Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
1
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Importance and Principles
Infiltration Performance
Selection and Areas of Application
Requirements and Design Considerations
Layout and Detailing
Maintenance and Monitoring
Permeable Concrete Block Paving (pCBP)
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
2
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Relieving Sewage Systems w/ Reduced Runoff
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
3
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Method: Reducing Runoff w/ Permeable CBP
• Absorption of Precipitation
With Permeable Surface
• Temporary Retention of Infiltrated Rainwater
With Permeable Pavement Structure
• Partial Infiltration of Seepage Water
Through the Formation Level depending on the Permeability of the Soil
• Restricted Recharge of the Remaining Runoff
With Connected Drainage Facilities
• Collecting the Seepage Water
With Impermeable Membranes on the Surface of the Formation Level
• Collecting the Remaining Runoff
For further Use
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
4
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Retention
Retention
Infiltration
Infiltration
Restricted Discharge
Principle: Reducing Runoff w/ Permeable CBP
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
5
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Reducing Runoff as a Component of SUDS
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
6
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Research: Permeability Reduction by Clogging
0
10
20
30
40
50
60
70
80
90
100
0.02 0.063 0.2 0.63 2 0.6 20
particle size d in mm
scre
en p
assi
ng (
<d
in m
ass-
%)
silt sand gravel
Upper 20 mm
Below 20 mm
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
7
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Results: Long-term Performance (Aging)
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
8
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Conclusions: Reduced Runoff Coefficient
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
9
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
• Determination of Possible Areas of application according to Traffic Load and Protection of Soil and Groundwater
• Judging the Soil according to Load Bearing Capacity and Permeability
• Designing the Road Construction according to Load Bearing Capacity and Permeability
• Selecting the Materials according to Load Bearing Capacity and Permeability
• Selecting the Permeable Paving Blocks according to Aesthetics and Infiltration Performance
• Choosing and Designing the Connected Drainage Facility
• Determination of Suitable Methods for Monitoring the Infiltration Performance
• Determination of Suitable Methods to Maintain the Infiltration Performance
Preconditions
General Requirements: No Affection of Soil and Ground Water Permanent Road Operation
(Damage-free Construction) Permanent Infiltration
(Proper Reduction of Runoff) Proper and Regular Drained Surface
(Safe Road)
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
10
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Areas of ApplicationTraffic area Use
Roads Residential Roads, Access Roads, Service Roads
Parking Areas Parking Areas occasional in use for Truck and Bus Traffic,Parking Areas constantly in use for Car Traffic and minor Truck/Bus Traffic
Industrial Traffic Areas
Industrial Roads with minor Traffic, Industrial Parking Areas,Container Hard Standings
Special Traffic Areas
Track and Rail Areas of Public Transport,Airbase Aprons and Parking Areas for Planes
Other Traffic Areas
Platforms for Public Transport, Farm and Forestry Roads,Emergency Escape Ramps
Residential/ Private Areas
Cycle Ways and Footpaths, Real Property Entries,Landscape and Garden Areas
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
11
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Areas of Application
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
12
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Areas of Application
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
13
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Determination of Construction and Thickness according to:• Frost Susceptibility of the Soil (→ Permeability)• Local Climate Conditions• Structural Performance of Aggregates and Base Courses• Design Traffic Load
Performance Criteria:Criteria:• Complete and Permanent Infiltration of a Standard Rainfall
Measure
Required Rainfall Measure (i.e. In the UK):• BRE Digest 365 (Soakaway design):
M5-10 = 180 l/(sha) eq. 1,08 mm/min• Required permeability of the soil:
kukf/2 = 3.610-5 m/s
Design Methods
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
14
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Criteria:• Sufficient Permeability to Absorb the Standard Rainfall
Measure• Required Permeability according to Aging:
3.610-4 m/s
• According to Percentage of Openings:
[m/s]% in openings of percentage
100kfk u
Mineral Aggregates:Openings/Bedding:
Crushed Gravel 1/3 to 2/5 mmBase course:
Modified Type 3 Material (Fines < 3 M.-%)
Performance Criteria
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
15
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Pavement Design with Permeable CBP
Base Course Thickness: Depending on Soil Permeability
Materials: Permeability according to Design-Rainfall
Permeable Paving: Depending on Traffic Load
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
16
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Pavement Design with Permeable CBP
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
17
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
• Suitability tests of the materials
• Suitability tests of the soil
• On-site acceptance tests
Type of Testing:
Lab Tests
Open-End-Test
Infiltration Test
Monitoring
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
18
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Monitoring: Testing the Subgrade
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
19
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Monitoring: Testing the Base Course
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
20
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Monitoring: Testing the Surface
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
21
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Monitoring: Testing the Surface
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
22
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Control of Pavement Condition and Function
• Assessment of Structural and Drainage Performance
Control of Joints and Joint Filling
• Completely Filled Joints Guarantee Horizontal Load Transmission!
Road Cleaning
• Mechanical Cleaning only 3 Months after Completion!
• Periodical Cleaning Afterwards can not Replace an Additional Drainage!
• In Practice Maintenance is Expensive!
Maintenance
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
23
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
The Overall Costs of Permeable Road Constructions are related to Conventional Road Constructions:
•Regularly the Same with Good Soil Conditions
•A little Higher with Bad Soil Conditions
Detailed Costs in Comparison to Conventional Road Constructions:
•Permeable Paving Blocks: Higher
•Base Courses: Same with Good Soil Conditions
Higher with Bad Soil Conditions
•Drainage Facilities: Lower
Costs
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
24
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Origin and Types of Overstress of the Pavement:
• Premature Exhaustion
• Sudden Local Collapse
• Long-ranging Permanent Deformation
Failures, Defects, Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
25
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
26
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
27
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
28
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
29
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
30
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
31
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
32
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
33
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Failures, Defects and Damages
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
34
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Quality Assessment
Purpose: Prevention of Constructional Damages
Method: Quality Improvement w/ Continuous Job-site Monitoring
Goal: • Document the technical and legal precise state of the art.
• Raise the standard of specification balanced for all parties.
• Improve the technical qualification of designers, specifiers, contractors and manufacturers.
• Continuously review the job-site construction work.
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
35
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Quality Assessment – Rectification Costs
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
36
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Quality Assessment – Methods
Documentation of the whole Sequence of Construction by
• Elaboration of Daily Work Step Checklists
(Contractor with Expert)
• Supervision of Documents by Integrity, Plausibility, Conformity
(Inspector of the Contractor)
• Monitoring of Documents and Work Progress
(External Expert)
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
37
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Quality Assessment
Checklists include i.e.:
• Incoming Controls of Building Materials
• Controls of Installation
• Controls of Pavement
Dr. Sönke Borgwardt
Dr. Soenke BorgwardtBuero BWB NorderstedtFehmarnstrasse 37D-22846 NorderstedtTlf. +49 (0)40 522 56 75Fax +49 (0)40 53 53 06 [email protected]
38
Water Permeable Pavements
Presentation SEPT-Workshop 2011 in Dresden
Accompanying Control Tests for Internal Controls, i.e.
• Compaction
• Difference in Elevation
• Difference in Evenness
• Joint Widths
Quality Assessment – Methods