 60 d / 20 60 d / 30 60 d / 40 60 d / 35 60 d / 35 60 d / 35 60 d / 35 60 d / 35

    TIEMPO RECORRIDO DESCARGADO Form. 60 d / 40 60 d / 50 60 d / 50 60 d / 50 60 d / 30 60 d / 40 60 d / 50 60 d / 45 60 d / 45 60 d / 45 60 d / 45 60 d / 45

    TIEMPO RECORRIDO Min. 3.50 2.91 3.20 3.20 5.00 3.50 2.70 3.05 3.05 3.05 3.05 3.05

    CICLO Form. 6.79 + 3.50d 0.00 + 2.91d 30.00 + 3.20d 30.00 + 3.20d 6.79 + 5.00d 20.00 + 3.50d 0.00 + 2.70d 20.00 + 3.05d 6.79 + 3.05d 6.79 + 3.05d 6.79 + 3.05d 6.79 + 3.05d

    CICLO Min. 10.29 2.91 88.88 152.24 7.79 23.50 2.70 125.14 57.38 39.32 51.73 58.60

    TIEMPO TRABAJADO POR DIA Min. 480 480 480 480 480 480 480 480 480 480 480 480

    EFICIENCIA % 90.00% 90.00% 90.00% 90.00% 90.00% 75.00% 75.00% 75.00% 90.00% 90.00% 90.00% 90.00%

    TIEMPO UTIL TRABAJADO Min. 432 432 432 432 432 360 360 360 432 432 432 432

    VOLUMEN DEL VOLQUETE M3. 15 15 15 15 15 15 15 15 15 15

    VOLUMEN DEL CAMION CISTERNA Gln. 2,000.00 2,000.00

    NUMERO DE VIAJES AL DIA Un. 42 148 5 3 55 15 133 3 8 11 8 7VOLUMEN TRANSPORTADO POR DIA M3. 630 2220 38 23 825 225 1995 45 120 165 120 105

    ESPONJAMIENTO 1.20 1.20 1.00 1.25 1.25 1.25 1.00 1.00 1.00 1.20

    RENDIMIENTO m3/dia 525 1,850 38 23 825 180 1,596 36 120 165 120 88

    (P/CONCR./BASE/R

    ELL.)

    CONCRE/BASE/RELLE

    NO/OBRA

    PIEDRA

    MEDIANA/GRANDE A

    OBRA

    MAT./BOTADERO