- fr om eur - dnw

2
1976 - 2016 40 YEARS GERMAN - DUTCH WIND TUNNELS 30 JUNE 1976 Establishment of Foundation DNW 01 JULY 1976 Start of civil construction work by driving first pile of LLF 01 MARCH 1978 First Advisory Committee Meeting 01 APRIL 1979 Appointment of first operational directors Jürgen Barche and Jacques van Nunen 02 MAY 1979 First time wind-on LLF 27 AUGUST 1980 Ceremonial opening of DNW by Mrs. Smit-Kroes and Dr. Haunschild 31 DECEMBER 1980 Discharge of project directors 01 MARCH 1982 Appointment of August Runge as Deputy Director 1982 First TPS test with Airbus A300 model 01 APRIL 1984 Appointment of Heinrich Weyer as Director 22 OCTOBER 1986 Celebration of ten years of operation of the LLF 01 JANUARY 1988 Appointment of Hans-Ulrich Meier as Director 01 MARCH 1996 Appointment of Cor Joosen as Deputy Director 1992 Automation of Administration 1991 First upgrade of LLF 01 JANUARY 1994 Leasing of NWB by DLR and LST by NLR to DNW for two- year trial 1995 Second upgrade of LLF 01 JANUARY 1996 Integration of LST and NWB into DNW 1996 ISO 9001 certification of LLF 01 JULY 1997 Operation of HST, SST, and ECF (NLR), TWG, RWG, KRG, HDG and KKK (DLR) for a 2.5-year trial 01 APRIL 1998 Appointment of Georg Eitelberg as Director 1998 Acoustic mirror and array systems for localization of acoustic sources 01 JANUARY 2000 DLR and NLR tunnels fully integrated in DNW 2000 New fan drive system NWB. Hexapod for dynamic derivatives operational 2005 Model positioning mechanism MPM of NWB operational 2006 Qualification of KKK for train testing 2007 EU-financed fan drive modernization of LLF SEPTEMBER 2010 Acoustic upgrade NWB finalized SEPTEMBER 2011 First part acoustic upgrade LLF finalized SEPTEMBER 2014 Second part acoustic upgrade LLF finalized 01 JANUARY 2016 NWB transferred to new Business Unit BGK 1976 F 1978 gof DNW by 1980 h 1984 1986 1988 1992 1994 1995 ST SST 1997 rg 1998 2005 01 JANUARY 1976 Installation of project group under project directors Freerk Jaarsma and Manfred Seidel 3 D 1982 1991 2000 f NWB operation tion of 2006 SE 2011 2016 mmittee Meeting 9 of first 1979 nalized 2010 SEPT Seco 2014 30 JUNE 2016 Celebration 40 years DNW 2007 01 APRIL 2012 Appointment of Christophe Hermans as Deputy Director 2012 1996 - from European cooperation to global leadership -

Upload: others

Post on 10-Jan-2022

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: - fr om Eur - DNW

1976 - 2016

40 YEARS G

ERMA

N - D

UTCH

W

IND

TUN

NELS

30 JUN

E 1976Establishm

ent ofFoundation D

NW

01 JULY 1976

Start of civil construction work

by driving first pile of LLF

01 MA

RCH 1978

First Advisory

Comm

ittee Meeting

01 APRIL 1979

Appointm

ent of first operational directors Jürgen Barche and Jacques van N

unen

02 MAY 1979

First time w

ind-on LLF

27 AU

GU

ST 1980

Ceremonial opening of D

NW

by M

rs. Smit-Kroes and D

r. Haunschild

31 DECEM

BER 1980D

ischarge of project directors

01 MA

RCH 1982

Appointm

ent of August

Runge as Deputy D

irector

1982

First TPS test with

Airbus A

300 model

01 APRIL 1984

Appointm

ent of H

einrich Weyer

as Director

22 OCTO

BER 1986Celebration of ten years of operation of the LLF

01 JAN

UARY 1988

Appointm

ent of H

ans-Ulrich M

eier as D

irector

01 MA

RCH 1996

Appointm

ent of Cor Joosen as D

eputy Director

1992A

utomation of A

dministration

1991First upgrade of LLF

01 JAN

UARY 1994

Leasing of NW

B by DLR

and LST by NLR to D

NW

for tw

o- year trial

1995

Second upgrade of LLF

01 JAN

UARY 1996

Integration of LST and N

WB into D

NW

1996ISO

9001 certification of LLF

01 JULY 1997

Operation of H

ST, SST, and ECF (N

LR), TWG

, RWG

, KRG

, HD

G and KKK (D

LR) for a 2.5-year trial

01 APRIL 1998

Appointm

ent of G

eorg Eitelberg as D

irector

1998A

coustic mirror

and array systems

for localization of acoustic sources

01 JAN

UARY 2000

DLR and N

LR tunnels fully integrated in D

NW

2000

New

fan drive system

NW

B. Hexapod for

dynamic derivatives

operational

2005M

odel positioning mechanism

M

PM of N

WB operational

2006

Qualification of

KKK for train testing

2007EU

-financed fan drive m

odernization of LLF

SEPTEMBER 2010

Acoustic upgrade

NW

B finalized

SEPTEMBER 2011

First part acoustic upgrade LLF finalized

SEPTEMBER 2014

Second part acoustic upgrade LLF finalized

01 JAN

UARY 2016

NW

B transferred to new

Business U

nit BGK

1976F

1978

gofD

NW

by

1980

h

19841986

1988

1992

1994

1995

STSST 1997

rg 1998

2005

01 JAN

UARY 1976

Installation of project group under project directors Freerk Jaarsm

a and Manfred Seidel

3D

1982

1991

2000

f NW

B operation

tionof 2006

SE

2011

2016

mm

ittee Meeting

9offirst 1979

nalized2010

SSEPT

Seco

2014

30 JUN

E 2016Celebration

40 years DN

W

2007

01 APRIL 2012

Appointm

ent of Christophe H

ermans as

Deputy D

irector

2012

1996

- from European cooperation to global leadership -

Page 2: - fr om Eur - DNW

19762016

conducted by the aeronautical industry, but the automotive, civil engineering, shipbuilding and sports industries have also benefited from DNW’s capabilities.

THE HISTORY BEHIND ITIn the early seventies of the last century, both NLR and DLR, , were planning to develop a large atmospheric low-speed wind tunnel (the plans were identified as Low Speed wind Tunnel LST 8x6 and Grosser Unterschall-Kanal GUK, respectively). In December 1973, a first exchange of plans took place during a meeting between DLR and NLR.

In September 1974 Prof. Jordan (DFVLR) approached Prof. Gerlach (NLR) at the International Astronautical Congress IAC in Amsterdam with the idea to combine the two projects. Two months later Prof. Gerlach responded by inviting DFVLR to join the NLR large low-speed LST 6x8 project, that just had started. This initiative was supported by a letter of the Netherlands minister of Transport and Public Works, Mr. Westerterp, to his German colleague minister Matthöfer (Bundesministerium für Forschung und Technologie), who responded positively, leading to a bilateral discussion at government level in May 1975.

At this meeting a Technical Working Group was established and tasked to assess the feasibility of developing one facility that would meet the technical requirements of

the two partners featuring multiple test sectionswith high flow quality. For this purpose the NLR pilot wind tunnel PLST

8x6 was modified to accommodate two additional test sections (6x6 and 9.5x9.5).

The NLR board, in August 1975, conditionally agreed to proceed with the cooperative project based on the principles of parity both in funding and operation: the wind tunnel construction should be led by an NLR engineer and the facility was to be located in the Northeastpolder (NL). At the third governmental meeting in September that year, DFVLR agreed to these conditions and put forward a draft agreement for further negotiation in the months to follow. The new foundation was supposed to conduct wind tunnel tests on contract (profit basis) in support of aeronautical projects in Germany, the Netherlands and other countries, making maximum practical use of facilities and capabilities of DFVLR and NLR.

Progress on verifying the technical feasibility of the wind tunnel concept and refining the collaboration principles was good, leading to a first preliminary DNW board meeting in February 1976. There it was decided to assign personnel to a project group becoming responsible for the actual construction of the facility. After signing the cooperation agreement between DFVLR and NLR (on the 28th of June) and the foundation act (on the 30th of June), the first pole for DNW was driven into the ground by the ministers Matthöfer and Westerterp on the first of July 1976. On that day the DNW board held its first formal meeting.

On the 30th of June 1976 the Duits-Nederlandse Windtunnel / Deutsch-Niederländischer Windkanal (German-Dutch wind tunnel DNW) was established as a foundation, only two years after first contacts between the two parent institutes, the Netherlands and German Aerospace Centers NLR and DLR. This milestone, achieved with the support of the German and the Netherlands governments, marks the start of the first joint venture in Europe operating a large aeronautical facility: a European collaboration ‘avant-la-lettre’.

The collaboration has been a continuous success. It started with the building and then operating the Large Low-speed Facility LLF in 1981; today the foundation DNW is responsible for the operation of eleven wind tunnels on five sites.

With support of NLR and DLR, DNW has served automotive (especially in its early years), aerospace industry and the European

research community with advanced experimental services. The Airbus transport aircraft (from A300 to A380, A400M), Embraer E-jet family, Eurofighter and F35 fighter aircraft and NH90 helicopter programs, to name a few, would not have been commercial successes without the high quality and efficient testing in DNW facilities.

GLOBAL LEADERSHIP IN WIND TUNNEL TESTINGDNW is one of Europe’s most advanced and specialized organizations for wind tunnel testing. DNW’s eleven wind tunnels include subsonic, transonic and supersonic facilities, and provide experimental aerodynamic simulation capabilities to the user community at large.

DNW is a non-profit foundation under Dutch law with headquarters in Marknesse in the Netherlands. Its tunnels are situated in a number of locations in the Netherlands and Germany: Marknesse, Amsterdam, Braunschweig, Göttingen and Köln.

DNW operates its own large, low-speed facility and the aeronautical wind tunnels of DLR and NLR. DNW provides solutions for the experimental simulation requirements of aerodynamic research and development projects. These projects can originate in the research community (universities, research establishments or research consortia) or in the course of industrial development of new products. Most of the industrial development projects are

1976 - 2016

40 YEARS GERMAN - DUTCH WIND TUNNELS- from European cooperation to global leadership -

8x6 was modified to accommodate two Celebration of 40 Years Foundation DNW

40 YEARS GERMAN - DUTCH WIND TUNNELS- from European cooperation to global leadership -