© webber wentzel 2013 eskom csp / solar augmentation conference the epc and o&m...

23
© Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

Upload: rachel-duling

Post on 02-Apr-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

© Webber Wentzel 2013

ESKOM CSP / SOLAR AUGMENTATION CONFERENCE

THE EPC AND O&M CONTRACTOR'S PERSPECTIVE

26 August 2013

Alessandra Pardini

Page 2: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

GLOBAL CSPCSP around the World

Page 3: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

GLOBAL CSP

• Global CSP up to January 2013 (figures include ISCC and ISCoal)o Total installed CSP: 2553 MWo Total installed CSP (2012): 811.5 MW - 31.8 % of total

o Total installed CSP prior to 2006: 354 MWo Total installed CSP (2006 - 2012): 2199 MW

o Total installed CSP in USA: 506 MW - 19.8 % of totalo Total installed CSP in USA (2012): 0 MW

o Total installed CSP in Spain: 1954 MW - 76.5 % of totalo Total installed CSP in Spain 2012: 802.5 MW - 100 % of total

(source: CSP World)3

Page 4: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

GLOBAL CSP

Projects:• Largest single operational project (parabolic trough):

o 100 MW Shams 1 in Abu Dabio Companies: Abengoa Solar, Masdar and Totalo EPC: Abener, Abengoa, Teymao O&M: Abengoa Solar

• Largest single operational project (central receiver):o 29 MW Coalinga in California: Chevrono Company: Chevrono Project developer: BrightSource Energy

4

Page 5: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

• Largest under construction:o 377 MW (central receiver) Ivanpah SEGS in Primm, Californiao Companies: BrightSource Energy, Google, NRG Energyo EPC: Bechtel Engineeringo O&M: NRG Energy

• Largest CSP facility:o Total of 354 MW SEGS - Solar Energy Generating System (parabolic

trough)o Consisting of 9 individual plants in 3 locationso Installed capacity of 14 MW (SEGS I) up to 80 MW (SEGS VIII and IX)o Developer: Luz Industries (now BrightSource Energy)o Current owners: Cogentrix (SEGS I and II), NextEra Energy Resources

(SEGS III – IX)5

Page 6: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

SOUTH AFRICACSP locally

Page 7: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Background on REIPPo Integrated Resources Plan for Electricity 2010 – 2030 (IRP 2010)

recognises the need for new generation capacity to ensure the continued uninterrupted supply of electricity to South Africa.

o Pursuant to this, the Department of Energy issued the First Determination, on 1 August 2011. This allocated 3725 MW to be procured, spread across various forms of renewable energy. The Second Determination, on 12 December 2012, allocated a further 3200 MW across these technologies.

o The allocated amounts broadly align with the capacity allocated in terms of IRP (Integrated Resources Plan) 2010.

o The Renewable Energy Independent Power Production procurement programme gives effect to the First and Second Determinations (REIPP). The REIPP programme is run by the Department of Energy, and the energy generated is purchased by Eskom.

7

Page 8: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Background continued…o The REIPP RFP contemplates that renewable energy will be procured in a

series of "Bid Windows". For each window, competitive Bids are submitted and Preferred Bidders are appointed thereafter.

o So far, Rounds 1 and 2 have been concluded, with most Round 1 projects under construction, and Round 2 projects in the late developmental stages.

o In terms of the First and Second Determinations, CSP was allocated 200 MW, followed by 400 MW, respectively. 150 MW of CSP was awarded in Round 1, with a further 50 MW awarded in Round 2.

8

Page 9: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Projects in South Africa - Operational demonstration and pilot plants

• BBEnergy Liner Fresnel demo plant: 0.08 MWo Operation start date: November 2010

• BBEnergy Eskom Fresnel pilot plant: 0.15 MWo Operation start date: January 2013

9

Page 10: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Under construction:o Kaxu Solar One: 100 MW parabolic trough (1st REIPP Bid Window)

• Developer: Abengoa, IDC• EPC: Abener, Teyma• O&M: Abengoa Solar

10

Page 11: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Under constructiono Khi Solar One: 50 MW central receiver (1st REIPP Bid Window)

• Developer: Abengoa, IDC• EPC: Abener, Teyma• O&M: Abengoa Solar

11

Page 12: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Under construction (as of August 2013)o Bokpoort: 50 MW parabolic trough (2nd REIPP Bid Window)

• Developer: Acwa Power International• EPC: Acciona Energia, SENER, TSK• O&M: Nomac, Investment in Africa Energy Services

12

Page 13: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• Planned:o Eskom CSP Plant: 100 MW central receiver (Webber Wentzel)

• Finance: World Bank, Clean Technology Fund, African Development Bank, Agence Française de Develop

• Engineering and Project Management: Tractebel Engineering (GDF-Suez), Astrom Technical Advisors, PD Naidoo & Associates

13

(source: www.tractabel-engineering-gdfsuez.com)

Page 14: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• REIPP Round 3:o For Round 3, 200 MW allocated to CSP.o Webber Wentzel has been involved in one CSP project in Round 3 -

Abengoa 100 MW CSP.o Another likely Round 3 project - Mestimatala 50 MW CLFR (Linear

Fresnel) is "Ready for Bidding" (source: amplesolar.com)o GDF-Suez has also submitted a CSP bid for Round 3

14

Page 15: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

CSP IN SOUTH AFRICA

• CSP Plants in South Africa (map data source: AfriGIS (Pty) Ltd)

15

Blue operational

Yellow construction

Green development / planned

Bokpoort is also now under construction

Page 16: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

EPC CONTRACTORSREIPP and EPC

Page 17: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

EPC CONTRACTORS IN REIPP?

• The EPC Contractors in REIPP are typically international firms. The international firms that have been involved in South Africa in the CSP sphere thus far are:

o GDF-Suez S.A. - French multinational electric utility company, headquartered in Paris which operates in the fields of electricity generation and distribution, natural gas and renewable energy:• involved in the Eskom CSP Project via Tractebel Engineering.

17

Page 18: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

EPC CONTRACTORS IN REIPP?

o Abengoa - Spanish multinational corporation, which includes companies in the domains of energy, telecommunications, transportation, and the environment; Abengoa Solar, a subsidiary, is focussed on design, financing and construction / operation of PV and CSP projects:• Involved in the Khi and Kaxu CSP projects locally, and construction of

the operational Shams 1 (100 MW) parabolic trough plant, discussed above.

• Involved in EPC for the first commercial central receiver (solar power tower) CSP plant, PS10 Solar Power Plant (11 MW) in Seville, Spain in 2007.

o Acciona Energia - Spanish company based in Madrid, subsidiary of Acciona, involved in developing renewable energy projects, including small hydro, biomass, solar energy and thermal energy, and the marketing of biofuels.

o Involved in several Round 2 projects - Bokpoort (50 MW CSP). 18

Page 19: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

KEY ISSUES – EPC (REIPP)Key issues for EPC Contractors in terms of REIPP

Delay damages Should be be capped? Conservative approach of SA banks has

required this to be capped at 15 %

Performance damages Similarly capped at 15 %

Defects liability With 24 months being acceptable, banks have requested d / p's

(independent of warranties) to be 5 years

Limitation of liability 100 %

Exclusion from limitation of liability Confidentiality

Corrupt Acts

Economic Development Obligations

Indemnities (IP)

Third party liability

Performance bond 10 – 20 %

Advance payment Very common for cash flow requirements

Retention Takes the form of a warranty bond for the defects liability period

Direct agreements with lenders Required by SA banks, with additional warranties, step-in rights and

subordination provisions

Pass through obligations (PPA, IA) and

equivalent project relief

These have been contentiously debated

19

Page 20: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

O&M CONTRACTORSO&M and REIPP

Page 21: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

KEY ISSUES – O&M (REIPP)

Key issues for O&M Contractors in terms of REIPP

Performance damages For availability in certain circumstances

Limitation of liability 200 %

Exclusion from limitation of liability Confidentiality

Corrupt Acts

Economic Development Obligations

Indemnities (IP)

Third party liability

Performance bond 100 % to 150 %

Direct agreements with lenders Yes

Pass through obligations (PPA, IA) and

equivalent project relief

These have been contentiously debated

21

Page 22: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

22

WEBBER WENTZEL

• Alessandra Pardini+27 11 530 5007 / 5244+27 82 978 [email protected]

THANK YOU

Page 23: © Webber Wentzel 2013 ESKOM CSP / SOLAR AUGMENTATION CONFERENCE THE EPC AND O&M CONTRACTOR'S PERSPECTIVE 26 August 2013 Alessandra Pardini

www.webberwentzel.com

JOHANNESBURG CAPE TOWN

10, 16 & 18 Fricker Road, 15th Floor, Convention Tower

Illovo Boulevard, Heerengracht, Foreshore

Johannesburg, 2196, South Africa Cape Town, 8001, South Africa

T +27 11 530 5000 T +27 21 431 7000

Legal Notice: these materials are for training purposes only and do not constitute legal or other professional advice