4/28/16 10:47 AM Page 1 of 2 MGM SPRINGFIELD CONSTRUCTION ACTIVITIES - 04/26/16-05/10/16 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected] FULL CONSTRUCTION BUILD OUT ZONE LOCATION STATUS 1 95 and 101 State Street Interior demolition is ongoing. Load testing inside the building is underway. 2 Hotel Backfilling Edisonia basement. Exterior abatement at Union Chandler is underway. 3 Casino Bracing the façade of 73 State Street 4 Da Vinci Park No work anticipated 5 Dave's Furniture No work anticipated 6 Armory Demolition of the rear portion anticipated to begin the week of May 2nd. 7 Plaza Loading out demolition debris from former YWCA Building is underway 8 Church Church building has been relocated to Union St. New foundation installation is anticipated to begin the week of May 2nd. 9 Entertainment No work anticipated 10 Parking Garage Site clearing and dust monitoring is underway. Bulk excavation is underway. Some noise and vibration should be anticipated throughout this process. Dust control measures will be implemented as necessary. 11 Support Area No work anticipated 12 MGM Way No work anticipated STREET WORK State Street No work anticipated Main Street No work anticipated

Upload: others

Post on 20-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 04-26-16 Weekly Construction Activities - MGM Springfield€¦ · MGM SPRINGFIELD CONSTRUCTION ACTIVITIES - 04/26/16-05/10/16 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED

4/28/16  10:47  AM Page  1  of  2

MGM SPRINGFIELD CONSTRUCTION ACTIVITIES - 04/26/16-05/10/16

WORK HOURS: 7:00 AM - 7:00 PM

FOR CONSTRUCTION-RELATED INQUIRES PLEASE CONTACT: [email protected]

FULL CONSTRUCTION BUILD OUT

ZONE LOCATION STATUS

1 95 and 101 State Street Interior demolition is ongoing. Load testing inside the building is underway.

2 Hotel Backfilling Edisonia basement. Exterior abatement at Union Chandler is underway.

3 Casino Bracing the façade of 73 State Street

4 Da Vinci Park No work anticipated

5 Dave's Furniture No work anticipated

6 Armory Demolition of the rear portion anticipated to begin the week of May 2nd.

7 Plaza Loading out demolition debris from former YWCA Building is underway

8 Church Church building has been relocated to Union St. New foundation installation is anticipated to begin the week of May 2nd.

9 Entertainment No work anticipated

10 Parking Garage Site clearing and dust monitoring is underway. Bulk excavation is underway. Some noise and vibration should be anticipated throughout this process. Dust control measures will be implemented as necessary.

11 Support Area No work anticipated

12 MGM Way No work anticipated

STREET WORK

State Street No work anticipated

Main Street No work anticipated

Page 2: 04-26-16 Weekly Construction Activities - MGM Springfield€¦ · MGM SPRINGFIELD CONSTRUCTION ACTIVITIES - 04/26/16-05/10/16 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED

4/28/16  10:47  AM Page  2  of  2

Union StreetInstallation of isolation valves anticipated to begin week of May 2nd. The road will be closed to thru traffic while this work is being performed. A police detail is anticipated. Access to Milano's parking lot and Pride Gas Station will be maintained throughout the process. Work on Union Street is anticipated to continue through Friday May 6th and could extend into the week of May 9th.

East Columbus Avenue No work anticipated

Bliss Street No work anticipated

Howard Street Turn Around No work anticipated

Howard Street Installation of new water main is underway.

UTILITY ACTIVITY

UTILITY PROVIDER WORK TO BE PERFORMED

Eversource No work anticipated

Verizon No work anticipated

Comcast No work anticipated

Columbia Gas No work anticipated

Springfield Water & Sewer Springfield Water and Sewer will be conducting work along Main Street from State Street to Union Street. Please note that this work is unrelated to the MGM Springfield project.

MISCELANEOUS ACTIVITY

LOCATION WORK TO BE PERFORMED

MGM Springfield Site Soil removal work is underway.

Page 3: 04-26-16 Weekly Construction Activities - MGM Springfield€¦ · MGM SPRINGFIELD CONSTRUCTION ACTIVITIES - 04/26/16-05/10/16 WORK HOURS: 7:00 AM - 7:00 PM FOR CONSTRUCTION-RELATED

MAIN STREET

STAT

E ST

REET

EAST COLUMBUS AVENUE

BLIS

S ST

REET

UNIO

N ST

REET

HOW

ARD

TURN

ARO

UND

195/101 STATE

2HOTEL

3CASINO

12MGM WAY

7PLAZA

6ARMORY

8CHURCH

5DAVE’S

FURNITURE

4DA VINCI

PARK

9ENTERTAINMENT

10PARKING GARAGE

11SUPPORT

AREA

HOW

ARD

STRE

ET

VALVE INSTALLATION MAY CAUSE STREET CLOSURE THROUGHFRIDAY MAY 6 AND COULD EXTEND INTO THE WEEK OF MAY 9. POLICE DETAIL ANTICIPATED.

STREET CLOSED FOR WATER MAIN WORK THROUGH MAY 6.