04. estimating, gantt chart and s-curve preperation
TRANSCRIPT
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
1/26
ESTIMATING, GANTT CHART
AND
S-CURVE PREPARATION
RAMON RELLITA TAN, CE, MPM
Asst. City Engineer
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
2/26
A)
ESTIMATING:
Estimating is a calculation of the quantities of variousitems of work, and the expenses likely to be incurred thereon.The total of these probable expenses to be incurred on the
work is known as estimated cost of the work. The estimatedcost of a work is a close approximation of its actual cost. Theagreement of the estimated cost with the actual cost willdepend on accurate use of estimating methods and correctvisualization of the work, as it will be done. Importance ofcorrect estimating is obvious. Under-estimating may result in
the client getting an unpleasant shock when tenders areopened and drastically modifying or abandoning the work atthat stage. Over-estimating may lose the engineer orestimator his client or his job, or in any case his confidence.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
3/26
PURPOSE OF ESTIMATING:
Thepurpose of estimating is to give a reasonablyaccurate idea of the cost. An estimate isnecessary to give the owner a reasonablyaccurate idea of the cost to help him decidewhether the work can be undertaken as
proposed or needs to be curtailed or abandoned,depending upon the availability of funds andprospective direct and indirect benefits.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
4/26
TYPES OF CONSTRUCTION
ESTIMATES:
There are several kinds of estimating techniques;these can be grouped into two main categories.
1. APPROXIMATE ESTIMATES
2. DETAILED ESTIMATES
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
5/26
APPROXIMATE ESTIMATES
An approximate estimate is an approximate orrough estimate prepared to obtain anapproximate cost in a short time. For certainpurposes the use of such methods is justified.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
6/26
DETAILED ESTIMATES
A detailed estimate of the cost of a project isprepared by determining the quantities and costs of
every thing that a contractor is required to provideand do for the satisfactory completion of the work. Itis the best and most reliable form of estimate.
Detailed Estimate of Construction Cost a forecastof construction cost prepared on the basis of adetailed analysis of materials and labor for all itemsof work, as contracted with an estimate based oncurrent area, volume or similar unit cost.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
7/26
QUALIFICATIONS OF AN ESTIMATOR
A good estimator should possess the following qualifications:
1. A thorough understanding of architectural drawings.2. A sound knowledge of building materials, construction
methods and customs prevailing in the trade.3. A full of information collected or gained through
experience in construction work, relating to materialsrequired, hourly output of workers and equipments,
overhead expenses and costs of all kinds.4. An understanding of a good method of preparing anestimate.
5. A systematic and orderly mind.6. Ability to collect, classify and evaluate data that would be
useful in estimating.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
8/26
IMPORTANT ITEMS TO BE CONSIDEREDIN ESTIMATING:
MATERIALS:
LABOR:
EQUIPMENT:
TIME:
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
9/26
MATERIALS:
From the estimate of a work it is possible todetermine what materials and in what quantitieswill be required for the work so that thearrangements to procure them can be made.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
10/26
LABOR:
The number and kind of workers of differentcategories who will have to be employed tocomplete the work in the specified time can befound out from the estimate.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
11/26
EQUIPMENT:
An estimate will help in determining amountand kind of equipment needed to complete thework.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
12/26
TIME:
The estimate of a work and the past experienceenable one to estimate quite closely the length oftime required to complete an item of work or thework as a whole.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
13/26
DOCUMENTS REQUIRED INESTIMATING
Architectural Plans
Specifications (separate for building)
Red Book (specification for Roads and Bridges)
National Building code
City/Municipal Ordinance
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
14/26
COST INVOLVED IN ESTIMATINGA-Direct Costs (for Building) B-Direct Costs (for Roads)
a. Mobilization a. Mobilizationb. Site Preparation b. Clearing and Grubbingc. Layout c. Roadway Excavationd. Earthworks (excavation & backfill) d. Embankmente. Structural Works e. Line Ditch
f. Architectural Finishes f. Sub-Base Courseg. Plumbing Works g. Base Courseh. Electrical Works h. Slope Protectioni. Mechanical Works
Indirect Costsa. Contingencies
b. Engineering Supervisionc. Contractors Profitd. Vate. City Tax
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
15/26
B)
GANTT CHART
AGantt Chart is a type of bar chart thatillustrates a project schedule. Gantt charts
illustrate the start and finish dates of theterminal elements and summary elements of aproject. Terminal elements and summary
elements comprise the work breakdownstructure of the project.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
16/26
The Bar Chart is derived from the Gantt Chart.It represents a graphic record of the projects
progress. It gives detail of the work along withthe time schedules from the beginning date tothe completion date of each activity. Thus, itshows the day-to-day status of every activity, the
comparison between the actual accomplishmentand the corresponding work schedules, anddistribution of manpower, materials, equipmentand cash flow.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
17/26
The Bar Chart has the distinct character ofbeing easily understood by non-technical people.
However, its simplicity becomes its weakness asa control tool because it lacksthe detailedbreakdown of the different activities particularly
their proper and operational dependencies. Thisbuilt-in weakness prevents the Bar Chart frombeing a fully effective updating instrument.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
18/26
C)
S-CURVE
An S-Curve is a well known projectmanagement tool and it consists in a display of
cumulative costs, labor hours or other quantitiesplotted against time. The name derives from theS-like shape of the curve, flatter at the beginning
and end and steeper in the middle, because thisis the way most of the projects look like.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
19/26
An S-Curve represents the actual workaccomplishment as against the work schedule,
visually identified with a sloping line originatingfrom the bottom left zero percent (0%)accomplishing going up to the upper right, 100%
accomplishment.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
20/26
Looking at the S-Curve line the reader canreadily see the project status at a given time
whether it is ahead of or behind schedule. Anupdated S-Curve immediately presents thepositive and negative variance ofaccomplishment and as such the timely remedialmeasures can be applied.
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
21/26
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
22/26
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
23/26
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
24/26
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
25/26
-
7/29/2019 04. Estimating, Gantt chart and S-Curve Preperation
26/26
GOOD AFTERNOON
THANK YOU