( Turnkey )Projects Constructed By Kahromika Major  

Project Name Customer Name Comp. Date And

Construction Period

Main Contractors

Kafr El Dawaar Power Station a- First Stage 2 units *110 MW b- Second Stage Another 2 Units * 110MW

EEA ( Electrical Egyptian Authority )

1978, 44 months 1982, 36 months

Consortium with SKODA

Cairo West Power Station. ( Four units * 87.5 MW Babcock Wilcox & Westinghouse )

EEA 1978 Babcock Wilcox & Westinghouse

Extention Of Talkha Power Station - 2 Units * 210 MW

EEA 1989,38 months Consortium With Skoda.

Instullation of Boilers Of Unit 5 & 6 Of Cairo West Power Station.

EEA 1992 , 21 months Sae-Sadelmi

Installation Boiler of Unit no,2 of Assuit Power Station

EEA 1994, 14 months Sae-Sadelmi

Boiler Installation of Unit, 5Of Abu quer Power Station 1*325 MW

EEA 1989, 16 months Stein Industry France

Turbine + Generator + Power Transformer and intakes instullation of modules 1,2,3 of Damietta Combined Cycle Power Station 3*145 MW.

EEA 1991, 11 months Gec- Alsthom ( Ratue Co.)

HSGR of Unit 1,5,8 Over Hauling of Cairo South

1994, 12 months Iemsa Italy

Boiler Over Hauling of Unit 1&2 of Kafr El Dawaar Power station 2*110MW

EEA 1989,14 months Skoda

Turbine Major Maintenance of Unit 3&4 of Kafr EL Dawaar Power Station2*110 MW

EEA 1983,6 months Skoda

Turbine Major Maintenance of Unit 5of Abu –Queer Power Station 1*325 MW

EEA 1998 . 6 Months Gec Alsthom

Boiler Annual maintenance of Doha East power station 7*150MW

State Of Kuwait 1 Month for each Turbine

Ministry of Elec. & Water ( MEW ) State Of Kuwait

Turbine Major Maintenance of Units 2,4,5,6,7 Doha West Power Station 8*300 MW

Ministry of Elec. & Water ( MEW ) State Of Kuwait

2 Months for each Turbine Mitsubishi Japan

Boiler Over Hauling of Unit 1,2,3,4&5 of El Suef Power station 5*30MW

EEA 1990, 18 months Skoda

Page 2: ( Turnkey )Projects Constructed By Kahromika industrial projects.pdfMajor ( Turnkey )Projects Constructed By Kahromika Project Name Customer Name Comp. Date And Construction Period

Supply ,Manufacture and erection of Flue And Gas Ducts Of Mahmoudia / Damanhour Combined Cycle Power Station

EEA 1994, 12 months Cimi Montubi

Supply ,Manufacture and erection of Flue And Gas Ducts Of Sidi Krir & Ayoun Mossa Combined Cycle Power Station

EEA 1997, 12 months Cimi Montubi

Mechanical, Piping Boiler Installation and Structural Steel Erection for Sidi Krir 2*235 MW Unit 3&4

Intergen Sidi- Krir Generating Co. 1999, 18 months Bechtle

B.O.P Of El Kurimate Powerstation 2*600 MW

EEA 1995, 24 months Sae-Sadelmi

Boiler Air & Gas Ducts Installation Of El Kurimate Power Station 2*600 MW

EEA 1997, 12 months Cimi Montubi ( Italy )

Ayoun Mossa Power Station( 2*320 MW ) Installation EEA 1998, 20 months Consortium With

Skoda. New Vally Pumping Station In Toshka:- a- Installation of All Major Pumps & Motors. b- Installation of all Other Mechanical & Electrical Equipment . c- Wiring & Insurmentation .

Minstry of Irrigation & Water Resources 24 Months

Arabian International Company

Operation And Maintenanceof All Power and Water Distillation Plants Over Kuwait State .

Ministry Of Electricity And Water - Kuwait

1999, 36 Months Kahromika

Over Hauling Fuel Tanks And Rehabilitation of Fuel System for The Following Power Stations :- a- Tobruk P.S. b- Derna P.S. c- Benghazy P.S. d- Sirte P.S. e- Khoms P.S. f- Tripoli West P.S.

General Electrical Co. Of Libya ( GECOL )

24 Months Kahromika

Alex Coke Handling MIDOR 2000 ( 5 months ) Roberts & Schaefer Co

PERTO RICO Coke HandlingRoberts & Schaefer Co 2001 ( 7 months ) KAHROMIKA

CEMENT FACTORY Misr Cement Benisuef 2001 ( 18 months ) KAHROMIKA

1- NEW VALLY PUMPING STATION IN TOSHKA:- a- Air breaking system b- Emergency bridge

Ministry of Irrigation & water Resorcess 2002 ( 12 months ) Arab International

company ( AIC )

Alex City Center Karfour 2003 ( 6 months ) Steel Tec. Co

Page 3: ( Turnkey )Projects Constructed By Kahromika industrial projects.pdfMajor ( Turnkey )Projects Constructed By Kahromika Project Name Customer Name Comp. Date And Construction Period

Tanks , Mobile Workshops & Containers

Egyptian Drilling Company ( EDC ) 2004 ( 2 months ) Kahromika

Lime Slacking Drum Sugar Co. 2004 ( 45 Days ) Kahromika Tanks , Mobile Workshops & Containers

Egyptian Drilling Company ( EDC )

2005 ( 7 months ) Kahromika

El Noubaria Power Station Egyptian Electrical Authority ( EEA )

2005 ( 3 months ) Kahromika

North Souhag Power Station

Egyptian Electrical Authority ( EEA )

2005 ( 3.5 months ) Kahromika

El Raswa Power Station Egyptian Electrical Authority ( EEA )

2005 ( 2 months ) Kahromika

Tanks , Mobile Workshops & Containers

Egyptian Drilling Company ( EDC )

2006 ( 6 months ) Kahromika

Talkha Power Station 2 * 300 MW

Egyptian Electrical Authority ( EEA ) & Petroget

2006 ( 5 months ) Kahromika

Cairo North power Station 2 * 300 MW

Egyptian Electrical Authority ( EEA ) & Petroget

2006 ( 5 months ) Kahromika

Drier Drum & Cyclone Sugar Co. Belkas 2006 ( 2 months ) Kahromika

Drier Drum & Cyclone Sugar Co. Elnubaria 2006 - 2007 ( 6 months )

Kahromika