0 development & financing of pv power plants & key issues in the off-grid/ hybrid sector
TRANSCRIPT
1
Development & Financing of PV Power Plants & Key Issues in the Off-Grid/
Hybrid Sector
Conergy at a glanceA
Financing of PV Systems & Issues in Hybrid SystemsB
3
Conergy has a wide experience in all downstream sales channels; diversified sales approach is key to balance risks
Conergy‘s downstream business
INDUSTRIAL (free-field)COMMERCIAL (roof-top)RESIDENTIAL
< 50 kWp 1) Large > ~ 200 kWp 1) > ~ 500 kWp 1) Small 50 ~ 200 kWp 1)
Indirect sale to wholesale EPC
(Engineering / procurement / construction of PV installations)
PD, Financing, EPC(Development / financing / EPC of
large PV power plants)
B2B PROJECTS
SA
LE
S C
HA
NN
EL
SM
AR
KE
T S
EG
ME
NT
SA
Source: Conergy 1) Indicative dimensions
Direct sale to installers and sollateurs
4
Conergy has a longstanding experience in Asia and Middle East
Overview of markets in APAC served by Conergy
Source: Conergy
Middle East
Countries with own CGY-entity
Countries with EPC business driven by Singapore
APAC & Middle East markets
REMARKS
Singapore
| Presence in Asia Pacific and Middle East markets since 2005
| Teams with global experience and local knowledge
| Regional Headquarters in Singapore serving surrounding markets – regional engineering center of excellence
| Offices in Australia, India, UAE, Thailand
| Strategic partners in Thailand, Indonesia, Malaysia, the Philippines and Saudi-Arabia
| Market entry in Japan currently in execution – own entity expected in H1/2013
A
5
AConergy offers high-quality solar systems and an all-round carefree service package for all sales channels from a single source
Solutio
Conergy‘s solution portfolio
Based on more than 14 years of solar experience and its in-depth expertise as a former system manufacturer ....
l .... Conergy integrates high-quality components and comprehensive services to all-round carefree solar system solutions
l .... Conergy’s sales force has the expertise in all components, such as modules, inverters, mounting systems, cables and electrical parts
l .... Conergy has the competence to ensure its high quality standards by strict quality management along the entire value chain
SYSTEM COMPETENCE
HIGH YIELD DURABLE SECURE SIMPLESource: Conergy
6
In general, Conergy operates in a proven consortium approach with selected strategic partners
Conergy – Local Partner Consortium
Consortium Member
General role in project
Tasks
Engineering Engineering Procurement ConstructionProcurement
PROJECT ENGINEERING PROJECT MANAGEMENT
• Overall conceptual design• Overall mechanical and electrical
design
• Main components supply
• Commissioning support
• Warranties
• Local civil design• Local mechanical design• Local electrical design
• Local components supply
• Installation • Commissioning
• O&M
A
Local Partner
Conergy at a glanceA
Financing of PV Systems & Issues in Hybrid SystemsB
8
PV Projects have the advantage to be comparable to financial products as they are straight forward on a technological perspective
Main characteristics of PV projects
Reliable
| Technology is simple and passive
| Maintenance is light
| Module life time 25 years
Predictable
| Sunlight is stable through the years
| Energy yield are predictable and Regular
| Output directly linked to quality of modules / inverters
| O&M costs are stable
Safe
| Returns are known well in advance
| Economical reality does not vary too much from simulations
9
Through the eyes of Finance a project is Risk Management
Overview of project development framework
ENVIRONMENT“Framework”
TECHNOLOGY“Know-how”
PLAYERS“human factor”
PROJECT
FINANCE
| Social Need
| Political framework
| Geological conditions
| Yield check
| Technical feasibility
| Technical/site risks
| Promoters
| Technology suppliers
| Investors
| Banks
Land + Rights
Project development
| Mitigate the risks of a project by
| Proper project documentation
| Scenario Analysis
| EPC Guarantees
10
Each partner in a project has a different goal..
EPC Margin (10 to 15%)
Loan Interests (6 to 10%)
Dividends (15%)
Sweat equity/Development Margin (15%)
Annual returns
Annual returns
One shot profits
One shot profits
EACH ACTOR HAS A DIFFERENT EXIT STRATEGY
IN MIND
Project stakeholders and their goals
Project
Project Promoter
Equity Investor
Money lender
EPC contractor
11
Typical Finance Cycle of commercial PV Systems
Exit by trade sale to long term equity investorswith lower IRR expectations (8 to 10%) :| Utilities| Pension funds
Financial close
Preferred exit option
Short term equity investors withEquity IRR expectations around 14% :| Development banks (label+equity)| Hedge/Innovation funds (equity)| Industrial partners (exit strategy offer)
Joint Venture development(SSA, SHA)
Project construction
Exit by sector IPO
Equity Partner search
Promoters+
Initial Investors
Cash bring as Equity Injection into New/future
project pipeline
x
12
| PPAS Capacity of local institutions to honor PPAs
| PPAs duration and renegotiation risk
| Land lease risks
For an investor a bad project is a project showing him shadow areas and risks with no answers, no mitigations …
Overview Project risks
PROJECT INTERNAL RISKSTECHNOLOGY RISK
| Clear shareholding structure of SPV with clear leadership Clear ownership rights
| One Majority shareholder mastering with track record
| Clear exit strategies
| Potential delays in EPC| Previous References project implementation
(Shareholders/EPC) in the country| Degradation factor of modules (generation)
over the years| Efficiency of components (Modules Inverters)| Guarantees on performance/yields| O& M issues
| Political stability and energy framework
| Project geological location| Project administrative environment
PARTNERSHIP RISKENVIRONMENT RISK
13
| Potential delays in EPC| Previous References project implementation
(Shareholders/EPC) in the country| Degradation factor of modules (generation)
over the years| Efficiency of components (Modules Inverters)| Guarantees on performance/yields| O& M issues
| Political stability and energy framework
| Project geological location| Project administrative
environment
| PPAS Capacity of local institutions to honor PPAs
| PPAs duration and renegotiation risk
| Land lease risks
For an investor a bad project is a project showing him shadow areas and risks with no answers, no mitigations …
Overview Project risks
PROJECT INTERNAL RISKSTECHNOLOGY RISK
| Clear shareholding structure of SPV with clear leadership Clear ownership rights
| One Majority shareholder mastering with track record
| Clear exit strategiesPARTNERSHIP RISKENVIRONMENT RISK
14
Overall private sector investments have the opportunity to bring efficiency and competition to the Off-Grid/ Hybrid Sector
Key points of concern for private investors
Some of the concerns can be addressed by the
Government while education play a key role and can be driven by the
private sector
A No sovereign guarantees to counter bankability issue
B Often remote access raises questions on O&M
C Difficulties to pool projects in order to attract equity
D Smaller systems difficult to debt-finance
E Wider span in quality/ reliability compared to PV PP
F Lack of education on RE in Off-grid markets